563-2 05
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 563-2.05 Concrete. The concrete shall meet the requirements of §718 -06, High Performance Concrete For Precast a nd Prestressed Bridge Beams.
563-2.06 Diaphragms. The requirements of §718 -07 shall apply.
563-2.07 Grouted Reinforcing Bar Splice Sleeves shall meet the requirements of §709 -15 Grouted
Reinforcing Bar Splice Sleeves.
563-3 CONSTRUCTION DETAILS. The requirements of the P.C.C.M. shall apply.
563-4 Method of Measurement
563-4.01 Prestressed Concrete I -Beam Units. The quantity to be paid for under this work shall be the
number of feet (horizontal length center -to-center of bearings or anchor dowels, as shown on the plans) of each unit furnished and placed in accordance with the plans and specifications.
563-4.02 Prestressed Concrete Box -Beam Units and Hollow and Solid Slab Units. The quantity to be
paid for under this work shall be the number of square feet of plan area of each prestressed unit installed. Plan area is defined as the area bounded by the centerline of bearings and the outer edges of each prestressed unit. No deductions will be made for chamfers, shear keys, or notch cuts. Space between the units shall not be included in any measurement.
563-5 BASIS OF PAYMENT. The unit price bid for these units shall include all labor, materials , diaphragms,
and equipment necessary to complete the work except that bearings shall be paid for under their respective items. Damaged units which cannot be satisfactorily repaired or which do not meet dimensional and camber tolerances shall be replaced by the Contractor at no cost to the State. Progress payments will be made when each unit is furnished and placed in accordance with the plans and specifications exclusive of preparing and filling joints. Payment will be made at the unit price bid for 90% of the quantity properly placed. The balan ce of the quantity will be paid for upon completion of the work. The completion of work will include the correct preparation and filling of the joints as well as the tightening of transverse ties. Payment will be made under: Item No. Item Pay Unit 563.010X Prestressed Concrete I -Beam Units (Types 1 -6) Foot 563.02 Prestressed Concrete Box Beam Units Square Foot 563.03 Prestressed Concrete Hollow Slab Units Square Foot 563.04 Prestressed Concrete Solid Slab Units Square Foot 563.05 Prestressed Concrete New England Bulb Tee Units Foot X = Type Designation (1 through 6) SECTION 564 - STRUCTURAL STEEL (Last Revised May, 2019)
564-1 DESCRIPTION. This work shall consist of fabricating, furnishing and erecting structural steel
and other metal parts in accordance with the contract documents and as directed by the Engineer. The Contractor shall notify the Deputy Chief Engineer, Structures (DCES) of the name and address of the fabricator of all structural steel in accordance with §106 -01 Sources of Supply .
564-2 MATERIALS. Materials for this work shall meet the requirements of the New York State Steel
Construction Manual (SCM) and the following subsections of Section 700 Materials and Manufacturing :
564-2 01
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 Structural Steel 715-01 High Strength Bolts, Nuts and Washers 715-14 Pins and Rollers 715-15 Certified copies of the results of tests conducted by the manufacturer shall be furnished to the Engineer in accordance with the requirements of §715 -01 Structural Steel .
564-2.01 Structural Steel Replacement - Stock Steel Option. Stock steel may be furnished for
components that are not fracture -critical members (FCMs). For FCMs, stock material shall be supplied only with the approval of the DCES. If furnished, the stock steel shall comply with the provisions of §715 -01 Structural Steel . Positive heat identification will be required for all stock steel. Certified copies of the results of chemical analysis and physical tests shall be furnished to the Department.
564-3 CONSTRUCTION DETAILS. All structural steel work, including, but not limited to fabrication
inspection, transportation, and erection shall be performed in accordance with the provisions of the SCM. Shop inspection will be provided unless otherwise noted on the contract plans, or waived by the DCES. Shop drawings prepared for Structural Steel Replacement shall be prepared, approved and distributed in accordance with the provisions of the SCM, except that the term DCES shall be interpreted as the Engineer.
564-4 01
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 H. Repair of Defects in Welds and Base Metal. The Contractor shall repair defects found by visual inspection or nondestructive tests at no additional cost to the State.
564-4 METHOD OF MEASUREMENT. Castings, forgings, fasteners, anchor bolts for other than
bridge bearing installation, cables and other metal parts used in the permanent construction, will be measured as structural steel, even if made of other materials.
564-4.01 Pound. The quantity to be measured for payment will be in pounds to the nearest whole pound.
The weight of each shipping unit shall be clearly shown on the approved shop drawings.
564-4 02
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Sections 200 - 599 STANDARD SPECIFICATIONS (USC) January 1, 202 4 Volume 2 B. Computed Weight. The density of steel used in computing weights for payment will be assumed to be 490 pcf. The density of cast iron will be assumed to be 450 pcf. The weights of rolled shapes and of plates of all dimensions will be computed based on their nominal weights as required by the dimensions shown on the approved shop drawings. If the Contractor elects to use steel members with weights that are greater tha n the nominal weights specified on the approved drawings for its convenience, the computations will be based on the nominal weight values shown on the approved shop drawings. Deductions will be made for copes, cuts and all holes except those holes require d for high -strength bolts. The weights of castings will be computed from the dimensions shown on the approved shop drawings, with an addition of 10% for fillets and overrun.
564-4.02 Each. The quantity to be measured for payment will be made on an ‘Each’ basis.
564.4.03 Lump Sum. The work will be measured for payment on a lump sum basis.
564-5 Basis of Payment
The price bid shall include the cost of furnishing all labor, materials and equipment necessary to satisfactorily complete the work, not including bridge bearings and associated anchor bolts. Payment will be made under: Item No. Item Pay Unit 564.05XX Structural Steel (Type 01 -22) Lump Sum 564.10nnnn Structural Steel Replacement Pound 564.51nnnn Structural Steel Pound 564.70nnnn Structural Steel Replacement Each NOTE : nnnn denotes a serialized pay item. SECTION 565 - BRIDGE BEARINGS
565-1 DESCRIPTION. The work shall consist of furnishing, placing and setting bridge bearings at the
locations indicated on the plans. The Contractor shall notify the Deputy Chief Engineer, Structures (DCES) of the name and address of the fabricator of all bridge bearings in accordance with §106 -01 Sources of Supply.
565-1.01 Bearing Types. There are various types of bearings. The specific type required will be
indicated on the plans. Bearing types are: