101.04 17 Working Drawings include: Engineered Drawings , installation plans , certified drawings, and any other supplementary plans or similar data that the Contractor is required to submit for acceptance .
101.04 Interpretations. In order to avoid cumbers ome and confusing repetition
of expressions in these Specifications, it is provided that whenever anything is, or is to be, done, if, as, or, when, or where “contemplated, required, determined, directed, specified, authorized, ordered, given, designated, i ndicated, considered necessary, deemed necessary, permitted, reserved, suspended, established, approval, approved, disapproved, acceptable, unacceptable, suitable, accepted, satisfactory, unsatisfactory, sufficient, insufficient, rejected, or condemned,” i t shall be understood as if the expression were followed by the words “by the Engineer” or “to the Engineer.” 102 BIDDING REQUIREMENTS AND CONDITIONS
102.01 Prequalification of Bidders. A Bidder must be prequalified by the
Department according to ORC Chapt er 5525 and the rules and regulations governing prequalification in order to submit a Bid. Upon request, the Department will provide a prequalification application, applicable rules and regulations, and other relevant information. For prospective Bidders t hat are not yet prequalified, furnish the Department with a properly completed prequalification application at least 30 days before the date specified for the receipt of Bids. The prequalification certificate is the Bidder’s license to Bid and perform cons truction for the Department. For foreign Contractors, refer to ORC 5525.18 and Ohio Administrative Rule 5501:2 -3-07. The Department will perform contractor performance evaluations for each contractor and subcontractor on every ODOT -let construction project. Evaluations shall be well documented, objective, and performed in a timely manner, in accordance with Supplement 1131. The contractor’s average scores for the previous calendar year will be used in the calculation of the contractor’s bidding cap acity. The contractor has the right to appeal an evaluation .
102.02 Contents of Bid Documents. Use the Proposal to prepare and submit
Bids for the Work. Upon request, the Department will provide Bid Documents that include or reference the following:
102.04 Interpretation of Quantities in Proposal . The quantities in the Bid
Documents are approximate and the Department uses them for the comparison of Bids only. The Department will only pay the Contractor for the actual quantities of Work performed and accepted according to the Contract Documents. The Department may increase, decrease, or omit the scheduled quantities of Work as provided in 109.04 without invalidating the Bid prices.
102.05 Examination of Bid Documents and Project Site and Submission of
Prebid Questions. Carefully examine the Bid Docu ments and perform a reasonable site investigation before submitting a Bid. Submitting a Bid is an affirmative statement that the Bidder has investigated the Project site and is satisfied as to the character, quality, quantities, and the conditions to be en countered in performing the Work. A reasonable site investigation includes investigating the Project site, borrow sites, hauling routes, and all other locations related to the performance of the Work. When available, the Department will include in the Cont ract Documents or provide for the Bidder’s review at the Department’s offices or website, one or more of the following:
102.06 Preparation of Bids. Prepare a Bid according to this subsection and the
requirements found in the Bid Documents. Properly complete the Expedite file and submit it using the software specified in the Bid Documents rather than completing it by handwriting, typing, or using unauthorized computer -generated forms. Provide a unit price for each item listed in the Proposal. Calculate and place the products for the respective unit p rices and quantities in the “Bid Amount” column. For a lump sum item, place the same price in the “Unit Price” column and in the “Bid Amount” column pertaining to that item. Indicate the total Bid amount by adding the values entered in the “Bid Amount” col umn for the listed items. Submit the Expedite file using the software specified in the Bid Documents. Properly execute the Proposal by completing the miscellaneous section and attaching the required signatures in the space provided in the Expedite file. ENTITY SUBMITTING PROP OSAL REQUIRED SIGNATURE Individual The individual or a duly authorized agent. Partnership A partner or a duly authorized agent. Joint Venture A member or a duly authorized agent of at least one of the joint venture firms. Corporation An authorized officer or duly authorized agent of the corporation. Also, show the name of the state chartering the corporation and affix the corporate seal. Limited Liability Company A manager, a member, or a duly authorized agent.
102.07 Duty to Notify of Errors in Bid Documents. Notify the Department of
errors and omissions in the Bid Documents. Make notification by submitting a question in the manner described in 102.05. The Contractor’s duty to disclose errors and omissions is not only a biddin g requirement but is also a legal requirement that cannot be ignored. Failure to provide the required notification prior to the opening of bids shall constitute a waiver by the Contractor and does not obligate the Department for any costs based upon any a pparent or patent ambiguity arising from insufficient data or obvious errors in the Bid documents. Knowingly withholding information regarding an error or omission in the Bid Documents, or intentionally misrepresenting an item of Work for financial or comp etitive gain may result in civil or criminal penalties in excess of the value of the item bid.
102.08 Unbalanced Bidding. Bid all items correctly and price each quantity as
indicated in the Bid Documents. The Department will reject a Mathematically Unbalan ced Bid if the Bid is also Materially Unbalanced. A Mathematically Unbalanced Bid is a Bid containing lump sum or unit price items that do not include reasonable labor, equipment, and material costs plus a reasonable proportionate share of the Bidder’s ove rhead costs, other indirect costs, and anticipated profit. A Materially Unbalanced Bid is when the Department determines that an award to the 102.09 20 Bidder submitting a Mathematically Unbalanced Bid will not result in the lowest ultimate cost to the Department.
102.09 Proposal Guaranty. The Department will reject a Bid submitted
without a Proposal Guaranty in the amount designated and payable to the Director. Submit the required Proposal Guaranty in one of the following forms:
102.10 Delivery of Bid. Unless otherwise indicated in the Proposal, all Bids
must be submitted using the electronic Bid submission software specified in the Proposal. The Department will accept Bids until the time and date designated in the Notice to Bidders. The Department will return Bids rece ived after the designated time to the Bidders unopened. The Department will return all Bids not prepared and submitted in accordance with the Proposal.
102.11 Withdrawal of Bids. After Bids are opened, ORC 5525.01 requires that
a Bidder identify a mistake in its Bid within 48 hours of the Bid opening. After Bids are opened the Bidder must provide a written request to withdraw a Bid already filed with the Department. Any Bidder for whom a request to withdraw its Bid is approved by the Department will not be permitted to participate in any manner in a contract awarded for that project for which the Bid was withdrawn.
102.12 Combination Proposals. The Department may elect to issue Bid
Documents for projects in combination or separately, so that Bids may be sub mitted either on the combination or on separate units of the combination. The Department reserves the right to make awards on combination Bids or separate Bids to the best advantage of the Department. The Department will not consider combination Bids, other than those it specifically identifies in the Bid Documents. The Department will write separate Contracts for each individual Project included in the combination. 102.13 21 102.13 Public Opening of Bids. The Department will publicly open Bids at the time and place indicated in the notice to Contractors. The Department will announce the total Bid amount for each Bid. Bidders or their authorized agent and other interested persons are invited to the opening. The Department may postpone the receipt of Bid time or the op ening of Bids time. If the Department changes the hour or the date of the receipt of Bids or the opening of Bids, it will issue an addendum or public notice to notify prospective Bidders.
102.14 Disqualification of Bidders. The Department will declare a Bi d non -
responsive and ineligible for award when any of the following occur: