SECTION 201 – CLEARING SITE

201.01 Description

This Section describes the requirements for clearing site; clearing site f or bridges and other structures, removing underground storage tanks, disposing and recycling of contaminated soil, installing monitoring wells, sealing abandoned wells, demolishing buildings, removal of asbestos, and temporary shielding.

201.02 Materials

Provide materials as specified: Soil Aggregate (I-14) ................................ ................................ ................................ ................................ ... 901.11 Concrete ................................ ................................ ................................ ................................ ...................... 903.03 Caution Fence ................................ ................................ ................................ ................................ .......... 913.02.02 Polyethylene Sheeting ................................ ................................ ................................ ................................ .. 919.12 Provide a commercially available basement waterproofing.

201.03 Construction

201.03.01 Clearing Site

A.Preparation. Construct SESC measures, as specified in 158.03.02, before clearing site.
B.Clearing and Grubbing. Before beginning excavation or embankment construction, clear the site within the limits of construction. Clear the ground surface of vegetation (trees of various caliper, brush, weeds, roots, matted leaves), small structures not shown on the Plans for demolition, debris, and other objectionabl e material where its existing position conflicts with the limits of construction. In cut sections, grub out tree stumps within the limits of the total cut area. In fill sections, the Contractor may leave tree stumps extending less than 1 foot above the original ground surface in those areas where the proposed subgrade, or proposed finished grade in non-pavement sections, is greater than 3 1/2 feet above the original ground surface. Grub out tree stumps that lie within 5 feet horizontally or vertically from any proposed structure, pipe, or duct. Do not remove trees, shrubs, and other landscape features that do not interfere with the Work or are designated for preservation. Prevent damage or injury to existing trees, plants, and other vegetation that are to remain within or adjacent to the Project Limits. Backfill and compact depressions in excavation areas that lie below the finished subgrade to finished subgrade using the directed method as specified in 203.03.02.B.3. Clear slopes in areas of cuts, embankments, ditches, channels, waterbodies, and structures, both old and new, of brush, hedges, weeds, heavy vegetation, and other objectionable material or growth. Clear to a maximum of 8 fee t beyond the top of slopes of roadway excavation and 5 feet beyond the top of slopes of ditches and channels, except do not clear outside ROW. Conduct clearing and removal activities in areas identified as containing regulated material according to the pre-excavation plans as specified in 202.03.05.1. Dispose of material and debris as specified in 201.03.01.H.
C.Mailbox and Sign Relocation. Remove and reset residential and commercial mailboxes at locations acceptable to the owners and according to United States Postal Service (USPS) requirements. Notify the USPS before relocating USPS mailboxes. Remove local street and road signs and reset at locations and in the manner acceptable to local authorities. Ensure that Tourist Oriented Directional Signs and logo signs remain visible to motorists during and after stages of construction. Remove from the immediate work site and safely store existing signs that are to be reset.
D.Plugging Pipe. Seal abandoned pipes and conduits using concrete. Construct the plugs to a depth equal to the diameter of the pipe or conduit, or 2 feet, whichever is less.
E.Removing Pipe, Inlets, and Manholes. Excavate for the removal of existing pipe, inlets, and manholes as specified in 601.03.01.B. Backfill with excavated material and compact using the directed method as specified in

203.03.02 B.3. The RE may require use of the density control compaction method as specified in 203.03.02.B.4,

except that the RE may increase the frequency of measurements. Reuse removed drainage structures as specified in 202.03.03.C.1. Unless designated for resetting on the Project, dispose of inlet and manhole castings as specified in 201.03.01.H.

F.Removing Sidewalks, Driveways, Curbs, and Gutters. Sawcut full depth at the limits of removal. Remove sidewalks, driveways, vertical curbs, sloping curbs, barrier curbs, and gutters, designated for removal and reuse as specified in 202.03.03.C. Obtain RE approval of methods to remove barrier curb before beginning work. Repair damage to adjacent pavement courses caused by removal operations.
G.Removing Electrical Material and Equipment. Remove existing foundations and junction boxes that are abandoned under the Contract to a minimum depth of 2 feet below the finished grade . Remove foundations or junction boxes that interfere with the installation of a new system and backfill as specified in 203.03.02.B.3. Reuse concrete from foundations and junction boxes as specified in 202.03.03.C.1. Dispose of castings as specified in

201.03.01 H.

Remove other electrical material and equipment that a re designated for removal, and dispose of as specified in

201.03.01 H. Obtain RE approval of methods of removal , and ensure remaining electrical equipment is left

undamaged. Salvage and deliver to the Department removed, above-ground electrical material as required.

H.Disposal of Materials. Dispose of or recycle removed materials and debris according to Solid Waste Management Act (N.J.S.A. 13:1E-1) and N.J.A.C 7:26 et seq. and according to the solid waste management plan developed by the solid waste management district of origin. Submit proper documentation from the disposal facility to the RE and the county of origin within 15 days of acceptance at the disposal facility.

201.03.02 Clearing Site, Bridge and Clearing Site, Structure

Submit a demolition plan detailing the work area, methods, and equipment to be used to the RE for approval 30 days before demolition operations. Clear site within work area as specified in 201.03.01. Remove the substructures of existing structures to at least 3 feet below the natural stream bottom, and remove those parts outside of the stream to at least 2 feet below natural ground surface. Where such portions of existing structures lie wholly or in part within the limits of a new structure, remove them to accommodat e the construction of the proposed structure. Only the f ollowing equipment is permitted for the work:

1.Pneumatic or Electric Equivalent Hand Operated Hammers.
a.When demolishing concrete not closer than 6 inches to structural members: hammers weighing no more than 90 pounds (exclusive of bit), equipped only with chisel point bits.
b.When demolishing concrete within 6 inches of structural members: h ammers weighing no more than 30 pounds (exclusive of bit).
2.Sawcutters.
a.When cutting concrete within 6 inches of structural members: concrete cutters and concrete saws. While using water in the cutting operation, provide shielding beneath the cutting operation to prevent water leakage. Continuously collect slurry and dispose of as specified in 201.03.01.H. Ensure that the slurry does not enter the structure or highway drainage system.
3.Hydraulic Breakers. Ram-hoe type breakers, hydraulic breakers, and demolition shears may be used with the following restrictions:
a.Submit required data to the RE for Department’s analysis of stresses induced to the girders.
b.Delineate the centerline and limits of the top flange of girders before the equipment operation.
c.Do not use equipment within 6 inches of the delineated flanges.
d.Do not pull or twist the reinforcement steel.
4.Hydraulic Splitters. Hydraulic splitters.
5.Other Equipment. Obtain RE approval before use. When removing creosote timbers in waterbodies , surround the removal area with absorbent booms in addition to SESC measures. Dispose of absorbent booms as specified in 201.03.01.H. Dismantle, with minimal damage, steel bridges and wood bridges that are to be salvaged for the Department as specified in the Special Provisions. Match-mark steel members unless such match-marking is waived by the Department. Remove salvageable material in sections or pieces, and store at specified places within the Project Limits. Before placing the new work, complete blasting or other operations necessary for the removal of an existing bridge or structure that may damage new construction. Prevent damage to existing structures designated to remain. If portion s of the existing structure scheduled to remain are damaged by removal activities, submit a repair plan to the RE for approval. Repair damaged portions of existing structures according to the approved repair plan.

201.03.03 Clearing Site, Tank Removal

Refer to the Special Provisions for the locations and types of underground storage tanks to be removed. Excavate test pits as necessary to confirm locations, types, and sizes of underground storage tanks as specified in 202.03.02. Use information gathered from the test pits to complete required NJDEP forms. Ensure each underground storage tank identified within the project area is closed and removed consistent with the closure requirements of N.J.A.C 7:14B, the American Petroleum Institute Standard and NJDEP Technical Guidance Documents. Upon completion of the tank removal operation, submit a Remedial Action Report per parcel pursuant to N.J.A.C 7:26E. Hire a license site remedial professional (LSRP) to oversee the removal, processing NJDEP forms and reporting. Submit copies of the Remedial Action Reports to the RE, the Bureau of Landscape Architecture and Environmental Solutions, and the Department’s environ mental consultant. Remove and dispose of underground storage tanks and piping systems, sample and analyze soils and water, recycle or dispose of contaminated soils, and install and seal monitoring wells according to Federal, State, and local laws, rules, and regulations, and the following:

1.Permits and Approvals. Submit documents to obtain the permits and approvals necessary for this work. Register unregistered tanks that are regulated by N.J.A.C 7:14B and NJDEP Technical Guidance Documents. Submit the “Underground Storage Tank Facility Questionnaire” and “Notice of Intent To Close An UST System” to the RE for review before submitting it to the NJDEP. Obtain NJDEP approval before commencing removal operations. Notify the RE 45 days before the removal of underground tanks to allow the Department to obtain the EPA Identification Number (EPA ID#) for the tank contents. Ensure that the waste disposal or recycling facility planned for receipt of the material is properly permitted for acceptance. Submit a copy of the facility permit to the RE 7 days before disposal or recycling.
2.Removal Operations. Monitor the site with an explosimeter to indicate the presence and concentration of flammable vapors and gas. If this test reveals that unsafe working conditions exist, notify the RE and immediately suspend removal operations until it is determined that conditions are acceptable for resuming work. Remove liquids and sludge contained in the underground storage tanks and piping before removing the tanks and associated piping systems from the ground, and dispose of the removed contents according to Federal, State, and local laws, rules, and regulations . Avoid leakage from the tanks onto the surrounding soil by properly pumping the contents of the tanks into permitted transport vehicles. If leakage or spillage occurs, immediately notify the RE. Notify the NJ DEP’s Environmental Action Hotline and the county health department within 15 minutes. Remove soil containing free and residual product that is present during the removal of the tank to the extent practical. Perform tank removal operations with the least disturbance to the soil surrounding the tanks. Erect caution fence around excavations. Ensure tanks are free of vapors before transporting off -site. Dispose of excavated tanks and piping systems as specified in 201.03.01.H. If there is evidence of discharge in the excavated hole, notify the RE and contact the NJDEP’s Environmental Action Hotline. Excavate and dispose of petroleum contaminated soil from the limits of the tank removal. Perform field tests to determine the extent of petroleum contaminated soils according to NJDEP requirements and to determine if additional soils must be excavated. Conduct post excavation soil sampling and analysis according to NJDEP’s N.J.A.C 7:14B and NJDEP Fi eld Sampling Procedures Manual Provide a copy of sampling log, chain of custody form, and analytical report to the RE. Before backfilling, remove and dispose of contaminated water not associated with ground water. If directed, immediately backfill the excavated hole and obtain documentation for the quality of the fill. In addition, provide to the RE a certification stating that it is virgin material from a commercial or noncommercial source or decontaminated recycled soil. Backfill the excavation as specified in 201.03.07.5 but use certified clean fill as noted above.
3.Temporarily Storing Excavated Soil . Temporarily store excavated soil in stockpiles as specified in

202.03.03 B. Construct stockpiles on polyethylene sheeting. Locate stockpiles where excavation equipment

can place the soil from the excavation directly onto a stockpile. Segregate material of differing types and degrees of contamination to prevent cross-contamination of materials. Cover stockpiles with polyethylen e sheeting of the same thickness as the underlying polyethylene sheeting. Secure cover polyethylene sheeting in place at all times. Overlap joints in the cover polyethylene sheeting a minimum of 12 inches, and secure the joints. Maintain the cover sheet ing, and replace damaged cover polyethylene sheeting as needed. Provide protection for the stockpile to control the migration of contaminants. Dispose of excavated material, within 180 days of being stockpiled, as specified in 202.03.09. Clean equipment used to move excavated material at the end of each working day or before removing the equipment from the Project Limits. Install non-vegetative SESC measures to limit the movement of the excavated material from equipment cleaning areas. Temporarily store the material collected during equipment cleaning in stockpiles.

201.03.04 Disposing and Recycling of Contaminated Soil - Tanks

Transport the contaminated soil to an approved recycling or disposal facility. Perform soil sampling and analyses according to disposal facility requirements. Provide a copy of sampling log, chain of custody form, and analytical report to the RE. P rocedures for sampling should be in accordance with the NJDEP Field Sampling Procedures Manual, NJDEP Technical Requirements for Site Remediation, NJDEP Management of Excavated Soils Guidelines, of N.J.A.C 7:14B, the American Petroleum Institute Standard and NJDEP Technical Guidance Documents. Sample material as per the recycling or dispo sal facility requirements. Submit proper documentation from the disposal facility acceptance of the contaminated soil, including the weigh ticket slips, to the RE within 15 days of acceptance at the disposal facility.

201.03.05 Monitoring Well

Install monitoring wells using a NJDEP certified well driller according to N.J.A.C 7:9D. Perform ground water sampling and analyses according to N.J.A.C. 7:26E and NJDEP Field Sampling Procedures Manual. Upon receipt of RE approval, seal monitoring wells according to N.J.A.C. 7:9 -D. Provide a copy of sampling log, chain of custody form, monitoring well sealing record, and analytical report to the RE.

201.03.06 Sealing Abandoned Wells

Fill and seal abandoned wells within the limits of clearing site or as shown on the Plans. Fill dug wells as specified in

201.03.07 5. Seal drilled wells according to N .J.A.C. 7:9D et seq. Provide a copy of the well abandonment records

submitted to NJDEP to the RE. If proposing an alternate method to seal the abandoned wells, obtain written approval from the NJDEP and from the RE.

201.03.07 Demolition

Refer to 108.12 of the Special Provisions for occupied properties and vacation dates and availability dates. Demolish and remove the required buildings in place. Only remove small structures and appurtenances outside the area to be cleared that are designated for removal. Existing laws, ordinances, and regulations govern the parking, loading, and operation of trucks on existing highways or streets. The Department assumes no responsibi lity for the condition of the v arious buildings or loss of fixtures, equipment, materials, or other objects between the submittal of the Proposal and the time of actual possession of the buildings. On a daily basis, remove and dispose of, as specified in 201.03.01.H, materials, including fixtures, equipment, debris, and rubbish, and do not store removed materials within the Project Limits. Do not sell materials within the Project Limits. Where others have removed buildings, arrange to disconnect and terminate remaining utility services. Remove foundation walls and steps to at least 3 feet below ground level. Remove detached buildings and fixtures, wood, and debris from the site and dispose of as specified in 201.03.01.H. Remove heating oil tanks according to N.J.A.C. 7:14B and N.J.A.C. 7:26E, and Federal, State, and local laws, rules, and regulations. Confine demolition operations to the limits shown, and perform work as specified by the following:

1.Demolition Safety Plan. Submit a Demolition Safety Plan to the RE for approval, 10 days before demolition. Include the following provisions in the plan:
a.Type and location of warning signs, KEEP OUT signs, and barricades.
b.Type and location of barrier around operations and openings in the ground.
c.Type and location of lights and footway shelter platforms in the vicinity of pedestrian walkways.
d.Methods for controlling dust from demolition operations. Follow the Demolition Safety Plan until the RE approves the removal of protective devices. For demolition of buildings having more than 3 floors, submit an additional plan to the RE for approval at least 10 days before beginning demolition. Include the demolition methods to be used and methods of protecting adjacent building and structures.
2.Utility Disconnections. Before demolishing any building, arrange to disconnect and terminate all utilities and facilities that are connected to the building, as specified by the municipalities and companies owning or controlling them. If only a portion of an occupied structure is to be demolished, conduct demolition and related operations so that service is not interrupted to the portion of the structure that is not demolished. Where it is necessary to reconnect any facilities to the undemolished portion of the structure, make reconnections permanent. Notify, in writing, the municipalities and companies concerned when such disconnections, terminations, or reconnections are required and provide copy to RE. Perform this work according to the municipalities and companies standard practices and requirements and under their supervision; otherwise arrange for the work to be performed with their forces.
3.Rodent Control and Extermination. Before beginning demolition operations, retain a qualified sanitation inspector to conduct a survey for evidence of current rodent activity. Initiate a control program by a certified pest control operator if the survey indicates that it is necessary. Apply exterminating materials according to N.J.A.C 7:30, et seq. At least 10 days before beginning demolition of any structures, ensure the pest control operator begins ridding the structure and adjacent areas within the Project Limits of rodents or their carcasses and prevent s their migration to other adjacent areas. Where there is no competing water supply, the Contractor may use liquid anticoagulant baits at the discretion of the certified pesticide applicator. Place toxic bait in the form of a 1 pound paraffinized block in each manhole or inlet of storm or combination drains located on the same street as the building to be demolished and within the same block, including the entire intersections of the nearest cross streets. Place bait in suitable locations within the draina ge structures, as determined by the pest control operator. Fasten the bait block in its location with wire. Inspect and renew toxic bait in structures or drains as necessary after initial baiting. Remove and dispose of carcasses to the satisfaction of the RE. After the initial treatment and each follow -up inspection, submit a signed statement, from the pest control operator, reporting the amount and type of bait placed in each location and stating the visible results obtained from the rodent control program. Ensure that the pest control operator is aware of the antidote noted on the rodenticide label.
4.Demolition Operations. Before demolishing buildings, remove and dispose of chemicals, miscellaneous cylinders, drums, above ground and underground heating oil tanks per NJDEP Unregulated Heating Oil Tank Program, asbestos, and garbage from the building according to applicable Federal, State, and local laws, rules, and regulations. Remove and recycle materials that are required to be recycled by the Federal, State, and local laws, rules, and regulations. Before beginning d emolition operations, pump out and clean basements, wells, cesspools, and outbuildings within the areas to be cleared in a sanitary manner. After being disinfected as required by the health authorities, backfill to adjacent ground level as specified in 201.03.07.5. Maintain wells, cisterns, cesspools, and other openings in the ground outside the area to be cleared without hindering their functionality. Cap well casings securely and permanently as specified in 201.03.06, and cutoff and cap pipes leading into or out of the well. Leave adjacent buildings in a safe condition, and do not deface, mar, or jeopardize them in any way. Repair or restore damaged buildings to the satisfaction of the RE. Ensure that the phases of demolition are performed within the designated limits and without hazard to adjacent properties or to the public. Do not set any structure on fire. Do not demolish or di sturb chimneys common to adjacent properties other than to give them the necessary support for their continued stability. If necessary, repoint and cap them. When demolishing a portion of a building, shore, brace, and support the remaining part so that the integrity and support of all remaining walls, floors, roofs, and their supporting members are maintained and continued in such a way that shoring, bracing, and support is outside the ROW. Board up and seal the remaining portion of such a partially demolished building along the ROW, and weatherproof the new closure and its connections to the remaining portion of the severed building. Ensure the material for closure consists of adequately braced studding of 2  4 inch timbers placed no more than 16 inches on center with wood facing nailed to the studding without any holes appearing therein. Cover the wood facing with 2 layers of smooth -finished, 65 pounds per roll, roofing material according to ASTM D 224 and having an overlap of at least 4 inches.
5.Backfilling. Backfill and compact subsurface areas including cellars using the directed method as specified in

203.03.02 B.3. The RE may require compaction using the density control method as specified in 203.03.02.B.4.

Use all available excavated material from within the Project Limits before bringing additional material for backfill to the Project Limits. If sufficient material is not available, backfill with I -14 soil aggregate. If excavated material or I-14 soil aggregate are recycled material, place the recycled material at least 2 foot above the water table. Ensure backfilling and grading establishes proper drainage. Before placing the first lift, break existing cellar floors and other surfaced areas into pieces having areas of less than 4 square feet with well -defined cracks through the full depth of the floors, or make holes of more than 1 square foot area through the floors on approximately 10 foot centers to provide vertical drainage. Remove wooden cellar floors. Clean, point, and apply 2 coats of waterproofing material to party wall foundations before backfilling against. If necessary, grade around the ground surface to eliminate water pockets. Backfill and level cellars and all other subsurface spaces to the adjacent ground elevation.

201.03.08 Removal of Asbestos

Refer to the Special Provisions for asbestos removal requirements.

201.03.09 Temporary Shielding

Submit working drawings for certification for a sy stem to protect vehicular, pedestrian, or railroad traffic or environmentally sensitive areas from falling debris, construction materials, or other objects. Temporary shielding requirements are in addition to forms and falsework required for construction. Design the temporary shielding system to conform to the following:

1.Withstands loads of at least 0.8 pounds per square inch, or greater if heavier loads are anticipated or if required by railroads.
2.Prevents small particles and dust from escaping the shield.
3.Seals the underside of the deck and extends outside of the deck and outside of the fascia stringers to enclose the soffits and parapets.
4.If parapet removal or parapet construction is required, provide an outrigging to enclose the soffit and parapet.
5.Does not bolt or weld the temporary shielding system to the beams.
6.Does not reduce the underclearance of the bridges to less than 14.75 feet over roadways and 22 feet over railroads or as specified in the Contract. If existing underclearanc e is less than these values, does not further reduce the underclearance. Show elements of the temporary shielding system, including design calculations, and the sequence of operations, and, when applicable, bonding and grounding over electrified rail lines. Include with the working drawings a plan for removing material, dust, or debris that has fallen into active traffic lanes, railroads, and environmentally sensitive areas. Install the temporary shielding according to the certified working drawings before performing any construction operations over vehicular, pedestrian, or railroad traffic or ecologically sensitive areas. The RE will not allow the installation of temporary shielding over active traffic lanes and pedestrian areas. When app licable, comply with the railroad’s maintenance of traffic requirements, rules and regulations. Remove and reinstall the temporary shielding as required by construction staging. Do not allow dropped materials to accumulate on the temporary shielding, and remove dropped materials promptly. If debris falls from the shielding, promptly clean it up and repair the damage. Do not remove any portion of the shielding without the approval of the RE.

201.04 Measurement and Payment

The Department will measure and make payment for Items as follows: Item Pay Unit CLEARING SITE LUMP SUM CLEARING SITE, BRIDGE LUMP SUM CLEARING SITE, STRUCTURE LUMP SUM CLEARING SITE, TANK REMOVAL UNIT DISPOSING AND RECYCLING OF CONTAMINATED SOIL - TANKS TON MONITORING WELL UNIT SEALING OF ABANDONED WELL UNIT DEMOLITION, PARCEL UNIT REMOVAL OF ASBESTOS, PARCEL UNIT TEMPORARY SHIELDING LUMP SUM A unit of CLEARING SITE, TANK REMOVAL is each tank removed. The Department will not make payment without the Remedial Investigation Report and tank disposal receipt.

Get an email when 201 changes

New Jersey revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Road and Bridge Construction, 2019 (rev. 2022-12-21) Edition. Pages 153–159 of 651. View official source ↗

Ask about this section

Scoped to New Jersey 2019 Standard Specifications for Road & Bridge Construction, Section 201 — Clearing Site. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.