00640Aggregate Base and Shoulders

OR · 2024 Standard SpecificationsBook pages 757758View official source ↗

00640.44 691 Section 00640 - Aggregate Base and Shoulders

Description

00640.00Scope - This Work consists of furnishing and placing one or more Courses of Aggregate

Base and/or Shoulders on a prepared surface to the lines, grades, thicknesses and Cross Sections shown or established.

Materials

00640.10Materials - Furnish Aggregates of either 1" - 0 or 3/4" - 0 as the Contractor elects. Use

clean, hard, durable Aggregates, reasonably well -graded from the maximum size to dust.

00640.16Acceptance of Aggregates - Acceptance will be visual by the Engineer

Construction

00640.40Preparation of F oundation - Provide a firm surface on which Aggregates are to be placed

according to Sections 00320, 00330, or 00610 as applicable .

00640.41Hauling and Placing - Transport the Aggregate to the Project Site , add water to obtain

proper moisture content, and place on the prepared surface or material by means acceptable to the Engineer. Do not place Shoulder Aggregates on the top Lift of newly constructed EAC or open-graded Pavement .

00640.42Thickness and Number of Layers:

(a)Base - If the required compacted depth of the Base Course exceeds 6 inches, construct it in

two or more layers of nearly equal thickness. The maximum compacted thickness of any one layer shall not exceed 6 inches .

Place each layer in spreads as wide as practicable and to the full width of the Course before a succeeding layer is placed.

(b)Shoulders - Place Shoulder Aggregates in a single layer, or two or more layers of nearly equal

thickness. The maximum compacted thickness of any one layer shall not exceed 9 inches.

00640.43Shaping and Compacting - Compact each layer of M aterial placed in Shoulder and Base

areas by rollers conforming in general to 00641.24 or as directed.

Shape and maintain the surface of each layer during the compaction operations to meet the requirements of 00640.44. Produce a uniform texture and firmly key the Aggregates.

Apply water over the Materials for proper compaction according to S ection 00340, and as directed. Continue the compactive effort until there is no reaction or yielding observed under the compactor.

00640.44Surface Tolerance - The finished surface and the surface of each underlying layer of the

Aggregate shall parallel the established grade and Cross Section for the finished surface within 0.04 foot.

00640.60 692 The finished surface of the compacted Aggregate Base , when tested with a 12 -foot straightedge, shall not vary from the testing edge by more than 1/2 inch at any point. Furnish and operate the straightedge as directed.

Maintenance

00640.60Care of the Work - After construction of each layer and completion of Base , maintain the

layer to specified conditions and prevent or repair segregation, raveling, or rutting, until it is covered with a following layer or until all Work is completed.

Measurement

00640.80Measurement - The quantities of Aggregate will be measured on the weight basis, in the

hauling vehicle.

Payment

00640.90Payment - The accepted quantities of Aggregates will be paid for at the Contract unit price,

per unit of measurement, for the following items: Pay Item Unit of Measuremen t

(a)Aggregate Base ..................................................................................... Ton
(b)Aggregate Shoulders ............................................................................. Ton

Payment will be payment in full for furnishing and placing all Materials, and for furnishing all Equipment , labor, and Incidentals necessary to complete the Work as specified.

No separate or additional payment will be made for water used to obtain proper compaction and in the care of the Work .

Source: Oregon Standard Specifications for Construction, 2024 Edition. Pages 757758 of 1,268.