697-1 02
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3
697-2 MATERIALS. None specified.
697-3 CONSTRUCTION DETAILS. None specified.
697-4 METHOD OF MEASUREMENT. The unit price shown in the proposal for this item will be
considered as the unit price bid and shall not be altered in any manner. Should the amount shown be altered, the figure entered will be disregarded and the original unit price will be used to dete rmine the total amount bid for the contract.
697-5 BASIS OF PAYMENT. All work to be paid under the FCP item must receive prior authorization
in conformance with §104 -02 Changes, Contingencies, Extra Work and Deductions. Disputed work, force account work, work associated with §104 -10 Value Engineering Change Proposals, or payments for time-related provisions are not eligible for FCP item payment. FCP item payments will be determined from the quantities and unit prices of eligible work that have been completed. Work for which FCP item payments are processed will be paid in accordance with the specifications governing the work. Prior to processing the final agreement, the FCP item payments will be reconciled through an Order - on-Contract, such that the amount of FCP item payments is converted to the corresponding quantities of the pertinent contract pay items. When the amount of F CP item payments is transferred to the appropriate items, the remaining amount of FCP funds will be deleted. Payment will be made under: Item No. Item Pay Unit 697.03 Field Change Payment (FCP) Dollars -Cents SECTION 698 - PRICE ADJUSTMENTS (Last Revised September, 20 21)
698-1 01
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 698-1 DESCRIPTION. This section will provide for additional compensation to the Contractor for increases, or repayment by the Contractor for decreases, in the price of asphalt, fuel, or steel/iron products.
698-1.01 Asphalt Price Adjustment. This item will enable the Department to make price adjustments to
account for changes in asphalt prices. Price adjustments will be made for eligible work listed in the contract proposal.
698-1.02 Fuel Price Adjustment. This item will enable the Department to make price adjustments to
account for changes in fuel prices. Price adjustments will be made for eligible work listed in the contract proposal.
698-1.03 Steel/Iron Price Adjustment. This item will enable the Department to make price adjustments
to account for changes in steel/iron product prices for materials eligible and identified by the Contractor which will be permanently incorporated into the work.
698-2 MATERIALS. None specified.
698-3 CONSTRUCTION DETAILS. No adjustment will be provided for any new or additional work
paid for by force account. Additional quantities of existing contract pay items at original bid prices will be considered eligible work. Additional work added by agreed price will be considered eligible work. Work performed by the Contractor at its own expense will not be eligible for price adjustment. The monthly average asphalt prices, monthly average fuel prices, steel cost basis and steel index values will be posted in the Engineering Bulletin entitled Fuel, Asphalt and Steel Price Adjustments. If eligible items are installed after the contract completion date, when an extension of time without the assessment of engineering charges and/or liquidated damages is approved, the monthly average posted price or monthly steel index value will be used to compute pri ce adjustments. If eligible items are installed after the contract completion date, when an extension of time was approved with the assessment of engineering charges and/or liquidated damages, the monthly average posted price or monthly steel index in effect on the last c ontract completion date without the assessment of engineering charges and/or liquidated damages, or the value for the month of installation/purchase, whichever is less, will be used to compute price adjustments.
698-3.01 Asphalt Price Adjustment. The asphalt price adjustment will be based solely on the price
changes for asphalt as determined by the formulas below. No adjustment will be made if the monthly average posted price is within $15.00 of the asphalt index price. No consideration will be g iven to the situation where an individual supplier's price exceeds the monthly average posted price.
698-3 02
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3
698-3.02 Fuel Price Adjustment. The fuel price adjustment will be based solely on the price changes for
fuel as determined by the formulas below. No adjustment will be made if the monthly average posted price is within $0.10 per gallon of the fuel index price. No consideration will be given to the situation where an individual supplier's price exceeds the monthly average posted price,
698-3.03 Steel/Iron Price Adjustment. Within 30 calendar days after award, the Contractor shall
provide the Engineer with a list of materials to which the Contractor opts to apply the steel price adjustment, identifying the materials by groups of similar material content within a core (3 digi t) contract pay item (e.g. 564 Structural Steel or 603.05xxxx Corrugated Steel Pipe ). For each material listed, the Contractor shall also identify the parties whose relationship establishes the invoice date. If the t wo parties are known, they shall be identified by name. If the two parties are not known, they shall be identified by role (Contractor, Subcontractor, Material Supplier, Fabricator, Manufacturer, Mill, etc.). Different parties may be identified for indiv idual or groups of contract pay items for the purposes of establishing an invoice date. If the Contractor does not provide a list of materials to which to apply the steel price adjustment, no steel price adjustment will be made.
698-3 03
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 If the percentage change for a given month does not exceed 5% plus or minus, from the benchmark steel index, no adjustments will be made for materials invoiced that month. For lump sum or each items that are assembled from numerous components, such as overhead sign structures, the percentage change will be determined for the assembled contract pay item using the month that the largest value of materials were invoiced. For unit price items such as guiderail that are assembled from numerous components, the percentage change will be determined for a given quantity of the contract pay item using the month that the largest value of component material s for that quantity of the contract pay item were invoiced. The weight of the steel and/or iron shall exclude minor appurtenances individually weighing less than 5 lbs (i.e., nuts, bolts, washers, etc.). Precast or prestressed concrete items shall have total reinforcing steel weight listed on the approved shop dra wings. The following sources shall be used, in declining order of precedence, to determine the weight of steel/iron: Department established weights of steel/iron by contract pay item per pay unit; approved shop drawings; verified shipping documents; contr act documents; Standard Sheets; industry standards (i.e., AISC Manual of Steel Construction, AWWA Standards, etc.); and manufacturer’s data.
698-4 01
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 month(s) of invoice, the source used to determine the weight, and if requested by the Engineer, copies of invoices to verify the month of invoice.
698-4 Method of Measurement.
698-4.01 Asphalt Price Adjustment. Asphalt price adjustments will be measured on a Dollar Cents
basis.
698-4.02 Fuel Price Adjustment. Fuel price adjustments will be measured on a Dollar Cents basis.
698-4.03 Steel/Iron Price Adjustment. Steel/Iron price adjustments will be measured on a Dollar Cents
basis.
698-5 BASIS OF PAYMENT. The unit price shown in the itemized proposal will be considered the unit
price bid, although actual payment will be calculated based on changes in posted material prices. Should the amount shown be altered, the altered figures will be disregarded and th e original price will be used to determine the total contract bid amount. If price adjustments are based on estimated material quantities, and a revision to the estimated material quantity is made in a subsequent or final estimate, an appropriate addition or deduction will be made to the price adjustment previously calculated. T he addition or deduction will be based on the adjustment factors initially used to calculate the price adjustment. If the installation dates of the revised material quantity cannot be determined, the addition or deduction will be based on the adjustment fa ctors in effect during the last month in which any portion of the material quantity was installed.
698-5.01 Asphalt Price Adjustment. The asphalt price adjustment will be based on the monthly
average posted price in effect at the time the work is completed, calculated using the price adjustment formula described above.
698-5 02
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Section 600 STANDARD SPECIFICATIONS (USC) January 1, 202 4 VOLUME 3 698-5.02 Fuel Price Adjustment. The fuel price adjustment will be based on the monthly average posted price in effect at the time the work is completed, calculated using the price adjustment formula described above.
698-5.03 Steel/Iron Price Adjustment. The steel/iron price adjustment will be based on the monthly
steel index in effect at the time of invoice between the two parties previously identified by the Contractor, calculated using the price adjustment formula described above. Payment will be made under: Item No. Item Pay Unit 698.04 Asphalt Price Adjustment Dollars Cents 698.05 Fuel Price Adjustment Dollars Cents 698.06 Steel/Iron Price Adjustment Dollars Cents SECTION 699 - MOBILIZATION
699-1 DESCRIPTION. Under this work the Contractor shall provide necessary bonds, insurance, and
prefinancing and shall set up his necessary general plant, including shops, storage areas, office and such sanitary and other facilities as are required by local or state law or regulation.
699-2 MATERIALS. Such materials as required for mobilization and that are not to be part of the
completed contract shall be as determined by the Contractor, except that they shall conform to any pertinent local or State Law, regulation or code.
699-3 CONSTRUCTION DETAILS. The work required to provide the above facilities and service for
mobilization shall be done in a safe and workmanlike manner and shall conform with any pertinent local or State Law, regulation or code. Good housekeeping consistent with safety shall be m aintained.
699-4 METHOD OF MEASUREMENT. Payment for mobilization will be made on a lump sum basis.
699-5 BASIS OF PAYMENT. The amount bid for mobilization shall not exceed four percent (4%) of
the total contract bid price excluding the bid price for mobilization. Should the bidder exceed the foregoing four percent (4%), the Department will make the necessary adjustment to de termine the total amount bid based on the arithmetically correct proposal. The amount bid shall include the furnishing and maintaining of services and facilities noted under §699 -1 DESCRIPTION, to the extent and at the time the Contractor deems them necessary for his operations, consistent with the requirements of this work and t he respective contract. The amount bid shall be payable to the Contractor with the first contract payment made for other contract work. Payment will be made under: Item No. Item Pay Unit 699.040001 Mob ilization Lump Sum