00710.00 712 Section 00710 - Single Appl ication Emulsified Asphalt Chip Seal Description
00710.00 Scope - This Work consists of applying Emulsified Asphalt and graded Aggregate s as
shown or directed. The chip seal design will be designated on the Plans or in the Special Provisions. Materials
00710.10 Aggregates - Furnish Aggregates meeting the following requirements:
00710.11 Emulsified Asphalt - Furnish polymer -modified Emulsified Asphalt or
non-polymer -modified Emulsified Asphalt as specified for the single application Emulsified Asphalt chip seal design designated in the Plans or Special Provisions. When non- polymer - modified Emulsified Asphalt is designated, the Contractor may elect to substitute a polymer -modified Emulsified Asphalt , however, selection of the polymer -modified Emulsified Asphalt will not be cause for additional compensation.
00710.15 Aggregate Production Quality Control - Provide sampling, testing, and quality control
during production of Aggregate according to Section 00165.
00710.16 Acceptance of Aggregate - The Contractors quality control tests will be used for
acceptance of Aggregates if verified by the Q uality Assurance Program. The Agency will perform Aggregate production quality assurance according to the following:
00710.20 Equipment - Provide a pressure distributor, hauling vehicles, chip spreader, compactors,
power brooms and other necessary Equipment to ensure efficient operation and construction to meet specified results. Provide Equipment in sufficient number and capacities that will provide coordinated and uniform progress of the Work . Provide two -way radio communication between the asphalt distributor and chip spreader. 00710.42
00710.21 Asphalt Distributor - Provide an asphalt distributor designed, equipped, maintained and
operated so the Emulsified Asphalt material may be applied uniformly at even heat. The distributor shall be capable of applying the asphalt on variable surface widths up to 16 feet, at readily determined and controlled rates from 0.05 - 2.0 gallons per square yard, and with uniform pressure. The variation allowed from any specified rate shall not exceed 0.02 gallons per square yard. Provide distributor Equipment that includes a tachometer, pressure gauges, accurate volume measuring devices and a thermometer for measuring temperature of t ank contents. Provide distributors equipped with a positive power unit for the asphalt pump, and full circulation spray bars adjustable both laterally and vertically. Set the bar height for triple lap coverage.
00710.22 Chip Spreaders - Provide self -propelled chip spreaders equipped with a mechanical
device that will spread the Aggregate at a uniform rate across the full width of the chip spreaders. Provide chip spreaders equipped with an Aggregate segregator assembly. Chip spreaders without an Aggregate segregator assembly may be allowed if approved by the Engineer. Provide chip spreaders of adequate width to provide full coverage of the specified P anel and without placing joints in the travel lanes.
00710.23 Compactors - Provide self -propelled pneumatic -tired or steel -wheeled rollers in good
condition and capable of operating at speeds compatible with the chip seal operation. A minimum of two pneumatic -tired rollers and one steel -wheeled roller is required.
00710.24 Power Brooms - Provide pickup or non- pickup type power brooms equipped with a
positive means to control vertical pres sure. Labor
00710.30 Quality Control Personnel - Provide a technician having a CAgT technical certification.
Construction
00710.40 Season and Weather Limitations - Do not apply Emulsified Asphalt when the Pavement
temperature is below 70 °F, or if the humidity is higher than 75 percent. Complete the application of the Emulsified Asphalt and the Aggregate 3 hours before sunset. Remove by milling, or other methods approved by the Engineer, and replace all chip seal s damaged by weather during the first 24 hours after application at no additional cost to the Agency. The placing of single application Emulsified Asphalt chip seal is not allowed before July 1 or after August 31.
00710.41 Rate of Progress and Scheduling - Do not apply more chip seal in any 1 Day than can
be broomed the following morning, unless approved by the Engineer. Provide a Traffic Control Plan for approval by the Engineer if operations exceed 3 centerline miles or 6 lane miles per Day .
00710.42 Preparation of Underlying Surfaces - Immediately before applying the Emulsified
Asphalt, clean and dry the surface to be treated in a manner approved by the Engineer. 00710.43
00710.43 Sequence of Operations - Construct the single application Emulsified Asphalt chip seal
with a single spread of Emulsified Asphalt followed immediately with a single spread of Aggregate and initial rolling, unless otherwise directed by the Engineer. Chip seal is not required for guardrail flares, driveways, or other irregular areas as directed.
00710.44 Application Rates - Apply the Emulsified Asphalt and spread the Aggregate within the
following ranges of rates for the specified chip seal design. The exact application and spread rate will be determined by the Engineer. Emulsified Asphalt Aggregate Chip Seal Design Application Rate Spread Rate (gal./sq. yd.) (cu. yd./sq. yd.) Fine 0.25 - 0.40 0.004 - 0.009 Single Size Medium 0.40 - 0.65 0.005 - 0.015 Graded Medium 0.40 - 0.65 0.005 - 0.015 Coarse 0.33 - 0.70 0.009 - 0.018
00710.45 Applying Emulsified Asphalt - Apply Emulsified Asphalt at the rates specified
in 00710.44 and according to the following: • Apply the Emulsified Asphalt working toward the Aggregate stockpile at all times, unless otherwise approved. • Leave a minimum of 200 gallons of Emulsified Asphalt in the distributor tank at all times. • Do not apply Emulsified Asphalt to more than one-half the width of the travel way at one time with the remaining width remaining open to traffic. Do not close the open lane until traffic controlled by pilot car is operating on the new chip seal. Apply the chip seal, weather permitting, to both sides of the travel way so that the end of the Work is squared up 3 hours before sunset. • Do not apply Emulsified Asphalt a greater distance than can be immediately covered by Aggregates before the emulsion breaks. • Place building paper over the treated surface at the beginning of each spread to ensure that the nozzles are operating properly before the uncovered surface is reached. Remove and dispose of building paper in a manner satisfactory to the Engineer. • If requested by the Engineer, demonstrate that the distribution of the Emulsified Asphalt does not vary between the individual nozzles by more than 15 percent transversely from the average, and no more than 10 percent longitudinally from the specified rate of application. • Apply the Emulsified Asphalt at a temperature between 140 °F and 185 °F as recommended by the manufacturer.
00710.46 Hauling and Spreading Aggregates - Spread Aggregates at the rates specified
in 00710.44. Do not operate hauling and spreading Equipment on uncovered Emulsified Asphalt. During the first hour after application of the Emulsified Asphalt and Aggregate, operate at speeds no more than 10 mph and after the first hour, not more than 15 mph until otherwise allowed by the Engineer. Carefully operate hauling Equipment at all times, at moderate speeds that will not damage the new chip seal or create a hazard to the traveling public. Route hauling Equipment and pilot lines as uniformly as possible over the full width of the new surface in place. Calibrate the gate opening, gear selection and engine RPM of the chip spreaders for the various sizes of Aggregate to be used. Following calibration, verify the rate of application by a method acceptable to the Engineer. 00710.80 Immediately cover the Emulsified Asphalt surface with Aggregate unless otherwise authorized by the Engineer. Maintain the rate of spread of this Aggregate within 10 percent of specified rate. Using approved methods, remove or repair Emulsified Asphalt that has set or "broke" before being covered with Aggregate, at no additional cost to the Agency. Aggregates shall be surface damp at the time of application. Excess free water (water not adhering to the Aggregate surface) on the Aggregate is not allowed. Do not operate the chip spreader at speeds which cause the chips to roll over after striking the emulsion covered surface. Provide Coverage without gaps or overlapping adjacent Coverages. Do not construct longitudinal joints within the travel lanes. Construct neat transverse cut off of Aggregates and remove any excess Aggregates from the surface prior to resuming operations.
00710.47 Shaping and Compacting - After the Aggregates have been placed on the Emulsified
Asphalt, spread or remove all piles, ridges, or uneven distribution to ensure against rough spots in the final surface. Compact the surface with a minimum of two Coverages with a pneumatic-tired roller and one Coverage with a steel-wheeled roller. Continue compacting until the Material is interlocked, firm and partially bound with the underlying Emulsified Asphalt. The sequence of roller Coverages may be adjusted at the discretion of the Engineer. Operate rollers at speeds such that the rollers do not pick up Aggregates from the surface. Do not exceed rolling speeds of 5 mph. In the event Aggregates begin to pick up under traffic or from the rolling operation, immediately cover and roll the area with additional quantities of Aggregate. Maintenance
00710.60 Power Brooming - Following the application of the chip seal, carefully broom the entire
surface to remove loose Aggregate. Discontinue the operation if brooming damages the chip seal. Use a minimum of two power brooms. Subsequent brooming the following 2 Days may be directed by the Engineer to ensure that the surface is free of loose Aggregate that could cause vehicle damage. In curbed areas, use a pick-up type power broom. On Bridges, sidewalks and other areas off the Roadway, remove all loose Aggregates to the satisfaction of the Engineer. Measurement
00710.80 Measurement - The quantities of Aggregate will be measured on the weight basis or on
the volume basis in the hauling vehicle. The quantities of Emulsified Asphalt will be measured on the weight basis. The quantities of asphalt chip seal of approaches will be measured on the unit basis for each street connection and road approach. 00710.90 Payment
00710.90 Payment - The accepted quantities of Work performed under this Section will be paid for
at the Contract unit price, per unit of measurement, for the following items: Pay Item Unit of Measurement