General Provisions (00100-00999)

884Bridge Guardrail Retrofits

OK · 2019 Standard SpecificationsBook pages 920935View official source ↗

884.02 Bridge Guardrail Retrofits

882.06 Basis of Payment

The Department will pay for each p ay item at the contract unit price per the specified pay unit as follows: Pay Item: Pay Unit:

A.CHANGEABLE MESSAGE SIGN Each or Sign Day
B.REMOTE CONTROLLED CHANGEABLE MESSAGE SIGN Each or Sign Day Include the cost of the cellular telephone and telephone charges required for the remote -controlled sign in the contract unit price for Remote -Controlled Changeable Message Sign . The cellular phone will become the property of the Department. If the Contra ct includes an each pay item for Changeable Message Sign or Remote Controlled Changeable Message Sign , the portable changeable message signs will become the property of the Department upon completion of the Project. If the Contract includes a sign day pay item for Changeable Message Sign or Remote Controlled Changeable Message Sign , the portable changeable message signs will become the property of the Contractor upon completion of the Project. Include the cost of prov iding, placing at a location approved by the Resident Engineer, maintaining, and operating one changeable message sign for 1 day in the contract unit price for the relevant pay item.

884.01 Description

This work consists of providing and installing bridge guardrail retrofits.

884.02 Materials

Provide materials in accordance with the following sections and subsections Material: Section or Subsection: Portland Cement Concrete 701 Reinforcing Steel 723 Metal Guard Rail 732.01 Aluminum Alloy Tubes for Railings 732.03.C Cast Aluminum Alloy Bridge Railing Post 732.03 Pipe Railing 732.04 BRIDGE GUA RDRAIL RETROFITS 884.06

884.03 Equipment — Vacant

884.04 Construction Methods

Install bridge guardrail retrofits as shown on the Plans.

884.05 Method of Measuremen T — Vacant

884.06 Basis of Payment

The Department will pay for each pay item at the contract unit price per the specified pay unit as follows: Pay Item: Pay Unit:

A.BRIDGE GUARDRAIL RETROFIT Linear Foot [Meter]
B.BRIDGE PARAPET RETROFIT Linear Foot [Meter]
C.REMOVE BRIDGE RAIL AND POSTS Linear Foot [Meter] INDEX Description: A Section No.: Abbreviation and Acronyms ................................ ................................ ................................ ................... 101 ADA Compliant Tactile Warnin gs ................................ ................................ ................................ ............ 610 Adjustment of Existing Structures ................................ ................................ ................................ .......... 612 Aggregates ................................ ................................ ............... 101, 106, 301,303,317, 402, 403, 405, 410, ................................ ................................ ................................ .. 411, 433, 505, 509, 513, 521, 703, 707, 708 Aggregate Base ................................ ................................ ................................ 101, 220, 303, 326, 433, 703 Agricultural Liming ................................ ................................ ................................ .......... 230, 232, 234, 735 Aluminum Pipe ................................ ................................ ................................ ................................ ........ 613 Anti-Graffiti Coating System ................................ ................................ ................................ ................... 737 Approach Slabs ................................ ................................ . 105, 414, 501, 502, 504, 509, 515, 516, 523, 535 Arrow Display ................................ ................................ ................................ ................................ .......... 880 Asphalt Concrete Pavement (Hot Mix) ................................ .... 404, 407, 411, 413, 414, 426, 433, 708, 712 Asphalt Membrane Overlay ................................ ................................ ................................ .................... 505 Award and Execution of Contract ................................ ................................ ................................ ........... 103 Description: B Section No.: Backfill ................................ ................................ ............................. 105, 202, 209, 221, 228, 231, 310, 416, ................................ ................................ ................................ ......... 501, 502,508, 509, 510, 516, 517, 602, ................................ ................................ ................................ ......... 603, 609, 610, 611, 613, 615, 616, 619, ................................ ................................ ................................ ......... 623, 626, 628, 701, 703, 739, 802, 803, ................................ ................................ ................................ ................................ ................. 804, 849, 853 Backp lates (Traffic Signal) ................................ ................................ ................................ ............... 740, 833 Bale Barriers ................................ ................................ ................................ ................................ ............ 221 Bases ................................ ................................ ............................... 301, 303, 305,310, 317, 319, 325, 326, ................................ ................................ ................................ ......... 403, 405, 406, 408, 411, 414, 502, 613, ................................ ................................ ................................ ......... 629, 701, 702, 703, 707, 708, 712, 720, ................................ ................................ ................................ ......... 735, 802, 806, 807, 810, 811, 812, 834, ................................ ................................ ................................ ................................ ................................ . 836 Bearing Assemblies ................................ ................................ ................................ ......... 106, 506, 507, 724 Bidding Requirement s and Conditions ................................ ................................ ................................ ... 102 Bituminous Bases and Surfaces (Plant Mix) ................................ .................... 319, 403, 405, 406, 411, 707, ................................ ................................ ................................ ................................ ......................... 708, 735 Bituminous Binder ................................ ................................ ................................ .................. 403, 409, 703 Bituminous Prime ................................ ................................ ................................ ............................ 403, 408 Bituminous Surface Treatment ................................ ................................ ................................ ....... 403, 703 Blockouts ................................ ................................ ................................ ................................ ......... 611, 623 Bonded Portland Cement Concrete O verlay ................................ ................................ .......................... 414 Borrow ................................ ................................ ............................ 104, 106, 107, 201, 202, 208, 209, 220, ................................ ................................ ................................ ................................ ................. 501, 614, 705 Breakaway Bases – Highway Lighting ................................ ................................ ..................... 806, 807, 810 Bridge Decks, Approaches, Rails and Parapets ................................ ............... 501, 502, 504, 505, 506, 509, ................................ ................................ ................................ ......................... 510, 511, 513, 515, 523,535, ................................ ................................ ................................ ................................ 622, 624, 701, 720, 732, ................................ ................................ ................................ ................................ ......................... 853, 884 Bridge Deck Overlay ................................ ................................ ................................ ........ 504, 505, 701, 712 Bridge Deck Repair ................................ ................................ ................................ .................. 505, 513, 701 Bridge Guard rail Retrofits ................................ ................................ ................................ ....................... 884 Buy America ................................ ................................ ................................ ................................ .... 106, 506 Description: C Section No.: Cable Barrier (High Tension) ................................ ................................ ................................ ................... 628 Caliche Base ................................ ................................ ................................ ................................ .... 305, 703 Cast Iron Pipe ................................ ................................ ................................ .......................... 506, 613, 733 Cement Kiln Dust ................................ ................................ ................................ ............................ 307, 702 Cement Treated Base ................................ ................................ ................................ .............. 317, 703, 712 Cementitious Modified Subgrade ................................ ................................ ................................ ........... 307 Cementitious Stabilized Subgrade ................................ ................................ ................................ .......... 307 Chain Link Fence (CLF) ................................ ................................ ................................ ............ 512, 624, 732 Changeable Message Sign ................................ ................................ ................................ ............... 801, 882 Chip Seal ................................ ................................ ................................ ................................ .................. 403 Claims for Adjustment ................................ ................................ ................................ .................... 105, 109 Clay Plating ................................ ................................ ................................ ................................ ...... 202, 208 Clearing and Grubbing ................................ ................................ ..................... 201, 202, 220, 326, 501, 624 Cold Milling Pavement ................................ ................................ ................................ ............................ 412 Collection and Handling of Waste ................................ ................................ ................................ .......... 512 Concrete Brid ge Decks ................................ ................................ ................................ ............ 504, 505, 513 Concrete Culverts ................................ ................................ ................................ ............ 507, 508, 613, 726 Concrete Footings ................................ ................................ ........................... 502, 510, 624, 629, 804, 805, ................................ ................................ ................................ ................................ ................. 827, 851, 852 Concrete Joint Sealing ................................ ................................ ................................ ............. 415, 425, 518 Concrete or Bituminous Sidewalks, Driveways and Dividing Strip ................................ ................. 510, 610 Concrete Patching ................................ ................................ ................................ ................................ ... 416 Concrete Surface Finish for Structures ................................ ................................ ........................... 509, 737 Cone s ................................ ................................ ................................ ................................ ....................... 880 Construction Barricades ................................ ................................ ................................ .......................... 880 Construction Fabric ................................ ................................ ................................ ................................ . 712 Construction Signing and Traffic Control ................................ ................ 101, 104, 105, 107, 402, 403, 505, ................................ ................................ ................................ ................. 513, 801, 804, 810, 825, 831,857, ................................ ................................ ................................ ................................ ................................ . 880 Construction Signs ................................ ................................ ................................ .......................... 104, 880 Construction Zone Pavement Markings ................................ ................................ ................. 855, 856, 857 Continuously Reinforced Portland Cement Concrete Pavement ................................ ........................... 414 Contract Time ................................ ................................ .......................... 101, 104, 105, 108, 109, 514, 642, ................................ ................................ ................................ ................................ ................................ . 880 Contractor Construction Staking ................................ ................................ ................................ .... 105, 642 Control of Materials ................................ ................................ ................................ ................................ 515 Control of Work ................................ ................................ ................................ ................................ ...... 105 Controlled Low -Strength Material (CLSM) ................................ ................................ ...... 501, 510, 701, 703 Coordination of Plans, Specifications, and Special Provisions ................................ ................................ 105 Copper Water Pipe ................................ ................................ ................................ .......................... 616, 733 Cored Holes ................................ ................................ ................................ ................................ ..... 426, 516 Corporation Stops ................................ ................................ ................................ ................................ ... 616 Cover Aggregates ................................ ................................ ................................ ............................ 403, 703 Critical Path Method Schedule (CPM) ................................ ................................ ................................ .... 108 Crosshole Sonic Logging (CSL) ................................ ................................ ................................ ................. 516 Culvert End Sections ................................ ................................ ................................ ............................... 508 Curb and Gutter ................................ ................................ ................................ ...... 407, 411, 425, 510, 609 Curb and Drop Inlets ................................ ................................ ................................ ....... 101, 611, 612, 619 Curing Agents ................................ ................................ ........................... 317, 318, 416, 504, 509, 523, 701 Description: D Section No.: Deadman ................................ ................................ ................................ ................................ ................. 603 Definition of Terms ................................ ................................ ......... 101, 109, 220, 310, 512, 515, 517, 523, ................................ ................................ ................................ ................................ ................................ . 710 Delineators ................................ ................................ ................................ .............................. 104, 710, 853 Detour Bridge ................................ ................................ ................................ ................................ .......... 502 Diamond Grinding Concrete Pavement ................................ ................................ .......................... 425, 504 Disincentive f or Late Completion ................................ ................................ ................................ ... 101, 108 Ditch Liner Protection ................................ ................................ ................................ ............................. 229 Dividing Strips ................................ ................................ ................................ ................................ ......... 610 Dowel Bar Retrofit ................................ ................................ ................................ .......................... 416, 701 Dowel Jointe d Portland Cement Concrete Pavement ................................ ................................ ............ 414 Drainage Conduit ................................ ................................ ................................ ............ 510, 613, 615, 726 Drilled Shaft Foundations ................................ ................................ ........ 502, 503, 509, 510,516, 519, 852 Driveways ................................ ................................ ......................... 108, 440, 510, 610, 629, 707, 708, 802 Driven Foundation Piles ................................ ................................ ................................ .. 502, 503, 510, 514 Drums ................................ ................................ ................................ ...................... 107, 404, 512, 701, 880 Ductile Pipe ................................ ................................ ................................ ................................ ............. 616 Ductile Iron Pipe (DIP) ................................ ................................ ................................ ..................... 616, 726 Description: E Section No.: Earthwork ................................ ................................ ........................ 104, 201, 202, 203, 209, 220, 310, 402, ................................ ................................ ................................ ................................ . 501, 510, 614, 642, 802 Econocrete Base ................................ ................................ ................................ .............................. 318, 703 Edge Drain ................................ ................................ ................................ ................................ ....... 613, 703 Elastomeric Bearing Pads ................................ ................................ ................................ 506, 507, 724, 733 Elastomeric Mortar ................................ ................................ ................................ ......................... 518, 701 Elastomeric Coating System ................................ ................................ ................................ ............ 517, 737 Electrical Conductors ................................ ................................ ................................ .............. 738, 811, 834 Electrical Conductors (Highway Lighting) ................................ ................................ ............... 738, 811, 834 Electrical Conductors (Traffic Signals) ................................ ................................ ..................... 738, 811, 834 Electrical Conduit ................................ ................................ ..................... 709, 802, 803, 804, 808, 810, 852 Electrical – Mechanical Performance and Operational Tests ................................ ................ 801, 805, 811, ................................ ................................ ................................ ................................ ......................... 834, 852 Embankment ................................ ................................ ................... 104, 202, 203, 205, 209, 220,221, 326, ................................ ................................ ................................ ......... 501, 509, 510, 514, 516, 602, 613, 614, ................................ ................................ ................................ ................................ ......................... 619, 713 Emulsified Asphalt ................................ ................................ ................... 233, 403, 409, 410, 703, 707, 708 Epoxy Coated Rei nforcing Steel ................................ ................................ ....................... 106,509, 511, 516 Epoxy Resin ................................ ................................ ..................... 503, 509, 517, 520, 523, 623, 701, 736, ................................ ................................ ................................ ................................ ................................ . 858 Erosion and Sedimentation ................................ ............................. 101, 104, 105, 107, 220, 221, 228, 230, ................................ ................................ ................................ ......... 232, 233, 501, 502, 602, 701, 712, 713, ................................ ................................ ................................ ................................ ................................ . 735 Erosion and Sedimentation (Temporary) ................................ ................................ ............... 220, 221, 233 Excavation ................................ ................................ ............................... 104, 105, 201, 202, 205, 209, 220, ................................ ................................ ................................ ......... 221, 231, 310, 501, 502, 508, 510, 514, ................................ ................................ ................................ ................. 516, 601, 602, 603, 609, 610, 611, ................................ ................................ ................................ ......... 613, 614, 615, 616, 619, 620, 624, 628, ................................ ................................ ................................ .......................... 642, 703, 735, 802, 803, 804 Excavation and Backfill for Structures ................................ ............................. 201, 202, 501, 502, 508, 510 Excelsior Mat ................................ ................................ ................................ ........................... 229, 233, 735 Expansion Joints ................................ ................................ ............... 106, 504, 505, 506, 509, 518, 609, 610 ................................ ................................ ................................ ................................ ......................... 701, 724 Description: F Section No.: Fabric Reinforcement for Asphalt Concrete Pavement ................................ ................................ .......... 712 Falsework ................................ ................................ ........................ 104, 502, 503, 504, 506, 508, 509, 510, ................................ ................................ ................................ ................................ . 513, 514, 521, 619, 627 Fences ................................ ................................ ................................ .................... 107, 201, 221, 624, 625, ................................ ................................ ................................ ................................ ................................ . 732 Fertilizing ................................ ................................ ................................ ................. 230, 231, 232, 233, 234 Fiber Reinforcement for Concrete ................................ ................................ ................................ .......... 701 Field Office ................................ ................................ ................................ ...................... 106, 109, 640, 641 Filter Blanket ................................ ................................ ................................ ................................ ... 601, 713 Filter Fabric ................................ ................................ ................................ ......221, 510, 601, 602, 614, 712 Fire Hydrants ................................ ................................ ................................ ........... 104, 105, 612, 616, 733 Flagger ................................ ................................ ................................ ................................ ..... 104, 107, 880 Flexible Conduits ................................ ................................ ................................ ............................. 613, 726 Flexible Delineator Posts ................................ ................................ ................................ ......................... 710 Flood Coats ................................ ................................ ................................ ................................ ..... 515, 523 Fly Ash ................................ ................................ ............................. 307, 317, 318, 319, 349, 414, 426, 509, ................................ ................................ ................................ ................................ . 516, 701, 702, 707, 733 Fly Ash Modified Subgrade ................................ ................................ ................................ ..................... 307 Fog Seal ................................ ................................ ............................ 403, 405, 406, 407, 409, 411, 412, 413 Footings ................................ ................................ ........................... 101, 501, 502, 509, 510, 511, 514, 516, ................................ ................................ ................................ ......................... 501, 624, 628, 629, 804, 805, ................................ ................................ ................................ ................................ ........ 827, 849, 851, 852, Description: G Section No.: Gabions ................................ ................................ ................................ ....101, 220, 221, 602, 712, 713, 732 Galvanized Steel Pipe ................................ ................................ ....................... 516, 613, 721, 732, 733, 851 Galvanized Steel Sign Posts ................................ ................................ ................................ ..... 721, 827, 851 Gates ................................ ................................ ................................ ................................ ............... 624, 732 Geogrid Reinforcement ................................ ................................ ................................ .......................... 326 Geotextile Reinforcement ................................ ................................ ................................ ....................... 326 Glare Deflector Fence (GDF) ................................ ................................ ................................ ........... 624, 732 Glass Beads ................................ ................................ ................................ ..................... 711, 854, 855, 856 Granular Backfill ................................ ................................ ................................ .............. 501, 510, 613, 703 Ground Boxes ................................ ................................ ................................ ................................ .. 803, 852 Ground Granulated Blast Furnace Slag ................................ ................................ ................... 414, 701, 702 Guarantees and Warranties ................................ ................................ ............................ 106, 801, 825, 827 Guard Rail and Guide Posts ................................ ................................ ......622, 623, 624, 710, 732, 733, 884 Description: H Section No.: Handrailing ................................ ................................ ................................ ................................ .............. 504 High Density Concrete ................................ ................................ ................................ ............ 505, 513, 701 High Early Strength Concrete ................................ ................................ ................................ .................. 701 High Mast Lowering Device ................................ ................................ ................................ ............ 812, 813 High Mast Poles ................................ ................................ ................................ ...................... 806, 812, 813 Highway Lighting, Signals and Signing Electrical ................................ ............. 101, 738, 801, 805, 806, 807, ................................ ................................ ................................ ................................ ......... 810, 811, 834, 852 Hydrated Lime ................................ ................................ .......................... 234, 307, 411, 611, 706, 707, 735 Hydraulic Cement ................................ ................................ ............................. 105, 317, 505, 509, 624, 701 Hydrodemolition ................................ ................................ ................................ ............................. 505, 513 Description: I Section No.: Impact Attenuation Module (Sand Filled) ................................ ................................ .............................. 870 Incentive for Early Completion ................................ ................................ ............................... 101, 108, 109 Inlets ................................ ................................ ................................ ............................... 101, 106, 221, 425, ................................ ................................ ................................ ................................ ........ 501, 517, 611, 612, Description: J Section No.: Jacked Conduit ................................ ................................ ................................ ................................ ........ 613 Joint Filler and Sealants ................................ ................................ .. 414, 415, 416, 503, 504, 509, 510, 518, ................................ ................................ ................................ ................................ . 609, 610, 613, 701, 726 Junction Boxes ................................ ................................ ................................ ........ 611, 612, 726, 802, 811 Description: L Section No.: Laboratory ................................ ................................ ....................... 101, 106, 109, 307, 503, 512, 517, 620, ................................ ................................ ................................ ......... 640, 641, 701, 708, 711, 724, 730, 731, ................................ ................................ ................................ ................................ ......................... 733, 735 Lane Rental ................................ ................................ ................................ ................................ ..... 101, 108 Latex Modified Concrete ................................ ................................ ................................ . 505, 513, 515, 701 Legal Relations and R espo nsibility to Public ................................ ................................ ................... 107, 202 Lighting (Highway) ................................ ................................ .. 106, 738, 801, 805, 806, 807, 810, 811, 834, ................................ ................................ ................................ ................................ ................................ . 852 Lighting Poles and Mastarms (Highway) ................................ ................................ ......................... 810, 806 Lime ................................ ................................ ................................ ........................ 233, 234, 307, 411, 414, ................................ ................................ ................................ .................. 517, 523, 611, 706, 707, 708, 735 Lime Pretreatment ................................ ................................ ................................ ................................ .. 307 Lime Modified Subgrade ................................ ................................ ................................ ......................... 307 Lime Stabilized Subgrade ................................ ................................ ................................ ........................ 307 Longitud inal Barrier (Concrete) ................................ ................................ ................................ ...... 627, 877 Longitudinal Barrier (Portable) ................................ ................................ ................................ ............... 877 Loop Detectors ................................ ................................ ................................ ................ 738, 825, 828, 834 Luminaires ................................ ................................ ............................... 801, 805, 806, 807, 809, 810, 811, ................................ ................................ ................................ ................................ ......... 812, 813, 852, 880 Description: M Section No.: Machine Grading ................................ ................................ ................................ ................................ ..... 209 Magnesium Ammonium Phosphate Concrete ................................ ................................ ................ 517, 701 Mailboxes ................................ ................................ ................................ ................................ ................ 629 Manholes ................................ ................................ ................................ ........ 106, 108, 202, 407, 410, 411, ................................ ................................ ................................ ................................ 611, 612, 613, 615, 619, Masonr y Brick ................................ ................................ ................................ ................................ ......... 714 Material Certifications ................................ ................................ ........................... 105, 106, 109, 512, 614, ................................ ................................ ................................ ................................ ......... 720, 849, 870, 878 Materials for Guard Rail, Guide Posts, Bridge Rail, Miscellaneous Railing and Fences ................................ ................................ ................................ ................................ ...... 624, 732 Materials (M iscellaneous) ................................ ................................ ................................ ....... 616, 711, 733 Measurement and Payment ................................ ................................ ................... 105, 108, 109, 853, 858 Metals (Miscellaneous) ................................ ................................ ................................ ........................... 725 Meter Boxes ................................ ................................ ................................ ................................ ............ 612 Meter Installation ................................ ................................ ................................ ................................ ... 616 Microsurfacing ................................ ................................ ................................ ................................ ........ 707 Mineral Aggregate, Miscellaneous Uses ................................ ................................ . 410, 411, 703, 707, 708 Mobilization ................................ ................................ ................................ ............................ 108, 109, 641 Modified Subgrade ................................ ................................ ................................ ................................ .. 307 Modular Glare Screen ................................ ................................ ................................ ............................. 878 Monuments ................................ ................................ ................................ ................................ ..... 107, 626 Mowing ................................ ................................ ................................ ........................... 230, 231, 232, 241 Muck Excavation ................................ ................................ ................................ ................................ ..... 202 Mulching ................................ ................................ ................................ ................................ . 220, 233, 735 Multiple Layer Polymer Concrete Overlay ................................ ................................ ...................... 505, 703 Description: N Section No.: NESHAP Pre -Demolition I nspection and Notification ................................ ................................ ..... 619, 802 Non -Shrink Grout ................................ ................................ ................................ ............................ 623, 733 Notice to Proceed ................................ ................................ ............ 101, 103, 105, 108, 109, 220, 624, 801 Erosion Control Mat ................................ ................................ ................................ ........................ 228, 735 Description: O Section No.: Obliterating Abandoned Road ................................ ................................ ................................ 201, 202, 210 Opaque Sealers and Stains ................................ ................................ ................................ ...................... 737 Open -Grade Bituminous Base ................................ ................................ ......................... 319, 406, 411, 708 Open -Graded Friction Surface Course ................................ ................................ .................... 406, 411, 708 Open -Graded Portland Cement Concrete Base ................................ ................................ ...................... 703 Optically Programmed Adjustable Traffic Signal Heads ................................ ................................ ......... 832 Overhead Sign Structures ................................ ................................ ................................ ....... 106, 516, 852 Description: P Section No.: Painting ................................ ................................ ........................... 105, 106, 506, 509, 512, 514, 623, 721, ................................ ................................ ................................ ................................ ................. 724, 725, 730 Parapets ................................ ................................ ................................ ................................ . 504, 505, 506, ................................ ................................ ................................ ................................ ................. 509, 518, 622 Pavement Edge Drain Conduit ................................ ................................ ................................ ................ 613 Pavement Markers ................................ ................................ ................................ .................. 414, 736, 858 Pavement Markers (Construction Zone) ................................ ................................ ........................ 736, 857 Payment ................................ ................................ ................................ ................................ .................. 109 Pedestrian Push Button ................................ ................................ ................................ .......................... 830 Penetrating Water Repellent Treatment ................................ ................................ ................ 509, 515, 701 Permeable Friction Course (PFC) ................................ ................................ ............................ 405, 411, 708 Pier Mounted Pole Brackets ................................ ................................ ................................ ................... 808 Piles ................................ ................................ ................................ . 106, 326, 402, 404, 405, 501, 502, 503, ................................ ................................ ................................ ................................ . 510, 514, 701, 708, 724 Pile Load Test ................................ ................................ ................................ ................................ .......... 514 Pipe Railing and Miscellaneous Pipe Work ................................ ................................ ..... 504, 622, 732, 884 Pipe Underdrain ................................ ................................ ................................ .............. 510, 613, 703, 712 Plans and Working Drawings ................................ .......................... 101, 105, 414, 502, 503, 505, 506, 507, ................................ ................................ ................................ .......... 508, 510, 511, 514, 517, 616, 806, 812 Plant Inspection ................................ ................................ ................................ ...................... 106, 109, 506 Planting ................................ ................................ ................................ ............ 101, 228, 230, 231, 232, 735 Pneumatically Applied Mortar ................................ ................................ ................................ ................ 521 Poles and Mast Arms ................................ ................................ ............... 801, 805, 806, 807, 810, 812, 813 Polyethylene Pipe ................................ ................................ ................................ ........................... 613, 726 Polymer -Modified Emulsified Asphalt ................................ ................................ ................................ .... 404 Polyvinyl Chloride Pipe (PVC) ................................ ................................ ..602, 613, 615, 616, 709, 726, 732, ................................ ................................ ................................ ................................ ................. 733, 802, 825 Portland Cement ................................ ................................ ..................... 109, 307, 318, 319, 426, 509, 516, ................................ ................................ ................................ .................. 601, 610, 611, 701, 702, 707, 733 Portland Cement Admixtures ................................ ................................ ................................ . 414, 509, 701 Portland Cement Concrete ................................ ................................ .....319, 413, 414, 416, 425, 426, 502, ................................ ................................ ................................ ................. 504, 505, 509, 510, 513, 516, 520, ................................ ................................ ................................ ................. 609, 610, 611, 619, 623, 624, 626, ................................ ................................ ................................ ................. 627, 628, 629, 701, 702, 711, 733, ................................ ................................ ................................ .................. 736, 804, 810, 855, 856, 877, 884 Portland Cement Concrete Pavement ................................ .................... 414, 415, 433, 504, 609, 619, 701, ................................ ................................ ................................ ................................ ................................ . 733 Post Tensioning ................................ ................................ ................................ ............................... 105, 517 Power Supplies ................................ ................................ ................................ ................................ 805, 810 Preconstruction Conference ................................ ................................ ................................ ... 106, 108, 220 Presplitting of Rock ................................ ................................ ................................ ................................ . 202 Pressure Grouting Portland Cement Concrete Pavement ................................ ................................ ...... 426 Prestressed Concrete Beams ................................ ................................ ................................ .................. 503 Prestressed Concrete Deck Panels ................................ ................................ ................................ .......... 503 Prime Coat ................................ ................................ ................................ ........ 303, 307, 319, 403, 408, 737 Project Completion and Acceptance ................................ ................................ ............. 101, 105, 107, 108, ................................ ................................ ................................ ................................ ......... 109, 220, 403, 880 Processing Existing Base and Surface ................................ ................................ ..................... 303, 305, 311 Prosecution and Progress ................................ ................................ ................................ ...................... 108, Pull Boxes ................................ ................................ ................................ ....................... 739, 803, 805, 811, ................................ ................................ ................................ ................................ ................. 828, 834, 852 Description: Q Section No.: Quick Lime ................................ ................................ ................................ ................................ ....... 307, 706 Description: R Section No.: Rails ................................ ................................ ................................ ........................ 504, 505, 508, 509, 609, ................................ ................................ ................................ ................................ . 622, 623, 720, 732, 878 Railroad Approach Slabs . ................................ ................................ ................................ ........................ 414 Railroad Flagging ................................ ................................ ................................ ................................ ..... 104 Railroad – Highway Crossbuck Signs ................................ ................................ ................................ ....... 849 Rapid Cure Joint Sealant ................................ ................................ ................................ ................. 504, 701 Rapid Setting Cement ................................ ................................ ................................ ............................. 701 Reclaimed Asphalt Pavement ................................ ................................ ................................ ......... 707, 708 Regulatory or Warning Signs with Flashers ................................ ................................ .................... 825, 836 Reinforced Concrete Pipe (RCP) ................................ ................................ ...................... 106, 613, 615, 726 Reinforcing Steel ................................ ................................ ............. 101, 106, 108, 221, 318, 414, 501, 502, ................................ ................................ ................................ ......... 503, 504, 505, 508, 509, 510, 511, 513, ................................ ................................ ................................ ......... 514, 516, 517, 521, 603, 611, 623, 624, ................................ ................................ ................................ ......... 626, 627, 628, 723, 804, 810, 852, 877, ................................ ................................ ................................ ................................ ......................... 880, 884 Reinforcing Steel for Structures ................................ ...................... 502, 503, 504, 505, 508, 509, 510, 511, ................................ ................................ ................................ .......... 514, 516, 517, 521, 611, 624, 627, 810 Re-laying Culvert Pipe ................................ ................................ ................................ ..................... 613, 726 Removal and Storage or Reconstruction of Fencing, Guard Rail and Guide Posts ................................ . 625 Removal of Contaminated Soil ................................ ................................ ................................ ............... 620 Removal of Culvert Ends ................................ ................................ ................................ ......................... 508 Removal of Existi ng Bridge Structure ................................ ................................ ................................ ..... 619 Removal of Oil Field Equipment ................................ ................................ ................................ ............. 619 Removal of Pavement Markings ................................ ................................ ......105, 414, 711, 855, 856, 857 Removal of Structures and Obstructions ................................ ................................ ................................ 619 Removal of Traffic Items ................................ ................................ ................................ ......................... 805 Removal of Underground Storage Tanks ................................ ................................ ................................ 620 Retaining Walls ................................ ................................ ................................ .............. 202, 501, 502, 504, ................................ ................................ ................................ .................. 508, 510, 511, 518, 602, 622, 701 Retroreflective Sheeting ................................ ................................ .......... 628, 710, 719, 740, 833, 850, 880 Revetmen t Mattresses ................................ ................................ ................................ ............ 602, 713, 732 Rich Bottom Layer (RBL). ................................ ................................ ................................ ................ 411, 708 Right -of-Way Markers ................................ ................................ ................................ ............................. 626 Riprap ................................ ................................ ................................ ...................... 101, 220, 601, 712, 713 Roadside Development and Erosion C ontrol (Materials for) ................................ ................................ . 735 Rock Excavation ................................ ................................ ................................ .............................. 201, 202 Rock Filter Dams ................................ ................................ ................................ ............................. 221, 713 Rolling and Sprinkling ................................ ................................ .............. 203, 230, 305, 307, 310, 326, 403, ................................ ................................ ................................ ................. 404, 405, 406, 408, 411, 501, 506, ................................ ................................ ................................ ................. 509, 517, 703, 707, 708, 724, 732, ................................ ................................ ................................ ................................ ................................ . 880 Rubblizing Portland Cement Concrete Pavement ................................ ................................ .................. 433 Rumble Strip ................................ ................................ ................................ ................................ ............ 413 Description: S Section No.: Salvaging Topsoil ................................ ................................ ................................ ..................... 201, 202, 205 Sani tary Sewer Pipe Conduits ................................ ................................ ................................ ......... 612, 615 Saw-Cut Grooving ................................ ................................ ................................ ................................ ... 504 Sawing Pavement ................................ ................................ ................................ ................................ .... 619 Scope of Work ................................ ................................ ................................ ................................ . 102, 104 Sediment Control Basins ................................ ................................ ................................ ................. 221, 505 Sediment Control Filters ................................ ................................ ................................ ................. 221, 505 Sediment Removal . ................................ ................................ ................................ ................................ . 221 Sealer Crack Preparation ................................ ................................ ................................ ........................ 523 Sealer Resin ................................ ................................ ................................ ................................ ............. 523 Seeding ................................ ................................ ................................ ............. 220, 228, 232, 233, 234, 735 Select Borrow ................................ ................................ ................................ .................. 201, 202, 501, 705 Selective Clearing ................................ ................................ ................................ ................................ .... 201 Selective Subgrade Topping ................................ ................................ .................... 201, 202, 307, 310, 619 Separator Fabric for Bases ................................ ................................ ................................ .............. 625, 613 Shielded Loop Detector Lead -In Cable ................................ ................................ ................................ .... 834 Shrubs ................................ ................................ ................................ ................................ ............. 201, 231 Sidewalk ................................ ................................ ................................ ........... 101, 510, 610, 619, 622, 802 Sign Posts (Galvanized) ................................ ................................ ................................ ... 721, 836, 827, 851 Signs. ................................ ................................ ................................ ............................... 827, 836, 849, 851 Silica Fume ................................ ................................ ................................ .............................. 509, 701, 702 Silt Fence ................................ ................................ ................................ ................................ ......... 221, 712 Silt Dike ................................ ................................ ................................ ................................ ........... 221, 735 Slope Drains ................................ ................................ ................................ ................................ ............ 221 Slopewall ................................ ................................ ................................ ................................ ................. 510 Slurry Grout ................................ ................................ ................................ ................................ ..... 426, 733 Sodding ................................ ................................ ................................ ....220, 229, 230, 232, 233, 234, 735 Solid State Flashing Controller ................................ ................................ ................................ ........ 827, 836 Solid State Time Clock ................................ ................................ ................................ ............................. 827 Sound Barrie r Walls ................................ ................................ ................................ ................................ 510 Sprigging. ................................ ................................ ................................ ......................... 220, 230, 232, 735 Stabilized Subgrade ................................ ................................ ................................ ................................ . 307 Staking ................................ ................................ ................................ ............................. 105, 108, 231, 642 Standard Bedding Material ................................ ................................ ................................ ..... 501, 613, 703 Steel Jetty Bank Protection ................................ ................................ ................................ ..................... 603 Stone for Riprap, Filter Blanket and Gabions ................................ ................................ ......................... 601 Stone Matrix Asphalt (SMA) ................................ ................................ ................................ ........... 411, 708 Storm Water Pollution Prevention and Control ................................ ..................... 101, 107, 220, 221, 501 Stranded Wire Fence (SWF) ................................ ................................ ................................ ............ 624, 732 Strip Drains ................................ ................................ ................................ ................................ .............. 614 Structural Concrete ................................ ................................ ................. 502, 503, 504, 505, 508, 509, 510, ................................ ................................ ................................ ................. 513, 514, 516, 517, 520, 613, 624, ................................ ................................ ................................ .......................... 626, 627, 628, 733, 804, 810 Structural Concrete Repair by Sealing and Injection ................................ ................................ ...... 517, 520 Structural Excavation ................................ ................................ ................................ .............. 201, 202, 501 Structural Steel ................................ ................................ ........................ 105, 106, 109, 502, 503, 504, 506, ................................ ................................ ................................ ................. 511, 512, 514, 516, 521, 603, 611, ................................ ................................ ................................ ................. 719, 721, 724, 725, 730, 732, 802, ................................ ................................ ................................ ................................ ......................... 808, 813 Subbase ................................ ................................ ................................ ............ 101, 301, 303, 305, 310, 311 Subgrade ................................ ................................ ................................ .101, 105, 201, 202, 203, 208, 210, ................................ ................................ ................................ ................. 220, 301, 303, 305, 307, 310, 311, ................................ ................................ ................................ ................. 317, 319, 325, 326, 402, 408, 414, ................................ ................................ ................................ ................. 509, 510, 609, 610, 611, 613, 616, ................................ ................................ ................................ ................................ ......................... 619, 712 Subletting of Contract ................................ ................................ ................................ ............................. 108 Superpave ................................ ................................ ................................ ................................ ....... 411, 708 Supplemental Drawings ................................ ................................ ................................ .................. 615, 616 Surfaces ................................ ................................ ................................ ...307, 310, 311, 401, 402, 403, 404, ................................ ................................ ................................ ................. 405, 406, 407, 408, 409, 411, 412, ................................ ................................ ................................ ................. 413, 414, 415, 416, 425, 426, 433, ................................ ................................ ................................ ................. 707, 708, 802, 803, 855, 856, 857, ................................ ................................ ................................ ................................ ......................... 858, 870 Description: T Section No.: Tack Coat ................................ ................................ ......................... 403, 405, 406, 407, 409, 411, 412, 413, ................................ ................................ ................................ ................................ ................. 414, 505, 609 Tactile Warning Device ................................ ................................ ................................ ........................... 610 Temporary Concrete ................................ ................................ ................................ ....................... 502, 701 Temporary Lighting ................................ ................................ ................................ ................................ . 810 Temporary Structures ................................ ................................ ................................ ..................... 104, 502 Terminal Joints ................................ ................................ ................................ ................................ ........ 414 Test Rolling ................................ ................................ ................................ ................................ .............. 203 Timber and Lumber ................................ ................................ ......... 501, 502, 514, 517, 603, 619, 731, 732, ................................ ................................ ................................ ................................ ................................ . 735 Timber Piles ................................ ................................ ................................ ................................ ............. 603 Timber Preservatives and Treatment ................................ ................................ ............................. 731, 732 Timber Structures ................................ ................................ ................................ ........................... 501, 502 Traffic Bound Surface Course ................................ ................................ ................................ ......... 402, 433 Traffic Control ................................ ................................ ................. 101, 104, 105, 107, 405, 403, 505, 513, ................................ ................................ ................................ .................. 801, 804, 810, 825, 831, 857, 880 Traffic Signal Controller Assembly ................................ ................................ ................................ .. 825, 828 Traffic Signal Heads ................................ ................................ ................................ ......... 831, 832, 833, 836 Traffic Signal Poles and Mastarms ................................ ................................ .................. 806, 828, 830, 834 Traffic Signals ................................ ................................ .................. 738, 740, 801, 803, 805, 806, 807, 811, ................................ ................................ ................................ ......... 812, 825, 828, 830, 831, 832, 833, 834, ................................ ................................ ................................ ................................ ......................... 836, 852 Traffic Stripe ................................ ................................ ................................ .....711, 854, 855, 856, 857, 858 Traffic Surveillance (Police) ................................ ................................ ................................ ..................... 880 Trees ................................ ................................ ................................ ......... 104, 201, 202, 231, 326, 732, 735 Trench Excavation ................................ ................................ ................................ ................................ ... 613 Truck Mounted Impact Attenuators ................................ ................................ ................................ ....... 876 Tube Channelizers ................................ ................................ ................................ ........................... 736, 880 Description: U Section No.: Ultra -Thin Bonded Wearing Course ................................ ................................ ................................ ........ 404 Description: V Section No.: Valves ................................ ................................ ................................ ....... 401, 426, 517, 612, 616, 619, 733 Valve Boxes ................................ ................................ ................................ ............................. 612, 619, 733 Value Engineering ................................ ................................ ................................ ........................... 101, 104 Vertical Panels ................................ ................................ ................................ ................................ ......... 880 Vines ................................ ................................ ................................ ................................ ................ 231, 624 Description: W Section No.: Warning Lights ................................ ................................ ................................ ................................ ........ 880 Water for Port land Cement Concrete ................................ ................................ ................................ ..... 701 Water for Roadside Development and Erosion Control ................................ ................................ ................................ .....220, 221, 230, 231, 232, 233, 234 Water Pipe and Fittings ................................ ................................ ................................ ... 612, 616, 619, 733 Water Repellent ................................ ................................ ................................ ...................... 509, 515, 701 Watering ................................ ................................ ................................ .......... 108, 201, 202, 230, 231, 232 White Concrete ................................ ................................ ................................ ....................... 627, 701, 877 Wick Drains ................................ ................................ ................................ ................................ ............. 614 Wire Baskets for Gabions and Revetment Mattresses ................................ ................................ ... 602, 732 Wood Cellulose Fiber ................................ ................................ ................................ ...................... 233, 735 Woven Wire Fence (WWF) ................................ ................................ ................................ ............. 624, 732
Source: Oklahoma Standard Specifications for Highway Construction, 2019 Edition. Pages 920935 of 935.