ITEM 256 BONDED PATCHING OF PORTLAND CEMENT CONCRETE PAVEMENT
256.01 Description. This work consists of bonded patching of portland cement concrete
pavements at spall areas adjacent to cracks or joints or other areas of the pavement as designated by the Engineer . This work involves removing all loose and unsound concrete and asphalt material patches; removing sound concrete as directed; preparing the surface; applying a bonding grout if required; reconstructing the joint or crack; and mixing, placing, finishing, and curing of the patching material called out in the pay item description.
256.02 Materials. Furnish materials conforming to:
Portland cement ............................... 701.05 Fine aggregate .................................. 703.02 Coarse aggregate, No. 8 size ............ 703.02 Curing material ................................ 705.07 Air-entraining admixture ................. 705.10 Quick setting concrete mortar .......... 705.21
256.03 Equipment. Use a milling machine, concrete saw, jackhammers, or other approved
equipment to remove existing surface material. Provide oil and moisture free compressed air for cleaning and abrasive blasting the prepared area. Provide an on-site concrete mixer capable of mixing a minimum of 2 -cubic foot (0.06 m³) batches of patching material. Provide chipping hammers not heavier than the nominal 35-pound (16 kg) class.
256.04 Removal of Unsound Concrete . The Engineer will locate and mark all areas to be
repaired prior to concrete sawing. Provide the Engineer with aerosol spray paint to outline the areas for repair. Repair areas will be rectangular or square in shape with dimensions as required to envelope the surface deterioration. Saw the perimeter of all areas designated for removal to a depth of 1 inch (25 mm) to produce a vertical or slightly undercut face. Make additional saw cuts as required to facilitate removal. Remove all unsound concrete, all asphalt material, and all obviously loose and disintegrated concrete within the patch area. Remove sound concrete where required to achieve the minimum depth within the patch area. Remove concrete by jack hammering or milling. The minimum depth of any partial depth repair is 1 1/2 inch (38 mm) except at the perimeter saw cuts. Operate chipping hammers at an angle of less than 45 degrees measured from the surface of the pavement. During removal of unsound concrete, remove all pavement reinforcing exposed in the patch areas using a cutting tool or a torch.
256.05 Preparation of Patch Area. Before placing the patching material or before applying the
bonding grout, if used, abrasive blast the exposed concrete surfaces to which the patching material is to bond until free of loose particles, oil, dust, traces of asphalt concrete and joint seale r, and other contaminates. Do not begin abrasive blasting operations until implementing reasonably available engineering controls to limit fugitive dust that are acceptable to the Engineer . Conform to State, regional, and local government agency requirements regarding control of dust generated by the blasting operation. Remove all sandblasting residue with compressed air just prior to placing the patching material or just prior to applying the bonding grout, if used. For Types B and C patching materials that do not use water as the activator, perform additional surface preparation according to the patching material manufacturer’s recommendations. Recreate joints and cracks through or along the patch using a joint board that extends below the prepared surface and has a width equal to the existing joint or crack. One hour after placing the patching material, remove the joint board in a manner that does not damage the patch.
256.06 Bonding Grout Installation. For bonding Type A patches, use grout that consists of
equal parts, by volume, of portland cement and sand, mixed with sufficient water to form a stiff slurry. Using a stiff brush or broom, apply a thin, uniform coating of grout to the prepared surface. S crub the grout onto the dry surfaces of the prepared area to be patched immediately before placing the patching material. Do not allow excess grout to collect in low spots. Do not allow the grout to dry before placing the new concrete. Paint grout over all sawed joints between the patch and adjacent concrete immediately after completing the finishing. For bonding Types B and C patches, conform to the patching material manufacturer’s recommendations.
256.07 Placement of Patch Material. Use Type A, B, or C patch material as follows:
256.08 Curing and Opening to Traffic. Cure Type A patches according to 451.11, except allow
the patch to attain a modulus of rupture of 400 pounds per square inch (2.8 MPa) before opening to traffic. Cure Types B and C patches according to the manufacturer’s recommendations.
256.09 Method of Measurement. The Department will measure the quantity of Bonded
Patching of Portland Cement Concrete Pavement , Type ___ by the number of square feet (square meters) of the exposed surface of all patches, irrespective of the depth of the patch, repaired in the complete and accepted work. If the actual measured area of a patch is less than 2 square feet (0.2 m²), the Engineer will increase each such measurement to 2 square feet (0.2 m²).
256.10 Basis of Payment. The Department will pay for accepted quantities at the contract price
as follows: Item Unit Description 256 Square Feet Bonded Patching of Portland (Square Meter) Cement Concrete Pavement, Type ___
Get an email when 256 changes