SECTION 160 – PRICE ADJUSTMENTS

160.01 Description

This Section describes the requirements for price adjustments for fuel and asphalt usage.

160.02 Materials

(Intentionally Blank)

160.03 Procedure

160.03.01 Fuel Price Adjustment

The Department will make monthly price adjustments for fuel usage for Items listed in Table 160.03.01-1. The Department will calculate fuel price adjustments based on the monthly pay quantities of listed Items using the fuel usage factors listed in Table 160.03.01-1. Price adjustments may result in an increased payment to the Contractor for increases in the price index and may result in a reduction in payment for decreases in the price index. If the as-built quantity of an Item listed in Table 160.03.01-1 differs from the sum of the quantities in the monthly Estimates and the as -built quantity cannot be readily distributed among the months that the Item liste d in Table 160.03.01-1 was constructed, then the Department will determine fuel price adjustment by distributing the difference in the same proportion as the Item’s monthly Estimate quantity is to the total of the Item’s monthly estimates. Table 160.03.01-1 Fuel Price Adjustments Items Fuel Usage Factor EXCAVATION, UNCLASSIFIED 0.50 Gallons per Cubic Yard EXCAVATION, REGULATED MATERIAL 0.50 Gallons per Cubic Yard EXCAVATION, ACID PRODUCING SOIL 0.50 Gallons per Cubic Yard REMOVAL OF PAVEMENT 0.25 Gallons per Square Yard HMA MILLING, 3" OR LESS 0.25 Gallons per Square Yard HMA MILLING, MORE THAN 3" TO 6" 0.25 Gallons per Square Yard CONCRETE MILLING, 0.25 Gallons per Square Yard HMA PROFILE MILLING 0.25 Gallons per Square Yard Table 160.03.01-1 Fuel Price Adjustments Items Fuel Usage Factor BREAKING PAVEMENT 0.25 Gallons per Square Yard RUBBLIZATION 0.25 Gallons per Square Yard SUBBASE 1.00 Gallon per Cubic Yard I-___ SOIL AGGREGATE 1.00 Gallon per Cubic Yard SOIL AGGREGATE BASE COURSE, ___ " THICK 1.00 Gallon per Cubic Yard SOIL AGGREGATE BASE COURSE, VARIABLE THICKNESS 1.00 Gallon per Cubic Yard DENSE-GRADED AGGREGATE BASE COURSE, ___ " THICK 1.00 Gallon per Cubic Yard DENSE-GRADED AGGREGATE BASE COURSE, VARIABLE THICKNESS 1.00 Gallon per Cubic Yard CONCRETE BASE COURSE, ___ " THICK 0.25 Gallons per Square Yard CONCRETE BASE COURSE, REINFORCED ___ " THICK 0.25 Gallons per Square Yard ASPHALT-STABILIZED DRAINAGE COURSE 2.50 Gallons per Ton OPEN-GRADED ___ FRICTION COURSE 2.50 Gallons per Ton HOT MIX ASPHALT ___ ___ ___ SURFACE COURSE 2.50 Gallons per Ton HOT MIX ASPHALT ___ ___ ___ INTERMEDIATE COURSE 2.50 Gallons per Ton HOT MIX ASPHALT ___ ___ ___ BASE COURSE 2.50 Gallons per Ton MODIFIED OPEN-GRADED ___ FRICTION COURSE ___ 2.50 Gallons per Ton ULTRA-THIN FRICTION COURSE 2.50 Gallons per Ton STONE MATRIX ASPHALT ___ SURFACE COURSE 2.50 Gallons per Ton HIGH PERFORMANCE THIN OVERLAY 2.50 Gallons per Ton BINDER RICH INTERMEDIATE COURSE 2.50 Gallons per Ton BRIDGE DECK WATERPROOFING SURFACE COURSE 2.50 Gallons per Ton NON-VEGETATIVE SURFACE, HOT MIX ASPHALT 2.50 Gallons per Ton COLOR-COATED NON-VEGETATIVE SURFACE, HOT MIX ASPHALT 2.50 Gallons per Ton CONCRETE SURFACE COURSE, ___ " THICK 0.25 Gallons per Square Yard DIAMOND GRINDING OF CONCRETE SURFACE COURSE 0.25 Gallons per Square Yard DIAMOND GRINDING EXISTING CONCRETE PAVEMENT 0.25 Gallons per Square Yard CONCRETE BRIDGE APPROACH 0.50 Gallons per Cubic Yard CONCRETE CULVERT 1.00 Gallon per Cubic Yard CONCRETE FOOTING 1.00 Gallon per Cubic Yard CONCRETE WING WALL 1.00 Gallon per Cubic Yard CONCRETE PIER COLUMN PROTECTION, HPC 1.00 Gallon per Cubic Yard CONCRETE PIER COLUMNS AND CAP 1.00 Gallon per Cubic Yard CONCRETE ABUTMENT WALL 1.00 Gallon per Cubic Yard CONCRETE PIER SHAFT 1.00 Gallon per Cubic Yard CONCRETE PEDESTRIAN BRIDGE 1.00 Gallon per Cubic Yard CONCRETE BRIDGE DECK 1.00 Gallon per Cubic Yard CONCRETE BRIDGE DECK, HPC 1.00 Gallon per Cubic Yard CONCRETE BRIDGE SIDEWALK 1.00 Gallon per Cubic Yard CONCRETE BRIDGE SIDEWALK HPC 1.00 Gallon per Cubic Yard CONCRETE BRIDGE PARAPET 1.00 Gallon per Cubic Yard CONCRETE BRIDGE PARAPET HPC 1.00 Gallon per Cubic Yard CAST-IN-PLACE CONCRETE PILES, DRIVEN ___ " DIAMETER 1.00 Gallon per Cubic Yard RETAINING WALL, LOCATION NO.___ ___ 0.10 Gallon per Square Foot If an item listed in Table 160.03.01 -1 has a payment unit which differs from that listed in Table 160.03.01 -1, the Department will apply an appropriate conversion factor to determine the number of gallons of fuel used. The Department will calculate fuel price adjustment on a monthly basis using the following formula: F = (MF − BF)  G Where: F = Fuel Price Adjustment MF = Monthly Fuel Price Index for work performed from the first day of the month to the last day of the month for the month prior to the estimate cutoff date. BF = Basic Fuel Price Index G = Gallons of Fuel for Price Adjustment The Department will post the monthly fuel price index every month on the Department’s website: http://www.state.nj.us/transportation/business/trnsport/PriceIndex.shtm. The basic fuel price index is the previous month’s fuel price index before receipt of bids. The Department will use the fuel price index for the month before the regular monthly estimate cutoff date as the Monthly Fuel Price Index for work performed in the previous calendar month. If the Monthly Fuel Price Index increases by 50 percent or more over the Basic Fuel Price Index, do not perform any work involving Items listed in Table 160.03.01-1 without written approval from the RE.

160.03.02 Asphalt Price Adjustment

The Department will make monthly price adjustments for asphalt binder usage. Th e Department will calculate asphalt price adjustments based on the quantities of Items containing asphalt binder constructed during a given month. Price adjustments may result in an increased payment to the Contractor for increases in the price index and may result in a reduction in payment for decreases in the price index. The Department will calculate the asphalt price adjustment by the following formula: A = (MA − BA)  T Where: A = Asphalt Price Adjustment MA = Monthly Asphalt Price Index for work performed from the first day of the month to the last day of the month for the month prior to the estimate cutoff date. BA = Basic Asphalt Price Index T = Tons of New Asphalt Binder1

1.The Department will determine the weight of asphalt binder for price adjustment by multiplying the percentage of new asphalt binder in the approved job mix formula by the weight of the item containing asphalt binder. If a Hot Mix Asphalt Item has a payment unit other than ton, the Department will apply an appropriate conversion factor to determine the number of tons of asphalt binder used. For Tack Coat, Prime Coat , MICRO SURFACING EMULSION , SLURRY SEAL EMULSION , and FOG SEAL TREATMENT, the Department will calculate the weight of asphalt as follows: T= G  C  0.00428 C = Petroleum content of the product Use 100% for Tack Coat 64-22 and Tack Coat 64E-22 Use 60% for Polymer Modified Tack Coat, and all other emulsified asphalts G = Gallons furnished The constant 0.00428 is derived from the conversion factor of tons per gallon using 8.345 lbs/gallon for water and a factor of 1.025 for the specific gravity of asphalt binder. The Department will not calculate an asphalt price adjustment for FOG SEAL STRIP. The monthly asphalt price index, as determined by the Department, will be the average of quotations from suppliers serving the area in which the Project is located, and will be determined by the Department each month. The Department will post the monthly asphalt price index every month on the Department’s website

Get an email when 160 changes

New Jersey revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Road and Bridge Construction, 2019 (rev. 2022-12-21) Edition. Pages 149–151 of 651. View official source ↗

Ask about this section

Scoped to New Jersey 2019 Standard Specifications for Road & Bridge Construction, Section 160 — Price Adjustments. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.