General Conditions

00641Aggregate Subbase, Base, and Shoulders

OR · 2024 Standard SpecificationsBook pages 759763View official source ↗

00641.12 693 Section 00641 - Aggregate Subbase, Base, and Shoulders

Description

00641.00Scope - This Work consists of furnishing and placing one or more layers of Aggregates,

mixed with water, on a prepared surface to the lines, grades, thicknesses and Cross Sections shown or established.

Materials

00641.10Materials:

(a)Base and Shoulder Aggregate - Aggregate for Bases and Shoulders shall be sized as

specified. Bas e Aggregate shall be dense-graded unless otherwise specified. Shoulder Aggregates shall be either 1" - 0 or 3/4" - 0 size as the Contractor elects.

Furnish Base and Shoulder Aggregates meeting the following requirements:

Dense-Graded Base Aggregate ............................................................ 02630.10 Open-Graded Aggregate ....................................................................... 02630.11

(b)Subbase Aggregate - Aggregate for Subbases shall be crushed or uncrushed, including

Sands, reasonably well graded from coarse to fine. Maximum size Aggregate shall not exceed 75 percent of the compacted thickness of the layer in which it is incorporated. Aggregates passing the 1/4 inch sieve shall not be less than 10 percent nor more than 50 percent of the whole, by weight. No more than 10 percent of the Aggregate shall pass the No. 100 sieve. Within these limits, the Subbase Aggregate gradation shall be adequate to produce a dense, firm Base when placed and compacted.

(1)Grading - All of the grading requirements are given as percentages by weight. The

gradation will be determined by sieve analysis according to AASHTO T 27.

(2)Abrasion - The source materials for Aggregate Subbase shall not exceed 45 percent wear

when tested according to AASHTO T 96 unless otherwise approved.

(3)Sand Equivalent - Aggregate Subbase will be tested according to AASHTO T 176 and shall

have a Sand equivalent of not less than 25.

00641.11Stockpiling - If the produced Aggregates are to be stockpiled, prepare the stockpile site

and pile the materials according to 00680.40 and 00680.41.

00641.12Limits of Mixture - Provide a mixture of Aggregate and water having a uniform moisture

content sufficient to obtain the required compaction. Proportions will be in percentages by weight and will be known as the Mix Desi gn. Determine t he proportion of Aggregate and water according to

When introducing water at the mixing plant, furnish the mixture with a tolerance of ± 2 percent of the optimum water content at the time of mixing. If approved, excess percentage of water may be allowed. The Agency will treat excess percentage of water a ccording to 00641.80(d).

00641.15 694 00641.15 Quality Control :

(a)Aggregate Production Quality Control - Have a CAgT perform sampling and testing of

Aggregates. Statistically evaluate the Aggregates.

(b)Preproduced Aggregate - Compliance of Aggregates produced and stockpiled before

issuance of Notice to Proceed will be determined according to (1) or (2) below.

(1)Continuing production records.
(2)Sampling and testing the entire stockpile .

00641.16Acceptance of Aggregates - Acceptance will be accor ding to Section 00165

(a)Stockpiled Aggregate for Aggregate Base and Shoulders - Acceptance will be based on

the Contractor's quality control testing, if verified, as required in Section 00165.

(1)Aggregate Gradation - A stockpile contains specification Aggregate gradation when the

Quality Level (QL) for each sieve size, calculated according to 00165.40, is equal to or greater than the QL in Table 00165-2 for a PF of 1.00. Each required sample represents a sublot. When the QL in Table 00165-2 yields a PF of less than 1.00 for any sieve size, the material is non-specification.

(2)Non -specification Aggregate Gradation - Stockpiled Aggregates having non- specification

Aggregate gradation will be rejected unless the non-specification material is removed from the stockpile. Do not add additional material to the stockpile until enough non- specification material has been removed so that the QL for each sieve size is equal to or gre ater than the QL in Table 00165-2 for a 1.00 PF.

No payment will be made for non -specification materials.

(b)Aggregate Base and Shoulder Mixture - Acceptance testing will be performed on random

samples obtained immediately following mixing with water according to Section 00165. For non-specification mixture the Engineer will determine the appropriate price reduction or order its removal from the Work according to 00150.25.

(c)Aggregate Subbase - Aggregate Subbase will be accepted based on the Engineer's visual

inspection. Samples will be obtained and tested for compliance with 00641.10 by the Engineer if it is suspected that the material does not meet Specifications.

Equipment

00641.20Mixing Plant - Mix Aggr egate and water by one of the following methods:

(a)Mixing Plant - Mix with a pug mill, rotary mixer, or other Equipment at a mixing plant that:

• Has adjustable weighing or calibrated feeders, and other Equipment that produces uniform, non-segregated, specified mixtures. • Discharges water into the mixer by weighing or metering. The device shall be adjustable and shall assure uniform water content in the mixture. • Has mixing blades or paddles of proper size, adjustment and clearance to provide uniform mixture.

(b)Road Mix - Motor grader or other suitable Equipment .

00641.43 695

00641.21Hauling Equipment - Provide mixture hauling vehicles capable of hauling and depositing

the mixture with a minimum of mix segregatio n.

00641.22Spreading Equipment - Provide Equipment capable of spreading the M aterial and striking

it off to designated line, grade, and transverse Slope without segregation, dragging, or fracture of Aggregate.

00641.24Compacting Equipment - Provide self -propelled rollers and compactors capable of

reversing without backlash. Rollers and compactors shall have a gross static weight of at least 8 Tons, and shall be capable of compacting to specified density while the mix is still moist.

Labo r

00641.30Quality Control Personnel - Provide technicians having CEBT, CAgT, and CDT technical

certifications. Construction

00641.40Preparation of Foundation - Provide a firm surface or material, on which Aggregates are

to be placed, according to Sections 00320, 00330, or 00610 as applicable.

00641.41Mixing, Hauling, and Placing - Add water to the Aggregate while mixing to provide a

moisture content according to 00641.12.

Thoroughly mix the combined Aggregate and water for as long as necessary to produce a homogenous mixture with all Aggregate particles uniformly coated with water. Mix, haul and place the Material by one of the following methods:

(a)Stationary Mixing Plant - Combine Materials in a pug mill or rotary mixer.

Deliver and deposit the mixture without delay. Deliver the mixture to the spreading Equipment by direct deposit into its receiving device, or by placing in uniform windrows in front of the Equipment .

(b)Road Mix - Place Materials for each layer, add water and mix with motor grader until

homogeneous mixture is achieved.

Do not place Aggregate shoulder material on the top Lift of newly constructed EAC or open- graded Pavement .

00641.42Placing Aggregate Base or Subbase on Geotextile - When Subgrade or drainage

geotextile is required between the Subgrade and Base , place the first Lift of Material directly on the fabric, without road mixing.

00641.43Thickness and Number of Layers:

(a)Aggregate Base Courses - If the required compacted depth of the Base Course exceeds

6 inches, construct it in two or more layers of nearly equal thickness. The maximum compacted thickness of any one layer shall not exceed 6 inches unless approved.

Place each layer in spreads as wide as practicable and to the full width of the Course before a succeeding layer is placed.

(b)Aggregate Subbase Courses - The maximum compacted thickness of any one layer shall not

exceed 9 inches unless approved.

00641.44 696 (c) Shoulder Courses - Place Aggregates in Shoulder areas, other than as part of the Base Course, in one layer, or in two or more layers of nearly equal thickness. The maximum compacted thickness of any one layer shall not exceed 9 inches.

00641.44Shaping and Compacting :

(a)Aggregate Base Courses:
(1)Dense -graded Aggregates - Begin compaction of each layer of dense-graded Aggregates

immediately after the M aterial is spread and continue until a density of not less than 95 percent of the maximum density has been achieved.

(2)Open -graded Aggregates - Compact the surface of e ach layer of open-graded Aggregates

using rollers conforming to 00641.24. Roll until there is no appreciable reaction or yielding under the compactor. Shape and maintain the surface of each Aggregate layer during the compaction operations to produce a finished surface meeting the requirements of 00641.45.

Apply additional water over the M aterials for proper compaction, according to Section 00340 and as directed.

(b)Aggregate Subbase and Shoulder C ourses - Compact each layer of Aggregate Subbase

and Shoulder Material until no reaction or yielding is observed under the compactor.

00641.45Surface Tolerance - The finished surface of the Aggregate and the surface of each

underlying layer shall parallel the established grade and Cross Section for the finished surface within 0.04 foot. The finished surface of the compacted Aggregate, wh en tested with a 12- foot straightedge, shall not vary from the testing edge by more than 1/2 inch at any point. Furnish and operate the straightedge as directed.

Maintenance

00641.60Care of the Work - After construction of each layer and completion o f Base , maintain the

layer to specified conditions and prevent or repair segregation, raveling, or rutting until it is covered with a following layer or until all Work is completed.

Measurement

00641.80Measurement - The quantities of Aggregate mixture will be measured on the weight basis,

on the volume basis, or on the area basis according to the following:

(a)Weight Basis - When measurement is by weight, quantities will be measured in the hauling

vehicle, after mixing.

(b)Volume Basis - When mea surement is by volume, quantities will be measured in the hauling

vehicle.

(c)Area Basis - When measurement is by area, the quantity will be the number of square yards

of Aggregate Base constructed to the full thickness. The surface area will be determined by horizontal measurements. Each area constructed with varying thicknesses, as directed or shown, will be adjusted by converting it to an equivalent area at the Pay Item thickness on a proportionate volume basis. 00641.91 697

(d)Adjustment of Water in Mixture - If the water in the Aggregate mixture placed according

to 00641.41(a) exceeds the percentage established in the mix design by more than 2 percent, the excess percentage of water will be deducted from the measurement of the mixture. Determination of excess water will be made by the same procedure used in setting the water content of the Mix Design under 00641.12 or converted to the equivalent volume.

If Aggregates are stationary plant mixed, no separate measurement will be made for water added at the plant to bring the material to optimum moisture content.

If Aggregates are road mixed, water used to bring the mixture to optimum moisture content will be measured according to 00340.80.

Payment

00641.90Payment - The accepted quantities of Aggregates will be paid for at the Contract unit price,

per unit of measurement, for the following items:

Pay Item Unit of Measurement

(a)Aggregate Subbase ................................................................... Ton or Cubic Yard
(b)Aggregate Base ......................................................................... Ton or Cubic Yard
(c)____ Aggregate Base ............................................................... Ton or Cubic Yard
(d)Plant Mix Aggregate Base .......................................................... Ton or Cubic Yard
(e)Plant Mix ____ Aggregate Base ................................................. Ton or Cubic Yard
(f)Aggregate Shoulders ................................................................. Ton or Cubic Yard
(g)Aggregate Base, ____ Inches Thick ............................................... Square Yar d

Items (b) and (d) will apply when the Contractor has the option of furnishing one or another of two or more designated sizes of Aggregates.

In items (c) and (e), the designated size of Aggregate to be used will be inserted in the blank.

In item (g), the depth of Aggregate Base will be inserted in the blank. Payment will be payment in full for furnishing and placing all Materials, and for furnishing all Equipment , labor, and Incidentals necessary to complete the Work as specified.

No separate or additional payment will be made for water used in the mixture, mixed and placed according to 00641.41(a), subject to the limitations of 00641.80(d).

No separate or additional payment will be made for water used in the care of the Work according to 00641.60.

00641.91Material on Hand - Payment for stockpiled materials on hand may be allowed according

to 00195.60, subject to the requirements of 00641.10, 00641.15, 00641.16(a), and subject to QA verification.

Source: Oregon Standard Specifications for Construction, 2024 Edition. Pages 759763 of 1,268.