ITEM 209 LINEAR GRADING

209.01 Description. This work consists of performing linear grading within the specified

alignment detailed in the Contract Documents and within the grading tolerances. Use removed or excavated materials in the Work when the material conforms to the specifications; if not, then recycle or dispose of the material according to 105.16 and 105.17.

209.02 Materials. Furnish suitable materials as defined in 203.02.R.

209.03 Construction Requirements. Construct embankment and subgrade work according to

Items 203 and 204. When off-project-limit embankment material is needed for the work, an estimated quantity for Item 209 Borrow will be specified in the Contract Documents.

209.04 Ditch Cleanout. Reestablish the cross -section of the existing ditch. Use the required

embankment material to fill the eroded conditions. The compaction requirements specified in Item 203 do not apply.

209.05 Reshaping Under Guardrail. Reshape graded shoulders at locations where the existing

guardrail is removed or where the new guardrail is to be erected to ensure a smooth drainable surface free of all irregularities.

209.06 Preparing Subgrade for Shoulder Paving. Prepare the subgrade for shoulder paving by

excavating the existing shoulder material to the depth shown in the plan. Trim unsound or broken edges of asphalt concrete or concrete pavement to a line established by the Engineer . Remove any unstable material and shape and compact the subgrade. Compact the subgrade according to 204.03. Backfill areas graded in excess of the depth shown on the plans with Item 617 compacted aggregate at no expense to the Department. When preparing the subgrade for a safety edge, grade an area approximately 10 inches wide from the edge of the paved surface to remove vegetation and any high spots. Provide a surface free of vegetation and level with or slightly below the surface to be paved.

209.07 Grading Tolerances. Do not encroach on stream channels, impact wetlands, or extend

beyond construction limits, Right-of-Way or easement limits. Do not make alignment or profile grade adjustments that adversely affect drainage. Construct the work to the tolerances in 203.08.

209.08 Method of Measurement. The Department will measure Linear Grading, Reshaping

Under Guardrail, and Preparing Subgrade for Shoulder Paving by the number of either stations or miles completed and accepted, along each side of the pavement. The Department will not make deductions for intersections and other gaps. The Department will measure Ditch Cleanout by the number of feet measured along the centerline of the ditch. The Department will measure Borrow according to 203.09.

209.09 Basis of Payment. The Department will pay according to 109.05 for changes or extra

work that increases the haul distance by more than 1/2 mile to the work detailed in the Contract Documents. The Department will pay for additional quantities that increase the haul distance 1/2 mile or less at the unit bid price. The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 209 Station or Mile Linear Grading 209 Feet Ditch Cleanout 209 Station or Mile Reshaping Under Guardrail 209 Station or Mile Preparing Subgrade for Shoulder Paving 209 Cubic Yard or Ton Borrow 250 PAVEMENT REPAIRS

Get an email when 209 changes

Ohio revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.