SECTION 209 - SOIL EROSION AND SEDIMENT CONTROL (Last Revised January 2019)

209-1 DESCRIPTION. This work shall consist of furnishing, installing, inspecting, maintaining, and

removing soil erosion and sediment control measures as shown on the contract documents and as directed by the Engineer.

209-1.01 Erosion Control. Erosion Control is any action taken to reduce soil erosion and control

sedimentation, including the use of mulch, straw/wood fiber mulch, seed and mulch, seed and straw/wood fiber mulch, rolled erosion control products, soil stabilizers, and pipe slope drains.

209-1.02 Sediment Control. Sediment Control is any action taken to minimize suspended solid material

transport by water, including the use of sediment traps, turbidity curtains, sediment filter logs, silt fence, check dams, drainage structure inlet protection, and stabilized construction entrance/exits.

209-2 Materials.

209-2.01 General. None specified.

209-2 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2

209-2.02 Mulch-Temporary. The materials shall meet the requirements of the following subsections of

§700 Materials and Manufacturing. Straw 713-19 Wood Fiber Mulch 713-11

209-2.03 Seed-Temporary. The materials shall meet the requirements of the following subsections of

§700 Materials and Manufacturing. Seeds 713-04 Water 712-01 Seed shall be ryegrasses (annual or perennial) or cereal grasses suitable for the area as a temporary cover and which will not compete with the grasses sown later for permanent cover.

209-2.04 Check Dams. The materials shall meet the requirements of the following subsections of

Section 700 Materials and Manufacturing. Stone Filling 733-21 Coarse Aggregate 703-02 Sediment Filter Logs 713-20 Geotextile 737-01

A.Stone Check Dams. Stone filling shall meet the requirements of §733-21 Stone Filling, Light and/or §703-02 Coarse Aggregate, size designation 1 or 2 as described in Table 703-04. Geotextile bedding shall conform to §737-01 Geotextiles, Table 737-01A – Bedding Geotextile Requirements.
B.Gravel Bag Check Dams.
1.Bags. Bags shall be fabricated from reinforced woven geotextile that meets the requirements of §737-01 Geotextile with a strength class 1 or 2 and shall include ties. No burlap bags shall be allowed.
2.Gravel. Coarse aggregate shall meet the gradation requirements of size designation #1 or #2 of Table 703-4 and shall be used as the fill material. Gravel bags shall be individually tied and double bagged. The bag with fill material shall be inversely inserted into the second bag in order to prevent leakage.
C.Prefabricated Check Dams.
1.Temporary Silt Dike. Temporary silt dikes shall be triangular in cross section, and have a height of at least 10 inches in the center with two equal sides and a 18 inch to 24 inch base. The inner material shall be urethane foam. The outer cover shall be a woven bedding type geotextile (§737-01; Table 737-01A) wrapped around the inner triangle and shall extend 24 inches to 36 inches beyond each side of the triangle base. Wire staples used to secure the prefabricated check dam shall be No. 11 gauge wire and be 6 inches to 8 inches long.

209-2 05

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2 Stone shall meet the requirements of §703-02 Coarse Aggregate, size designation 1 as described in Table 703-4. Stone filling shall be placed over the geotextile apron. Refer to the standard sheets for additional information.

2.Sediment Filter Logs. The materials for prefabricated sediment filter logs check dams shall meet the requirements of §713-20 Sediment Filter Logs.

209-2.05 Linear Measures. The materials shall meet the requirements of the following subsections of

Section 700 Materials and Manufacturing. Geotextiles 737-01 Sediment Filter Logs 713-20

A.Silt Fence-Temporary. A silt fence assembly shall consist of silt fence geotextile, posts, and fasteners and may include mesh support consistent with the Approved List.
1.Geotextile. Silt fence geotextile shall meet the requirements of §737-01 Geotextiles, G. Silt Fence and be listed in the Approved List.
2.Posts. Posts shall meet the following requirements: Wood posts shall have a minimum cross section area of 3.5 square inches; steel post shall be “T” or “U” shaped in cross section, with a minimum weight of 1.33 pounds per foot. Posts shall be a minimum of 40 inches long and shall be spaced according to the geotextile selected, as indicated in the Approved List.
3.Mesh Support. For those silt fence geotextiles on the Approved List that require a mesh support, the support shall consist of 14 gauge (minimum) welded wire mesh with a maximum 6 inch by 6 inch opening or polymeric mesh. All mesh support shall be a minimum of 30 inches in height.
4.Fasteners. Fasteners shall be heavy duty staples, hog rings, tie wires, or any other fastener compatible with the post material.
B.Sediment Filter Logs. A sediment filter log assembly shall consist of the sediment filter log and posts.
1.Posts. Posts shall be nominal 2 x 2 wood. The length of posts shall be at least 16 inches greater than the diameter of the log.

209-2.06 Sediment Traps-Temporary. The materials shall meet the requirements of the following

subsections of §700 Materials and Manufacturing: Stone Filling 733-21 Geotextile 737-01

A.Impervious Embankment Material. Impervious embankment material shall be §733-08 Embankment in Place, §733-10 Select Fill, §733-11 Select Granular Fill, or §733-12 Select Granular Fill Slope Protection, and the impervious embankment material shall have the following gradation:

209-2 07

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2 Sieve Size Percent Passing by Weight 6 inch 90 – 100 3/4 inch 50 – 100 1/4 inch 40 – 90 #40 30 – 85 #200 25 - 75

B.Gravel Bags.
1.Bags. Bags shall be fabricated from reinforced woven geotextile that meets the requirements of §737-01 Geotextile with a strength class 1 or 2 and shall include ties. Burlap bags will not be allowed.
2.Gravel. Coarse aggregate used as fill material shall meet the gradation requirements of size designation 1 or 2 of Table 703-4. Each gravel bag shall be individually tied and double bagged. The bag with fill material shall be inversely inserted into the second bag in order to prevent leakage.
C.Geotextile Bedding. The geotextile bedding material shall meet the requirements of §737-01 Geotextile, Table 737-01A. Bedding Geotextile.
D.Riser Pipe. Riser Pipe shall be 16 gauge corrugated steel, aluminum or polyethylene and perforated with 1 inch diameter holes or slits spaced 6 inches vertically by 6 inches horizontally and placed in the concave portion of the corrugations. No holes will be allowed within 6 inches of the outlet pipe.
E.Hardware Cloth. Hardware cloth wire shall meet ASTM A740-98 Hardware Cloth (Woven or Welded Galvanized Steel Wire Fabric), be 23 gauge (minimum) and have 1/4 inch or 1/2 inch openings.
F.Geotextile Drainage Fabric. The geotextile drainage fabric shall meet the requirements of §737- 01 Geotextile, Table 737-01C Drainage Geotextile Requirements.
G.Steel Base Plates. Steel base plates shall be 1/4 inch minimum thickness.
H.Outlet Pipes. The outlet pipe shall be 12 inch 16 gauge corrugated steel pipe.
I.Stone Filling. Stone filling shall meet the requirements of §733-21 Stone Filling.

209-2.07 Pipe Slope Drain-Temporary. The materials shall meet the requirements of the following

subsections of §700 Materials and Manufacturing. Smooth Interior Corrugated Polyethylene Pipe 706-12 Corrugated Interior Polyethylene Pipe 706-14 Corrugated Steel Pipe 707-02 Corrugated Aluminum Pipe 707-13 Stone Filling 733-21 Coarse Aggregate 703-02 Geotextile 737-01

209-2 08

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2

A.Pipe. The pipe shall be corrugated plastic pipe per §706-14 or corrugated metal pipe (CMP) per §707-02 or 707-13 or other material as approved by the Engineer. The pipe shall have soil-tight or better connections. Refer to the standard sheets for direction on pipe sizes.
B.Gravel Bags.
1.Bags. Bags shall be fabricated from reinforced woven geotextile that meets the requirements of §737-01 Geotextile with a strength class 1 or 2 and shall include ties. No burlap bags shall be allowed.
2.Gravel. Coarse aggregate used as fill shall meet the gradation requirements of size designation 1 or 2 of Table 703-4. Each gravel bag shall be individually tied to prevent leakage.
C.Geotextile Bedding. Geotextile bedding shall meet the requirements of §737-01 Geotextile for Geotextile Bedding as described in Table 737-01A.
D.Crushed Stone or Stone Filling. Crushed stone or stone filling shall meet the requirements of §733-21 Stone Filling.
E.Sediment Filter Logs. A sediment filter log assembly shall consist of the sediment filter log and posts.
1.Posts. Posts shall be nominal 2 x 2 wood. The length of posts shall be at least 16 inches greater than the diameter of the log. Pipe slope drain materials may consist of new or used material in satisfactory condition. Pipe couplings shall be appropriate for the pipe and as recommended by the Manufacturer. End sections may be galvanized steel or aluminum.

209-2.08 Rolled Erosion Control Products and Soil Stabilizers. The materials shall meet the

requirements of the following subsections of Section 700 Materials and Manufacturing. Rolled Erosion Control Products and Soil Stabilizers 713-07 The Type and Class shall be as specified in the contract documents.

209-2.09 Stabilized Construction Access. The materials shall meet the requirements of the following

subsections of this Section and §700 Materials and Manufacturing. Straw 713-19 Wood Fiber Mulch 713-11 Seeds 713-04 Water 712-01 Coarse Aggregate 703-02 Geotextiles 737-01

A.Geotextile. Geotextiles shall meet the requirements of §737-01 E. Geotextile Stabilization, Strength Class 1.

209-2 10

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2

B.Crushed Stone or Gravel. Crushed stone or gravel shall meet the requirements of size designation #3 on Table 703-4.
C.Drainage Pipes. The drainage pipe may be steel, aluminum or polyethylene and consist of new or used material in satisfactory condition and suitable for the intended use.
D.Fill Material. Fill material shall meet the requirements of §733-08 Embankment In Place, §733- 10 Select Fill, §733-11 Select Granular Fill, or §733-12 Select Granular Fill Slope Protection.
E.Temporary Seed and Mulch. Temporary Seed and Mulch shall meet the requirements of §713-19 – Straw, §713-11 – Wood Fiber Mulch, §713-04 – Seeds and §712-01 – Water .

209-2.10 Turbidity Curtain-Temporary. The materials shall meet the requirements of the following

subsections of §700 Materials and Manufacturing. Turbidity Curtain 737-01F. The Turbidity Curtain shall be a commercially available, pre-assembled system, including a geotextile, flotation system, bottom weight, and anchoring and securing mechanism. If assembled in panels, it shall include a secure mechanism for joining panels together. Hemmed pockets shall be sewn or heat bonded to contain flotation material, bottom weights, and for anchor lines. The flotation material shall maintain buoyancy if punctured or cut. The bottom weight shall be sufficient to hold the curtain in a vertical position. For sites not subject to tidal or heavy wave action, the curtain shall be capable of molding to conform to bottom contours so that suspended sediment is prevented from escaping underneath the curtain. Anchorage lines shall be provided of sufficient strength and number to support the curtain and maintain it in position under normally expected conditions. End anchors shall be provided, with intermediate anchor points (for stakes or anchors) such that unanchored spans do not exceed 100 feet, sufficient to maintain the turbidity curtain in place. Where the turbidity curtain is constructed in panels, anchor-line and shackle connections securing the panels together shall be sufficient for normally expected current, wind, or wave conditions.

209-2.11 Drainage Structure Inlet Protection-Temporary. The materials shall meet the requirements

of the following subsections of Section 700 Materials and Manufacturing. Coarse Aggregate 703-02 Geotextiles 737-01 Sediment Filter Logs 713-20

A.Silt Fence. Geotextile shall meet the requirements of §737-01 G. Silt Fence and be listed in the NYSDOT Materials and Equipment Approved List (Approved List). Drainage Structure Inlet Protection assembly shall consist of silt fence geotextile, posts, frame and fasteners and may include mesh support consistent with the Approved List.
1.Post/Frame. Shall be 2 inch by 4 inch nominal dimension wood posts a minimum of 40 inches long.
2.Mesh Support. For those silt fence geotextiles on the Approved List that require a mesh support, the support shall consist of 14 gauge (minimum) welded wire mesh with a maximum 6 inch x 6 inch opening or polymeric mesh. All mesh support shall be a minimum of 28 inches in height.

209-3 01

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2

3.Fasteners. Fasteners shall be heavy duty staples, hog rings, tie wires, or any other fastener compatible with the post material.
B.Prefabricated. Prefabricated drainage structure inlet protection shall be a temporary silt dike or sediment filter log.
1.Temporary Silt Dike. Temporary silt dikes shall be triangular in cross section, and have a height of at least 10 inches in the center with two equal sides and a 18 inch to 24 inch base. The inner material shall be urethane foam. The outer cover shall be a woven bedding type geotextile (§737-01; Table 737-01A) wrapped around the inner triangle and extends 24 inches to 36 inches beyond each side of the triangle base. Wire staples used to secure the prefabricated check dam shall be No. 11 gauge wire and be 6 inches to 8 inches long.
2.Sediment Filter Logs. Sediment Filter Logs shall meet the requirements of §713-20 Sediment Filter Logs. A sediment filter log assembly shall consist of the sediment filter log and posts. Posts shall be nominal 2 x 2 wood and be at least 16 inches longer than the diameter of the log. Logs to be left in place will be noted on plans.
C.Concrete Block. Concrete blocks with holes used for inlet protection shall conform to the requirements of C 90 ASTM. Non-woven geotextile shall conform to the requirements described in §737-01C Drainage Geotextiles, Class A.
1.Crushed Stone. Crushed stone shall meet the gradation requirements of size designation 1 or 2 of Table 703-02.
2.Hardware Cloth. Hardware cloth wire shall meet ASTM A740-98 Hardware Cloth (Woven or Welded Galvanized Steel Wire Fabric), be 23 gauge (minimum) and have 1/4 inch or 1/2 inch openings.
3.Geotextile Drainage Fabric. The geotextile drainage fabric shall meet the requirements of §737-01 Geotextile, Table 737-01C Drainage Geotextile Requirements.
D.Excavated.
1.Geotextile. §737-01 Geotextile, Table 737-01C Drainage Geotextile, Class A.
2.Crushed Stone. §703-02 Coarse Aggregate, size designation 1 as described in Table 703-4.

209-3 Construction Details.

209-3.01 General. In the event of conflict between these requirements and pollution control laws, rules,

regulations or permit conditions by other federal or state agencies, the more restrictive shall apply. Soil erosion and sediment control shall be performed consistent with §107-12 Water Quality Protection and included as part of the construction schedule submitted by the Contractor in accordance with §108-01 Start and Progress of Work. To the extent practicable, this work shall be coordinated with other items of work specified elsewhere in the contract documents. The intent is to assure effective and continuous erosion and sediment control throughout the construction phase and post construction to reduce the impacts of soil loss on receiving waters and adjacent properties.

209-3 02

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2 Sediment controls shall be installed prior to performing grubbing, excavation, and borrow or fill operations, except for those actions necessary to install the sediment controls. The Contractor shall limit the area of clearing and grubbing, excavation, borrow and embankment operations in progress commensurate with their capability to minimize erosion and sediment transport and keep the finish grading, mulching, seeding and other temporary and/or permanent control measures current in accordance with the approved schedule. The Engineer may determine that a potential for erosion or sediment transport exists and direct the Contractor to install temporary erosion controls earlier. When permanent soil erosion and sediment control measures cannot be installed due to seasonal or other limitations, temporary soil erosion and sediment control measures shall be installed. Prior to removing or disturbing any erosion or sediment control measure that may be required to be reestablished due to continual grading operations, the Contractor shall verify the proposed progression of operations and the reestablishment of control measures with the Engineer to ensure the continuity of erosion and sediment control. Sediment control measures shall not be removed without the Engineer’s approval.

A.Inspection and Maintenance. Soil erosion and sediment control measures shall be inspected and maintained by the Contractor for the duration of the contract, including winter shutdown, etc. Inspection and maintenance shall continue until after the permanent stabilization measures are established and the temporary control measures are removed. The remaining disturbed area shall be permanently stabilized in accordance with the contract documents. All temporary controls shall be inspected by the Contractor at least every seven calendar days and after each runoff event to determine if the practice is functioning as intended. All inspections shall be completed within one calendar day. Within 1 work day from completion of the inspection, the Contractor shall:
1.Repair or rebuild the practice to function as originally intended.
2.Remove sediment deposition which reaches one half the height of the practice. All sediment removed during maintenance of the practice shall be considered unsuitable material and disposed of in accordance with §203-3.01E Unsuitable Material. Material shall be disposed of away from sensitive resources including wetlands, water courses or other bodies of water. Where erosion control materials have been used on final grades that have been permanently seeded, the Contractor shall care for the areas until acceptance of the Contract or acceptance of the turf, whichever is later. Where necessary, such care may include, but is not limited to providing warning signs or barricades for protection against traffic. In addition to routine maintenance, any surface that has settled, become gullied, or otherwise damaged due to the Contractor’s operations shall be repaired at no additional expense to the state to reestablish the grade and soil conditions that existed prior to placing erosion control materials.

209-3.02 Mulch-Temporary. The Contractor shall have the capability to mulch any disturbed areas on

any given day (e.g., those areas where earthwork operations are ongoing, etc.). The Contractor shall apply mulch on disturbed areas consistent with the approved project schedule or no later than seven days after grading. Straw mulch shall be spread uniformly in a continuous blanket at a rate of 2 tons per acre. Wood fiber mulch shall be applied at a rate of 1.5 tons per acre. Mulch may be spread by hand, mechanical spreaders, or blowers.

209-3.03 Seed and Mulch-Temporary. The Contractor shall apply seed and mulch on disturbed areas

that will remain idle for more than fourteen days and regraded at a later date. The Contractor shall clean all equipment involved in seeding to remove all unwanted plants, seeds and propagules prior to starting work.

209-3 04

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2 Prior to the application of seed, all areas where compaction has occurred shall be scarified. The seed bed shall be loose and friable for positive seed retention. The Contractor shall spread ryegrass at a rate of 30 pounds per acre or cereal grasses spread at a rate of 100 pounds per acre to uniformly cover the ground. The Contractor shall evenly distribute seed by any method of sowing that does not injure the seeds in the process of spreading. The Contractor shall spread mulch immediately following application of seed. If using straw mulch, it shall be spread uniformly in a continuous blanket at an approximate rate of 2 tons per acre by hand, or by mechanical spreaders or blowers. Mulch and seed shall not be placed simultaneously, except in the case of hydroseeding. The Contractor shall secure straw mulch to the soil surface by crimping or applying a soil stabilizer immediately after mulching, then water the seeded area. The application of water shall not result in damage to the seeded area including the redistribution of seeds (congregating seeds as a result of ponding or pooling water) or soil erosion (rilling). The Contractor shall water the temporary seed and mulch area until seed has germinated. Maintenance of temporary seed and mulch areas shall include re-seeding, as necessary, to achieve temporary stabilization.

209-3.04 Check Dams. Check dams shall be constructed in accordance with the standard sheets and to

the dimensions and locations shown in the contract documents. A bedding type geotextile (§737-01 Geotextiles) or stone (§733-21 Stone Filling, Light or §703-02 Coarse Aggregate) scour protection shall be placed as indicated in the contract documents. Temporary Silt Dike check dams shall be attached to the ground with wire staples. Staples shall be placed according to Manufacturer’s instructions. Sediment Filter Log prefabricated check dams shall be installed according to Manufacturer’s instructions. Sediment Filter Logs shall be removed at the end of the contract, unless noted otherwise in contract documents.

209-3.05 Linear Measures. Linear measures shall be constructed in accordance with the standard sheets

and to the dimensions and locations shown in the contract documents.

A.Silt Fence-Temporary. Silt fence shall be removed when disturbed soil upslope of the practice has been fully stabilized with permanent vegetation, pavement or stone.
B.Sediment Filter Logs. Sediment filter logs shall be removed when disturbed soil upslope of the practice has been fully stabilized with permanent vegetation, pavement or stone, or sediment filter logs may be left in place on long or steep slopes to provide long-term runoff control. Logs to be left in place will be noted on plans.

209-3.06 Sediment Trap-Temporary. Sediment traps shall be constructed in accordance with the

standard sheets and to the dimensions and locations shown in the contract documents. The area under which the berm will be constructed shall be cleared, grubbed and stripped of any vegetation and root mat. The pool area shall be cleared of woody vegetation. All work shall be performed in accordance with §201 Clearing and Grubbing and paid for separately.

A.Gravel Bag or Sediment Filter Log Berm. Gravel Bag or Sediment Filter Log Berms shall be constructed in accordance with the standard sheets and to the dimensions and locations shown in the contract drawings.
B.Earth Berm. The earth berm embankment shall be constructed consistent with the requirements of §203 Excavation & Embankment, except as herein modified. Immediately prior to placement of the impervious embankment material, the earth surface on or against which fill is to be placed, shall be thoroughly scarified to a depth of 6 inches and compacted to not less than 95 percent of Standard

209-3 07

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2 Proctor Maximum Density. Impervious embankment material shall then be deposited in lifts not exceeding 8 inches and compacted to not less than 95 percent of Standard Proctor Maximum Density. The moisture content of all impervious embankment material shall not be greater than 2 percent above Optimum Moisture Content as determined by AASHTO T-99 Standard Method of Test for Moisture-Density relations of Soils using a 5.5 pound Rammer and a 12 inch Drop, Method C at the time of compaction.

C.Riser and Outlet Pipe. The riser and outlet pipe shall be installed in accordance with the standard sheets and to the dimensions and locations shown in the contract documents.

209-3.07 Pipe Slope Drain-Temporary. Pipe slope drain shall be installed in accordance with the

contract documents and standard sheets. Additional right-of-way may be required to accommodate this practice.

209-3.08 Rolled Erosion Control Products and Soil Stabilizers. Rolled Erosion Control products and

Soil Stabilizers shall be installed or applied as specified in the contract documents and/or according to Manufacturer’s instructions. For areas at final grade, all loose stones, clods, sticks, or other undesirable material shall be removed in accordance with the Manufacturer’s recommendations or as specified in the contract documents. Where topsoil is specified, the rolled erosion control product will be installed within 2 work days of topsoil placement and soil stabilizers shall be applied according to Manufacturer’s instructions.

A.Rolled Erosion Control Products. Construct according to the Manufacturer’s recommendations and the following as minimum installation technique:
1.Class I and Class II, Rolled Erosion Control Products. Rolled erosion control products (RECP) shall be placed without stretching on the freshly prepared surface so that it lays loosely on the soil and is in contact with the soil at all points; and then it shall be rolled or tamped firmly into the soil surface. The upper end of each roll shall be turned down and buried to a depth of 6 inches with the soil firmly tamped against it. RECP shall be placed so that all edges shall have a minimum overlap of 6 inches. RECP shall be held tightly to the soil by anchors driven firmly into the ground. Anchors shall be spaced not more than 40 inches apart on the sides and along the centerline of all drainage ways. Unless otherwise specified in the contract documents, lengths of rolled erosion control products shall not exceed 50 feet. If the RECP needs to be spliced in the middle of a slope be sure the RECP is “shingled” with the upgrade RECP overlapping the downgrade RECP. To continue the row downslope, a new section of fabric shall be applied by burying the fabric to a depth of 6 inches with the soil firmly tamped against it, and the upper section of fabric overlapping the downslope section by a minimum of 4 inches. Seams shall be staggered at alternating elevations. RECP ends and splices shall have anchors spaced at 24 inch intervals.
2.Class III Turf Reinforcement Mat (TRM). Type A and Type B TRMs shall be completely filled with topsoil immediately after installation. Type C and Type D TRMs, which contain a composite, do not need to be filled with topsoil unless recommended by the Manufacturer. To prevent initial soil loss, Type A and Type B TRMs shall be covered with one of the following materials, which will be paid for separately.
a.For Slope application:
1.Class IV-Soil Stabilizer

209-3 09

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2

2.An approved RECP (Class I or II)
3.Mulch
b.For Channels:
1.An approved RECP (Class I or II)
B.Class IV Soil Stabilizers. These materials shall be applied as recommended by the Manufacturer. Type A & B are intended to be applied with hydroseeding equipment. Type B may also be placed through dry spreading. When dry spreading method is used, the Contractor shall apply the material uniformly. Where applied, Type A shall be a minimum of 1/4 inch thick. When Type A is used in conjunction with turf establishment, seeds must be sown separately and prior to the application of the soil stabilizer.

209-3.09 Stabilized Construction Access. Stabilized Construction Access shall be placed where shown

in the contract documents and constructed in accordance with the standard sheets, or as otherwise approved by the Engineer. The Contractor shall grade, including excavating or placing fill, to prepare the original ground surface for the placement of a stabilized pad of at least 6 inches of coarse aggregate material, underlain by a geotextile. If necessary, a drainage pipe shall be installed to maintain the capacity of the ditch. The pipe dimension shall be consistent with the modified soil erosion and sediment control plan approved by the Engineer. All areas cut or filled and not stabilized by the stabilized construction access material shall be covered with an erosion control treatment (temporary mulch, temporary seed and mulch, etc.) and shall be included in this pay item. When wheel washing is performed, the washing area shall be located away from the stabilized construction access in an area which will drain into an approved sediment control measure(s). The stabilized construction access shall be maintained in a condition which will prevent tracking or flowing of sediment onto a paved public roadway. All sediment spilled, dropped, washed or tracked onto paved public roadway shall be removed immediately. In the event the stabilized construction access is no longer performing properly (i.e. the course aggregate becomes clogged with sediment), the Contractor shall top- dress the stabilized construction access with additional coarse aggregate material.

209-3.10 Turbidity Curtain-Temporary.

A.Systems Requirements.
1.For sites not subject to tidal or heavy wave action, the curtain height shall provide sufficient slack to allow the top of the curtain to rise to the maximum expected high-water level (including waves), while the bottom maintains continuous contact with the bottom of the water body. The bottom edge of the curtain shall have a weight system capable of holding the bottom of the curtain down and conforming to the water body, so as to prohibit escape of turbid water under the curtain.
2.For sites subject to tidal or heavy wave action, the curtain height shall provide sufficient slack to allow the top of the curtain to rise to the maximum expected high-water level (including waves), while the bottom remains 24 inches above the bottom. The weight system shall hold the lower edge of the curtain in place so as to allow 24 inches of clearance above the bottom at mean low water, so that the curtain does not stir up sediment by repeatedly striking the bottom.

209-3 10

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2

3.If constructed in panels, panels shall be connected in such a manner as to prevent suspended particles passing through joints. Load lines shall be connected so as to develop the full strength of the line across the joint.
4.Flotation material shall be arranged so as to be flexible and to provide continuous support.
5.The flotation and curtain top shall be such as to provide a minimum of 4 inches of freeboard along the entire length of the curtain, to prohibit escape of turbid water over the top.
B.Installation
1.The turbidity curtain shall be installed as shown in the contract documents in accordance with the Manufacturer’s instructions. It shall be placed as close to the site of disturbance as possible without interfering with construction activity.
2.Turbidity curtain shall be installed and maintained in a manner that precludes passage of equipment, other than hand-held equipment or boats, to the water body outside the protected area.
3.The fully assembled turbidity curtain shall be prepared for installation by being furled and tied at intervals of 5 feet for the length of the curtain. It shall be placed and secured in the furled condition, then released to allow the bottom edge to sink.
4.At sites subject to tidal or heavy wave action, adjustment lines may be used to achieve the required height of the curtain.
5.At sites not subject to tidal or heavy wave action, excess curtain material shall lay on the bottom, away from construction activity.
6.Turbidity curtain shall be placed as nearly as possible parallel to current flow. It shall not be deployed across a flowing water course.
7.The ends of the installation shall be anchored securely well up the bank. Intermediate anchors of a type and number sufficient to hold the curtain in place under expected conditions shall be placed, and firmly fastened to the top of the curtain assembly. Maximum spacing between anchorage points shall not exceed 100 feet.
8.In situations with flow velocities that exceed 5 feet per second, use a redirection barrier. The redirection barrier shall be installed prior to installation of the turbidity curtain wherever possible, and care should be exercised in order to minimize disturbance of the bottom of the water body during installation of the redirection barrier.
C.Inspection and Maintenance
1.The turbidity curtain shall be inspected daily, with additional monitoring of performance during storms or significant flow events.
2.Any visible plume of turbid water passing beyond the curtain from the enclosed construction area shall constitute inadequate performance of the turbidity curtain. The Contractor shall immediately modify, adjust, or repair any portion of the turbidity curtain to correct inadequate performance.

209-3 11

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2

3.The turbidity curtain shall remain in place until the protected construction activities have ceased and there is no visible contrast between the water being contained and the water body being protected.
D.Removal.
1.The turbidity curtain shall be removed in such a way so as to minimize release of sediment.
2.Sediment behind the curtain may be removed before removal of the curtain, if directed by the Engineer. If so, any resulting turbidity must be allowed to settle before removal proceeds.

209-3.11 Drainage Structure Inlet Protection-Temporary. Drainage structure inlet protection shall be

placed where shown in the contract documents and constructed in accordance with the standard sheets.

209-4 Method of Measurement.

209-4.01 General. Vacant.

209-4.02 Mulch-Temporary. The quantity to be measured for payment will be in square yards to the

nearest whole square yard of mulch-temporary installed.

209-4.03 Seed and Mulch-Temporary. This work will be measured in square yards to the nearest whole

square yard of seed and mulch-temporary installed.

209-4.04 Check Dam.

A.Check Dam – Temporary (Stone). Stone (Temporary and Permanent). The work will be measured as the number of stone check dams installed.”
B.Check Dam – Gravel Bag (Temporary). The work will be measured as the number of each gravel bag check dam installed.

209-4.05 Linear Measures. The work will be measured as the number of linear feet to the nearest whole

linear foot of silt fence or sediment filter logs installed. No additional measurement will be made for seams or overlaps.

209-4.06 Sediment Traps-Temporary. The work will be measured as the number of sediment traps

installed.

209-4.07 Pipe Slope Drains-Temporary. The work will be measured as the number of pipe slope drains

installed.

209-4.08 Rolled Erosion Control Products and Soil Stabilizers. The work will be measured as the

number of square yards to the nearest square yard of rolled erosion control products and soil stabilizers installed.

209-4.09 Stabilized Construction Access. The work will be measured as the number of square yards to

the nearest square yard of construction stabilized construction access installed.

209-4 10

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2

209-4.10 Turbidity Curtain-Temporary. This work will be measured in linear feet, to the nearest whole

linear foot, of turbidity curtain installed.

209-4.11 Drainage Structure Inlet Protection-Temporary. This work will be measured as the number

of linear feet to the nearest whole linear foot of drainage structure inlet protection installed. No additional measurements will be made for seams or overlaps.

209-5 Basis of Payment.

209-5.01 General. The unit price bid for all work items shall include the cost of all labor, equipment, and

materials necessary to satisfactorily complete the work, including the cost of removal of accumulated sediment. Progress payments will be made for all sediment control measures as follows: Seventy-five percent of the price bid will be paid after installation of Check Dams, Silt Fence-Temporary, Stabilized Construction Access, Drainage Structure Inlet Protection-Temporary, Sediment Filter Logs and Turbidity Curtain-Temporary. Fifty percent of the price bid will be paid after installation of Sediment Traps and Pipe Slope Drains. The remaining percentage will be paid when the temporary practice is removed and the remaining area is permanently stabilized. Payment for Mulch-Temporary, Seed and Mulch-Temporary and Rolled Erosion Control Products and Soil Stabilizers will be paid in full after installation of the practice.

209-5.02 Mulch-Temporary. The unit price bid per square yard of mulch-temporary shall include the

cost of all labor, equipment, and materials necessary to satisfactorily complete the work.

209-5.03 Seed and Mulch-Temporary. The unit price bid per square yard seed and mulch-temporary

shall include the cost of all labor, equipment, and materials necessary to satisfactorily complete the work.

209-5.04 Check Dams. The unit price bid for check dams shall include the cost of all labor, material and

equipment necessary to satisfactorily complete the work.

209-5.05 Linear Measures. The unit price bid for silt fence-temporary or sediment filter logs shall

include the cost of all labor, materials and equipment necessary to satisfactorily complete the work.

209-5.06 Sediment Traps-Temporary. The unit price bid for sediment traps-temporary shall include the

cost of all labor, material and equipment necessary to satisfactorily complete the work. Temporary seed and mulch and rolled erosion control product will be paid for separately.

209-5.07 Pipe Slope Drains-Temporary. The unit price bid for pipe slope drains-temporary shall include

the cost of all labor, material and equipment necessary to satisfactorily complete the work, including gravel bags, stone, sediment filter logs, manufactured silt dikes and/or other materials necessary to construct the practice.

209-5.08 Rolled Erosion Control Products and Soil Stabilizers. The unit price bid for rolled erosion

control products and soil stabilizers shall include the cost of all labor, material and equipment necessary to satisfactorily complete the work.

209-5.09 Stabilized Construction Access. The unit price bid for stabilized construction access shall

include the cost of all labor, material and equipment necessary to satisfactorily complete the work. Payment will not be made for construction entrances associated with the Contractor’s facilities (e.g., staging areas, storage yards, borrow sites, etc.).

209-5 10

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2

209-5.10 Turbidity Curtain-Temporary. The unit price bid for turbidity curtain-temporary shall include

the cost of all labor, materials, and equipment necessary to satisfactorily complete the work.

209-5.11 Drainage Structure Inlet Protection-Temporary. The unit price bid for drainage structure

inlet protection – temporary shall include the cost of all labor, materials, and equipment necessary to satisfactorily complete the work. Payment will be made under: Item No. Item Pay Unit 209.100101 Mulch-Temporary Square Yard 209.100102 Seed-Temporary Square Yard 209.1003 Seed and Mulch-Temporary Square Yard 209.110101 Check Dam (Ditch Bottom Width 0.0 to 3′), Stone-Temporary Each 209.110102 Check Dam (Ditch Bottom Width >3′ to 6′), Stone-Temporary Each 209.110103 Check Dam (Ditch Bottom Width >6′ to 10′), Stone-Temporary Each 209.110104 Check Dam (Ditch Bottom Width >10′), Stone-Temporary Each 209.110201 Check Dam (Ditch Bottom Width 0.0 to 3′), Gravel Bag-Temporary Each 209.110202 Check Dam (Ditch Bottom Width >3′ to 6′), Gravel Bag-Temporary Each 209.110203 Check Dam (Ditch Bottom Width >6′ to 10′), Gravel Bag-Temporary Each 209.110204 Check Dam (Ditch Bottom Width >10′), Gravel Bag-Temporary Each 209.1105 Check Dam, Prefabricated-Temporary Foot 209.110601 Check Dam, (Ditch Bottom Width 0.0 to 3′), Stone-Permanent Each 209.110602 Check Dam, (Ditch Bottom Width >3′ to 6′), Stone-Permanent Each 209.110603 Check Dam, (Ditch Bottom Width >6′ to 10′), Stone-Permanent Each 209.110604 Check Dam, (Ditch Bottom Width >10′) Stone-Permanent Each 209.13 Silt Fence-Temporary Foot 209.1401nn Sediment Trap, Earth Berm-Temporary Each 209.1402nn Sediment Trap, Sand Bag-Temporary Each 209.1403nn Sediment Trap, Ditch Dam-Temporary Each 209.1501 Turbidity Curtain-Temporary Foot 209.160103 Pipe Slope Drain, 12" -Temporary Each 209.160105 Pipe Slope Drain, 18" -Temporary Each 209.160106 Pipe Slope Drain, 24" -Temporary Each 209.1701 Drainage Structure Inlet Protection, Silt Fence-Temporary Foot 209.1702 Drainage Structure Inlet Protection, Gravel Bag-Temporary Cubic Yard 209.1703 Drainage Structure Inlet Protection, Prefabricated-Temporary Foot 209.1704 Drainage Structure Inlet Protection, Concrete Block-Temporary Foot 209.1705 Drainage Structure Inlet Protection, Excavated-Temporary Foot 209.1801 Rolled Erosion Control Product, Class I Type A, Short Term Square Yard 209.1802 Rolled Erosion Control Product, Class I Type B, Short Term Square Yard 209.1803 Rolled Erosion Control Product, Class I Type C, Short Term Square Yard 209.1901 Rolled Erosion Control Product, Class II Type A, Intermediate Square Yard 209.190201 Rolled Erosion Control Product, Class II Type B, Intermediate Square Yard 209.190301 Rolled Erosion Control Product, Class II Type C, Intermediate Square Yard 209.1904 Rolled Erosion Control Product, Class II Type D, Intermediate Square Yard 209.200101 Turf Reinforcement Mats, Class III Type A, Permanent Square Yard 209.200201 Turf Reinforcement Mats, Class III Type B, Permanent Square Yard 209.200301 Turf Reinforcement Mats, Class III Type C, Permanent Square Yard 209.200401 Turf Reinforcement Mats, Class III Type D, Permanent Square Yard 209.2101 Soil Stabilizers, Class IV Type A Square Yard 209.2102 Soil Stabilizers, Class IV Type B Square Yard

209-5 11

NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 2026 Volume 2 209.22 Stabilized Construction Access Square Yard 209.2103 Soil Stabilizers, Class IV Type C Square Yard 209.2301 Sediment Filter Log, 12″ Foot 209.2302 Sediment Filter Log, 18″ to 20″ Foot 209.2303 Sediment Filter Log, 24″ Foot NOTE: nn denotes serialized pay item. These items will be paid for within established size groups.

Get an email when 209 changes

New York revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications (US Customary Units), 2026 (Jan) Edition. Pages 273–288 of 1,489. View official source ↗

Ask about this section

Scoped to New York Standard Specifications (Construction and Materials), Section 209 — Soil Erosion and Sediment Control. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.