- 756 - SECTION 917 -- RECONSTRUCTION OF MANHOLES AND ADJUSTING MANHOLES TO GRADE
917.02 Material Requirements
Brick mortar shall be 1 part cement, 2 parts sand, and water as necessary to insure brick can be set at designed spacing.
916.03 when concrete is used.
3.Bricks shall be approved by the Engineer. The bricks shall be bonded in mortar. All brick must be wetted before being placed. All joints shall be completely filled with mortar and shall be 3/8 inch (9 mm) thick.
4.The Contractor shall provide and set all cast iron covers, rings, frames, flanges, and other items as described in the contract.
918.03 Construction Methods
1.The Contractor shall remove the manhole cover and the top cast iron flange.
2.The Contractor shall demolish the manhole, inlet, or junction box walls to at least 40 inches (1 m) below the finished grade elevation.
3.The Contractor shall plug all opening with concrete pipe plugs. 4. The Contractor shall demolish th e floor of the structure. No piece shall be longer than 40 inches (1 m) in any dimension.
5.a. The Contractor shall fill the opening created by the demolition with granular material to within 40 inches (1 m) of the finished grade elevation.
b.The Contractor shall fill the remaining hole with soil and compact to the same stiff ness as surrounding soils.
6.Materials which are removed and not salvaged shall be disposed of in accordance with requirements in Section 203. Source: Nebraska Standard Specifications for Highway Construction, 2017 Edition. Pages 790–790 of 1,048.