00745.02 769 Section 00745 - Asphalt Concrete Pavement - Statistical Acceptance
Description
00745.00Scope - This Work consists of constructing one or more Courses of hot mix or warm mix
asphalt concrete Pavement , plant mixed into a uniformly coated mixture, laid on a prepared foundation, compacted to specified density, and finished to a specified smoothness to the lines, grades, thickness, and Cross Sections shown or established.
00745.01Abbreviations :
Gmm - Maximum Specific Gravity of Mixture HMAC - Hot Mix Asphalt Concrete MAMD - Moving Average Maximum Density MDT - Maximum Density Test MDV - Mix Design Verification Pbe - Effective Asphalt Content RAM - Recycled Asphalt Material RAS - Recycled Asphalt Shingles SDC - Surface Damp Condition TSR - Tensile Strength Ratio Va - Air Voids in Compacted Mixture VFA - Voids Filled with Asphalt VMA - Voids in Mineral Aggregate WMAC - Warm Mix Asphalt Concrete
00745.02Definitions :
Asphalt Concrete Pavement - Uniformly coated mixture of asphalt cement, graded Aggregate, and additives as required. The use of ACP in this section refers to either hot mix or W arm Mx Asphalt Concrete. Hot Mix Asphalt Concrete - A hot plant mixed, uniformly coated mixture of asphalt cement, graded Aggregate and additives as required. Level 1 ACP - ACP for use in applications with very low traffic and only limited exposure to trucks. Level 2 ACP - ACP for use in applic ations with low traffic volumes and low volume truck traffic.
Level 3 ACP - ACP for use in applications exposed to moderate truck traffic. Level 4 ACP - ACP for use in applications exposed to very heavy traffic volumes or heavy truck traffic. Lot Size - A lot is the total quantity of M aterial or Work produced per JMF per Project . The following circumstances will require a different lot:
• A new JMF is used. A JMF adjusted according to 00745.16 is not considered a new JMF. • The method for measuring compaction is changed. • A new compaction specification limit is required according to 00745.49(b)(3). 00745.10 770 • A change from one test procedure for measuring asphalt content to another test procedure for measuring asphalt content occurs. • WMAC technology is used.
The Engi neer may allow Material for irregular areas not completed during the main paving operations, such as driveways or guardrail flares to be evaluated as a separate lot.
Recycled Asphalt Material - The combination of reclaimed asphalt Pavement (RAP) and recycled asphalt shingles (RAS).
Sublot Size - A sublot is 1,000 Tons of ACP. Surface Damp Condition - When the outside of the Aggregates are damp with moisture, but little or no free water is present.
Warm Mix Asphalt Concrete - An asphalt concrete mix following all requirements of HMAC, except that through use of approved additives or processes, it is mixed, placed, and compacted at lower temperatures.
Wearing Course - The top Lift of ACP, regardless of thickness.
Materials
00745.10Aggregate - When requested by the Engineer, supervisory personnel of the Contractor
and any Subcontractors who are to be involved in ACP Aggregate crushing shall meet with the Engineer at a mutually agreed upon time to discuss accomplishing all phases of the crushing Work .
following requirements:
Aggregate that will be used and the proposed targets for each individual sieve size for each stockpile. A minimum of one C oarse Aggregate and one F ine Aggregate stockpile is required. If the Contractor proposes to produce C oarse and Fine Aggregates in separateds izes other than those specified, request the proposed size changes in writing, and state the proposed target value and specified tolerance for each of the individual sieve sizes of the proposed Materials.
The number of Fine Aggregate separated sizes selec ted by the Contractor does not relieve the Contractor of providing a JMF and producing ACP meeting the air voids, VMA, and VFA requirements of 00745.13( a) and 00745.16(b)(1)(a). Perform recrushing, rescreening, or other special processing of the Fine Aggr egates necessary to achieve the air voids, VMA, or VFA requirements at no additional cost to the Agency.
Rock after it has passed through the primary crusher. The Material remaining may be accepted for use by visual inspection. The Engineer may perform verification testing of the gradation. The M aterial shall meet the following:
Sieve Size Percent Passing (by Weight) 8" 95 - 100 3/4" 5 max. 00745.10 771
12 percent when subjected to five cycles of the soundness test using sodium sulfate solution according to AASHTO T 104.
Test Test Method Aggregates ODOT AASHTO Coarse Abrasion T 96 30.0% Degradation Passing No. 20 sieve TM 208 30.0% Sediment Height TM 208 3.0"
fractured faces as determined by AASHTO T 335 as follows:
Percent of Fracture (by Weight) Material Retained on 1 1/2", 1", 3/4", 1/2" Material Retained and No. 4 Sieve on No. 8 Sie ve Type of Mix (two fractured faces) (one fractured face) All ACP 75 75
Test Test Method Aggregates ODOT AASHTO Coarse Fine Lightweight pieces T 113 1.0% Wood Particles TM 225 0.10% Elongated Pieces TM 229 10.0% (at a ratio of 5:1) Plasticity Index T 90 0 or NP Sand Equivalent T 176 45 min.
1 50 min. for Level 4 ACP
Material of similar characteristics.
Type of Asphalt Allowable Separated Sizes Concrete Mixture 1 1/4" - 3/4" 3/4" - No. 4 3/4" - 1/2" 1/2" - No. 4 1" ACP Yes Yes Yes Yes 3/4" ACP − Yes Yes Yes 1/2" ACP − − − Yes
Establish the target values for each allowable separated size after a maximum of 10 percent 00745.10 772 of planned stockpile quantity has been produced. Produce the Aggregate within the following listed tolerances (T):
Separated Sizes 1 1/4" - 3/4" 3/4" - No. 4 3/4" - 1/2" 1/2" - No. 4 Percent Passing (by Weight) Sieve Size T T T T 1 1/2" − 1 − − − 1 1/4" ± 5 − − − 1" ± 10 − 1 − 1 − 3/4" ± 5 ± 5 ± 7 − 1 1/2" − ± 8 ± 8 ± 5 3/8" * − − − − No. 4 ± 3 ± 8 ± 8 ± 8 No. 8 − ± 5 ± 5 ± 5 No. 16 * − − - − No. 30 ± 1 ± 3 ± 3 ± 3 No. 50 * − − − − No. 100 * − − − − No. 200 − ± 1.0 ± 1.0 ± 1.0
* Report percent passing sieve when no tolerance is listed
characteristics an d if allowed, blend Sand.
No. 4 - 0 No. 4 - No. 8 No. 8 - 0
Establish the target values for each allowable separate size after a maximum of 10 percent of planned stockpile quantity has produced. Produce the Aggregate within the following listed tolerances (T):
Separated Sizes No. 4 - 0 No. 4 - No. 8 No. 8 - 0 Percent Passing (by Weight) Sieve Size T T T 3/8" − 1 − 1 − No. 4 ± 7 ± 10 − 1 No. 8 ± 7 ± 7 ± 10 No. 16 * − − − No. 30 ± 7 ± 5 ± 8 No. 50 * − − − No. 100 * − − − No. 200 ± 3.0 ± 2.0 ± 4.0
* Report percent passing sieve when no tolerance is listed
00745.10 773 d. Combination of Fine Aggregate for Testing - Blend together Fine Aggregate produced in two separate sizes at a 1:1 ratio when testing for Sand equivalent.
Sand is allowed for Levels 1, 2, and 3 mixes. For these mixes, establish the target gradation and produce all Material within the following tolerances (T):
Percen t Passing (by Weight) Sieve Size T 3/8" − 1 No. 4 ± 5 No. 8 ± 15 No. 30 ± 20 No. 200 ± 5.0
Determine sieve analysis according to AASHTO T 27 and AASHTO T 11. Do not use more than 6 percent natural or uncrushed blend Sand, by weight, in the total Aggregate. Provide a means of verifying and documenting the amount of blend Sand added to the Aggregate.
No more than 30 percent RAP will be allowed in Level 1, Level 2, and Level 3 ACP. No more than 30 percent RAP will be allowed in Level 4 Base Courses. No more than 20 percent RAP will be allowed in Level 4 wearing Courses.
Establish the amount of asphalt cement in the RAP in the mixture design phase according to ODOT TM 319 and the ODOT Contractor Mix Design Guidelines for Asphalt Concrete or other method if approved by the Engineer. Additional testing may be requested at any time by the Agency or the Contractor during the production of the RAP mixture to verify the amount of asphalt cement in the RAP. Conduct new tests by a laboratory mutually agreed upon by the Agency and the Contractor. The part y requesting the additional testing pays the cost of the additional testing.
manufacturer waste (post -manufacturer) RAS or tear -off (post -consumer) RAS may be used. Manufacturer waste RAS is processed asphalt shingle Material derived from manufacturer's shingle scrap. Tear-off RAS is processed asphalt shingle Material derived from shingle scrap removed from Structures. All percentages are based upon dry weights for calculations.
100 percent of the shredded pieces are less than 1/2 inch in any dimension and that 90 percent are less than 3/8 inch in any dimension when sampled according to AASHTO R 90 and tested according to AASHTO T 27. Sample and test the processed RAS according to Se ction 00165.
the policies and procedures established by the Department of Environmental Quality. Test deleterious Materials according to ODOT TM 335 according to Section 00165. Limit the percentage of deleterious M aterials to 1.0 percent. If Fine Aggregate is added as an anti-clumping agent, sample and test processed RAS for harmful substances before adding the Fine Aggregates.
may be added to the RAS in a quantity not to exceed 4 percent by weight of RAS to keep the Material workable and to prevent conglomeration of the shingle particles in the stockpile. RAS may also be blended with RAP in controlled percentages to preclude clumping. Do not contaminate stockpiled RAS with dirt or other foreign materials. 00745.11 774
allowed in ACP mixtures. Restrict the maximum allowable percentage of asphalt binder replacement to 20.0 percent for Base Courses and 15.0 percent for wearing Courses in ACP containing only RAS.
When RAS is used in conjunction with RAP, restrict the maximum allowable percentage of binder replacement to 30.0 percent for Base Courses and 25.0 percent for wearing Courses.
addition of Fine Aggregate as an anti -clumping agent, test the Material according to ODOT TM 319 to establish the asphalt content, M aterial specific gravities, and gradation. Develop mixture designs according to the ODOT Contractor Mix Design Guidelines for Asphalt Concrete. Addi tional testing may be requested by the Agency or the Contractor at any time during the production of the RAS or RAM mixture to verify the amount of asphalt cement in the RAS or RAM. Conduct new tests by a laboratory mutually agreed upon by the Agency and the Contractor. The party requesting the additional testing pays the cost of the additional testing.
RAS, or RAM M aterial with new Aggregate to provide a mixture conf orming to the JMF within the tolerances specified. Have a CAT -I perform sampling and testing of RAP and RAS Aggregates according to Section 00165.
segregation and contamination, as much as possible, when stockpiling and removing the Aggregate.
Aggregates according to Section 00165 and the MFTP. Statistically evaluate the Aggregates according to Section 00165. Sample before treating with hydrated lime, when lime is required.
00165.
00745.11Asphalt Cement, Additives, and Aggregate Treatment - Furnish the following asphalt
cement, additives and Aggregate treatments:
asphaltce ment conforming to the requirement of ODOT's publication Standard Specifications for Asphalt Materials . Copies of the publication are available from ODOT's Pavement Services Engineer. The applicable Specifications are those contained in the current publi cation on the date the Project is advertised. PG 64 -22 or PG 64- 28 asphalt cement may be substituted for the grade of asphalt cement specified in the Contract for guardrail flares, mailbox turnouts, road approaches, driveways, and non -travel lane areas of restricted widths that are less than 8 feet wide, excluding Shoulders. Use of substitute asphalt cement for these areas will not require a new JMF.
are of known value for the intended purpose and approved for use on the basis of laboratory tests and capable of being thoroughly mixed. Do not use asphalt cement additives that have deleterious effects on the asphalt material. Do not use silicones as an additi ve. Add the following asphalt cement additives when required by the JMF:
00745.12 775 Anti-stripping asphalt cement additives to prevent stripping or separation of asphalt coatings from Aggregates to satisfy the TSR specified in 00745.13. Asphalt cement admixtures us ed to aid in the mixing.
When WMAC is used, select one of the WMAC technologies and process and additive types identified on ODOT's publication Approved WMAC Technologies .
Submit the proposed WMAC technology to be used and a plan for its implementation at the pre - construction conference.
Comply with the manufacturer's recommendations for incorporating additives and WMAC technologies into the mix. Comply with manufacturer's recommendations regarding receiving, storing, and delivering the additives.
or required to satisfy the TSR specified in 00745.13, treat new crushed Aggregates, except those in RAP, RAS, or RAM materials, with dry hydrated lime meeting the req uirements of Section 02090. Treat Aggregate as follows:
If the rates of a pplication specified in 00745.11(c)(2)(b) are not met, take corrective action. Document the corrective action and notify the Engineer.
before they enter the paving plant dryer.
moisture:
Hydrated Lime (%) 1.0 Lime Tolerance (%) - 0.2/+ 0.5 Moisture Content of Aggregate SDC
00745.12Mix Type and Broadband Limits - Furnish the mix type specified in the C ontract
Documents within the broadband limits according to the following:
two types for a Course of Pavement , use only one type throughout the Course.
below: 00745.13 776 Sieve Size 3/4" ACP 1/2" ACP 3/8" ACP Control Points (% passing by Weight) Control Points (% passing by Weight) Control Points (% passing by Weight) Min. Max. Min. Max. Min. Max. 1" 100 3/4" 90 100 100 1/2" − 90 90 100 100 3/8" − − − 90 90 100 No. 4 − − − − − 90 No. 8 23 49 28 58 32 67 No. 200 2.0 8.0 2.0 10.0 2.0 10.0
00745.13Job Mix Formula Requirements - Do not begin production of ACP for use on the Project
until the JMF is reviewed by the Engineer and written consent is provided to proceed. The JMF proposed for use on the Project will be evaluated based on the criteria identified in 00745.13( a) and .13(b) and the latest ODOT Contractor Mix Design Guidelines for Asphalt Concrete. A new JMF is required if the asphalt cement grade, any additives, or the source of the Aggregate change during production. A change in the source of asphalt cement requires a new passing TSR. Provide a range of proposed JMF targets to the CMDT. The CMDT will select targets from within the proposed range if all of the JMF requirements of 00745.13( a) are met.
A separate JMF will be issued for WMAC. Do not use RAS in WMAC m ixes with minimum compaction temperatures less than 260 °F.
When WMAC is used, provide the following information in addition to the requirements listed for HMAC:
• WMAC technology and WMAC additives information. WMAC technology manufacturer's established r ecommendations of usage. WMAC technology manufacturer's established target rate for water and additives, and the acceptable variation for production. WMAC technology material safety data sheets if applicable. Temperature range for mixing. Temperature range for compacting. Except for foaming technology, asphalt binder performance grade test data of the asphalt binder and chemical additive at the manufacturer's recommended dosage rate. Except for foaming technology, WMAC mixture performance test results. Perform testing for foaming technology on the production mix on specimens compacted at WMAC compaction temperatures.
Have a CMDT prepare, sign and submit a JMF to the Engineer for each mixture required at least 10 Calendar Days before the anticipated use in ACP, and according to the latest copy of the ODOT Contractor Mix Design Guidelines for Asphalt Concrete. If requested, submit material samples at least 10 Calendar Days before use.
00745.14 777 (a) Job Mix Formula Requirements - Provide a JMF meeting the following mixture requirements:
Level 1 Level 2 Level 3 Level 4 Design Method Superpave Superpave Superpave Superpave Compaction Level 65 Gyrations 65 Gyrations 80 Gyrations 100 Gyrations Air Voids, % 3.5 4.0 4.0 4.0 VMA, % minimum 1/2 inch - 14.0 3/4 inch - 13.0 3/4 inch - 13.0 3/4 inch - 13.0 3/8 inch - 15.0 1/2 inch - 14.0 1/2 inch - 14.0 1/2 inch - 14.0 3/8 inch - 15.0 3/8 inch - 15.0 3/8 inch - 15.0 VMA, % maximum min + 2.0% min + 2.0% min + 2.0% min + 2.0% P No. 200 / Eff. AC ratio 0.8 to 1.6 0.8 to 1.6 0.8 to 1.6 0.8 to 1.6 TSR, % minimum 80 80 80 80 VFA, % 70 - 80 65 - 78 65 - 75 65 - 75 3/8 inch: 70 - 80 3/8 inch: 70 - 80 3/8 inch: 70 - 80 3/8 inch: 70 - 80
submittal shall include the results of performance testing as outlined in the latest ODOT Contractor Mix Design Guidelines for Asphalt Concrete.
00745.14Tolerances and Limits - For gradation, measure the sieves with a weighting factor of one
or more according to 00745.95. Produce and place ACP within the following JMF tolerances and limits:
Gradation Constituent 3/4" 1/2" 3/8" 1" JMF ± 5% * 3/4" 90 - 100% JMF ± 5% * 1/2" JMF ± 5% 90 - 100% JMF ± 5% * 3/8" ** − − 90 - 100% No. 4 JMF ± 5% JMF ± 5% JMF ± 5% No. 8 JMF ± 4% JMF ± 4% JMF ± 4% No. 16 ** − − − No. 30 JMF ± 4% JMF ± 4% JMF ± 4% No. 50 ** − − − No. 100 ** − − − No 200 JMF ± 2.0% JMF ± 2.0% JMF ± 2.0% * Maximum not to exceed 100 % ** Report percent passing sieve when no tolerance is listed
Constituent of Mixture ACP Asphalt Cement - AASHTO T 308 (Ignition) and ODOT TM 323 JMF ± 0.50% RAP Content - ODOT TM 321 JMF ± 2.0% RAS Content - ODOT TM 321 JMF ± 1.0% RAM Content - ODOT TM 321 JMF ± 2.0% Moisture content at time of discharge from the mixing plant - AASHTO T 329 0.80% max.
00745.16 778 When a JMF tolerance applies to a constituent, full tolerance will be given even if it exceeds the control points established in 00745.12(b). Full tolerance will be given for RAP content even if it exceeds the limits established in 00745.10(b). Full tolerance will be given for RAS or RAM content even if it exceeds the limits established in 00745.10(c).
Take corrective action when the RAP, RAS, or RAM content , or the moisture content at time of discharge from the mixing plant, exceeds the above tolerance. If the RAP , RAS, or RAM content , or the moisture content at time of discharge from the mixing plant, continues to be outside tolerance, stop production until a plan for corrective action is approved by the Engineer.
00745.16Asphalt Concrete Pavement Production QC /QA - Provide sampling, testing, and quality
control of ACP according to Section 00165 and the following:
and according to the following:
• Obtaining samples with certified technicians. • Having all testing, data analysis and reporting of test results performed by a CAT -I. • Having a CAT -II available to evaluate and reconcile laboratory and field test results, submit required forms within required timeframes, and make necessary process adjustm ents. • Providing at least one CAT -I full -time at each plant site when producing mixture for the Project. • Providing access to laboratory facilities, technicians, and test results to the Engineer at all times during the production and testing process.
laboratory. Furnish the laboratory with the necessary Equipment and supplies for performing Contractor quality control testing. Calibrate all testing Equipment according to t he required test methods. The Engineer may inspect measuring and testing devices to confirm both calibration and condition.
The laboratory shall be operational before beginning the ACP production and be equipped with a telephone or cellular telephone, if either service is available. Provide laboratory Equipment meeting the requirements of the applicable test methods identified in the Specifications and selected for use on the Project .
randomly selected samples for each design mixture. Do not obtain the first sample of the Day in the first 25 Tons of production. If the rando m number indicates that the sample is to be obtained in the first 25 Tons, sample at 25 Tons. In addition, test the asphalt content at least once during each Day of production. This requirement may be waived by the Engineer.
Provide "QC Program" sampling and testing frequencies (random numbers) to the Engineer before starting production. Provide QC test results to the Engineer by the middle of the following work shift.
Stop production when the pay factor for any constituent with a weighting factor greater than one falls below 0.75. Resume production when a plan for correction is accepted by the Engineer.
00745.16 779 (5) Plant Calibration - Calibrate all meters and belt scales at the ACP mixing plant according to ODOT TM 322 before beginning production.
verification (MDV) tests on the HMAC as required at start -up according to 00745.16(b)(1)(c ). Two consecutive MDV test results from testing of HMAC shall be within the limits of 00745.16(b)(1)(a). The Engineer may waive ODOT TM 306 for HMAC production required before WMAC production for one shift. Perform MDV tests on every sublot and as required at start up according to 00745.16(b)(1)( c) and Section 00165. Perform gradation and asphalt content testing with each MDV test. Calculate the following values for each MDV test:
• Air Voids • Voids in Mineral Aggregate (VMA) • Voids Filled with Asphalt (VFA) • Passing No. 200/Effective Asphalt Content (Pbe) Ratio The running averages of four MDV results shall be within the limits given below:
Average of Limit Air Voids 4 samples JMF Target ± 1.0% VMA 4 samples 12.5 - 17.0 (3/4" Mix) 13.5 - 17.0 (1/2" Mix) 14.5 - 17.0 (3/8" Mix) VFA 4 samples 65 - 75 (3/4" and 1/2" Mix in Level 3 and 4) 65 - 78 (3/4" and 1/2" Mix in Level 2) 70 - 80 (1/2" Mix in Level 1 and 3/8" Mix in Levels 1 - 4) Passing No. 200/Pbe 4 samples 0.8 - 1.6
from the initial control strip to the CAT -II for evaluation and comparison with the MDV results at the completion of the control strip. If the MDV and density test results are contradictory, inform the Engineer and initiate an investigation. The CAT -II shall recommend a plan to the Engineer for resolving the discrepancy based on the results of the investigation. Submit results of investigation and plan no later than the end of two shifts after investigation has been initiated.
of the JMF production according to the following process:
testing.
00745.16 780 2. If the Va and VMA mix properties of 00745.16(b)(1)(a) are within tolerance, then continue subsequent MDV testing at the established random QC sublot interval. If not, then go to step "3".
mix adjustments within the requirements of 00745.16(b)(1)(d ) and immediately obtain another sample and perform MDV testing. Two adjustments will be given. If any of the test results for Va and VMA are not within the limits of 00745.16(b)(1)(a) after second adjustment, then stop production and go to step "4".
to the Engineer. Obtain the approval of the Engineer before restarting production. Production will be restarted with MDV testing according to this Subsection.
Use the initial MDV sample as the first random QC sublot test. Subsequent MDV samples required due to failure of start-up criteria will be used for a sublot QC test if the sample is taken within 100 Tons of the scheduled random QC sample location. If not, perform the MDV testing separate from, and not included in, the random QC testing program. Complete all required MDV testing at no additional cost to the Agency.
of 00745.16(b)(1)( c). After the requirements of 00745.16 (b)(1)(c ) have been met, take corrective action if the MDV test results show that two consecutive running averages of four samples are outside the limits for air voids, VMA, VFA, or P No. 200/Pbe ratio according to 00745.16(b)(1)(a). Document the corrective action and submit to the Engineer. If the subsequent MDV test results following the corrective action are outside the limits of 00745.16(b)(1)(a), immediately stop production and make adjustments. Restart production accordin g to 00745.16(b)(1)( c) only after th e Engineer has approved the proposed adjustments. If the MDV test results are outside the limits of 00745.16(b)(1)(a), but the mixture meets the current requirements for gradation and asphalt content, an adjustment to the JMF targets is required. A new l ot is not required as a result of the adjustment.
according to AASHTO T 283 on a sample obtained during the first 2 D ays of production after QC test results verify that ACP constituents with a weighting factor greater than one according to 00745.95 are in tolerance. Provide test results to the Engineer within 6 Calendar Days of obtaining the sample. Stop production and make adjustments if the TSR is less than 70. Restart production only after the Engineer has approved the proposed adjustments. The Engineer may waive Field TSR testing if the Contractor provides Field TSR data dated within the prior 3 months of the first MDV sample.
JMF targets may be made to the Engineer by the Contractor's CAT -II. The requested change will be reviewed and documented by the Engineer. If acceptable, a revised JMF will be allowed. Document the sublot test for which the adjusted targets are in effect. When making adjustments for gradation do not exceed the tolerances specified for the original JMF limits. Keep AC content adjustments for HMAC within 0.5 percent of the original JMF. Keep AC content adj ustments for WMAC within 0.3 percent of the original JMF. The JMF asphalt content may only be adjusted if the production VMA meets the requirements of 00745.16(b)(1)(a). Keep a djustments for RAP or RAM within 5 percent of the original JMF blend percentage, but do not exceed the requirements of 00745.10(b) or 00745.10(c). Adjusting proportions of the combined RAP and RAS is not allowed during production of the mixture. Keep adjustments for RAS content within 1 percent of the original JMF, but do not exceed the requirements of 00745.10(c). A gradation adjustment is required if the VMA is 00745.20 781 outside of the 00745.16(b)(1)(a) limits. Regardless of these tolerances, keep the adjusted JMF within the mixture specification control points of 00745.12. If a redesign of the mixture becomes necessary, submit a new JMF according to the Specifications .
Contractor's performing of MDV test procedures and calculations. Immediately correct any deviations from the specified test procedures. The Engineer may conduct MDV assurance testing at any time.
WMAC according to 00745.16 (b)(1)(a). Continued production and placement of WMAC will be allowed at the discretion of the Engineer.
to Section 00165. When QA testing is performed, the Contractor's quality control results will be used for acceptance if they are within acceptable limits of the QA test results as defined in the Quality Assurance Program.
00745.17Small Quantity Acceptance - When the quantity of ACP in a lot is less than 2,500 Tons,
the Engineer may accept the ACP according to Section 4(B) of the MFTP or by test results according to the following:
all constituents, including compaction, the Material will be accepted and the Contract unit price will be paid for the M aterial represented by that test.
specification limit the Engineer wil l have the backup sample tested.
within specification, the M aterial will be accepted and the full Contract unit price will be paid for the Material represented by that test.
the Contractor may choose to accept the price adjustment calculated according to 00745.95 or may choose to sample the in- place Material for further testing according to 00745.17(b)(3). The price adjustments will be computed using all original test results as well as all backup test results. If there are less than three tests, average the two tests and use the average as a third test result. The maximum composite pay factor (CPF) will be 1.0.
a minimum of three random locations from the area represented by the lot in question under the observation of the Engineer. If the in- place sample test results are within specification, the Material will be accepted and paid for at the full Contract unit price. If the in -place sample test results are not within specification, the Material will be accepted and paid for at an adjusted price according to 00745.95. The maximum CPF will be 1.0. Perform sampling and testing of in- place Material at no additional cost to the Agency.
Equipment
00745.20Lime Treated Aggregate Plant - When lime treated Aggregate is specified, pr ovide a
mixing plant that includes:
• A pug mill that mixes the Aggregate and lime until the Aggregate is uniformly coated and the lime is distributed throughout the Aggregate. 00745.21 782 • Provide a system for adding water to the pug mill if necessary to achieve Aggregate that is in SDC. This requirement may be waived by the Engineer if the stockpiled Aggregates are watered to the satisfaction of the Engineer. • A lime metering or weighing device that determines the amount of lime incorporated within any selected time period. Provide a device that is of sufficient accuracy to supply lime within the tolerances specified in 00745.11(c).
00745.21Mixing Plant - Provide ACP plants that comply with the following:
provide the Engineer with copies of all permits according to 00160.70.
according to 00190.30.
Aggregate, RAP, RAS, or RAM and lumps of cemented material that are detrimental to the mix.
the asphalt at the ACP mixing plant, provide a means to weigh or meter the additive at a specified rate that has an accuracy of plus or minus 0.5 percent.
• A direct reading, full operating range thermometer in the asphalt feed line near the mixer unit. • A thermometric instrument that automatically registers the temperature of the materials at the discharge of the mixer.
the quantity of material required for the appropriate tests when sampling at or around crushing, screening or mixing plants.
required by the manufacturer to introduce the WMAC technology. Plant modifications may include additional plant instrumentation, the installation of asphalt binder foaming systems and WMAC additive delivery systems, tuning the plant burner, and adjusting the flights in order to operate at lower production temperatures and reduced tonnage. Document the integration of plant controls and interlocks.
00745.22Hauling Equipment - Provide hauling vehicles in good operating condition with tight,
clean, smooth beds. Coat the beds with a minimum amount of an approved material to keep the ACP from sticking to the beds. Do not use diesel oil. Drain excess coating material before loading by raising the truck bed, opening belly dump gates, or operating the conveyor belt, as appropriate.
00745.23Pavers - Provide pavers that are:
• Self-contained, self -propelled, supported on tracks or wheels, none of which contact the mix ture being placed. • Equipped with augers and a screed, heated when necessary, which: • Can spread and finish the ACP to a uniform texture, in the specified widths, thicknesses, lines, grades and Cross Sections. • Will not segregate, tear, shove or gouge the ACP . • Equipped with a paver control system which: 00745.24 783 • Controls the ACP placement to specified Slope and grade. • Maintains the paver screed in proper position. • Provides the specified results through mechanical sensors and sensor -directed devices actuated from independent line and grade control references. • Equipped with adequate lighting to illuminate the paver and the R oadway in front of and behind the paver during the period from 30 minutes after sunset to 30 minutes before sunrise, or as directed. Shield lighting from adjacent traffic as necessary. Provide a minimum light level of 10 footcandles as measured by the Engineer on the Roadway surface at a distance of 16 feet from the front and back edges of the paver.
00745.24Compactors - Provide the specified self -propelled rollers capable of reversing without
backlash, as follows:
Level 1 and Level 2 Level 3 Level 4 Breakdown and Intermediate 8 Ton 10 Ton 12 Ton Finish 6 Ton 8 Ton 10 Ton
• Are equipped with amplitude and frequency controls. Are specifically designed to compact ACP. Are Capable of at least 2000 vibrations per minute. Have a minimum gross static weight meeting the requirements of 00745.24(a).
Do not operate in vibratory mode for Lifts thinner than two times the maximum Aggregate size for the type of ACP being compacted.
If vibratory rollers are used for finish rolling, they shall:
• Have a minimum gross static weight meeting the requirements of 00745.24(a). • Not be operated in the vibratory mode.
• Be tandem, or multiple axle, multiple wheel type. • Have smooth-tread, pneumatic tires of equal size. • Have tires staggered on the axles, spaced and overlapped to provide uniform compacting pressure for the full compacting width. • Have a minimum total load of 2,800 pounds per tire with tire inflation pressures of 45 psi to 90 psi • Be fully skirted to reduce tire heat loss and mixture pick up.
front of and behind each c ompactor during the period 30 minutes after sunset to 30 minutes before sunrise, or as directed. Shield lighting from adjacent traffic as necessary. Provide a minimum light level of 10 footcandles as measured by the Engineer on the Roadway surface at a distance of 60 feet from the front and back edges of each compactor.
00745.30 784 Labor
00745.30Quality Control Personnel - Provide technicians having CAgT, CAT -I, CAT- II, CDT, and
CMDT technical certifications.
Cons truction
00745.40Season and Temperature Limitations - Place ACP during the dates specified, and when
the temperature of the surface that is to be paved is not less than the temperature specified :
Nominal Comp acted All Levels Level 1 and Level 2 Level 3 and Level 4 Thickness of Individual Lifts and Courses as Travel Lane All Other shown on the typical All Courses Wearing Course Courses section of the Plans Surface From To From To From To Temperature* Inclusive Inclusive Inclusive
Less than 2 inches 60 °F All Year** 3/15 9/30 All Year** 2 inches - 2 1/2 inches 40 °F All Year** 3/15 9/30 All Year** Greater than 2 1/2 inches 40 °F All Year** 3/15 9/30 All Year**
Temporary 40 °F All Year** All Year** All Year**
* Do not use field burners or other devices to heat the Pavement surface to the specified minimum temperature unless approved. ** If placing ACP between March 15 and September 30, temperature requirement may be lowered 5 °F.
00745.41Prepaving Conference - Have a prepaving conference with all Contractor supervisory
personnel, all Subcontractors who are to be involved in the paving Work , and the Engineer. Meet at a mutually agreed time and discuss all methods of accomplishing all phases of the paving Work . When Level 3 and Level 4 mixes quantities are greater than 5,000 Tons include in the prepaving conference a Contractor representative who is responsible for Project quality control.
00745.42Preparation of Underlying Surfaces - All Bases and foundations on which the Pavement
is to be constructed shall meet the applicable Specifications and be approved before the start of paving. Recondition existing Bases and foundations according to Section 00610. Trim broken or ragged edges to firm material when directed.
Remove existing pavement markers, recessed markers, and pavement legends before paving. Remove pavement lines, bars, and pavement legends as shown or directed and according to 00225.45.
Level and compact depressed areas with ACP as specified or directed. Perform the Leveling Work as a separate operation and at the locations and to the extent as shown or directed. Spread the Leveling material with a paving machine, unless otherwise directed.
Treat all paved surfaces on and against which ACP is to be placed with an asphalt tack coat, according to Section 00730.
Treat all waterproofing membranes on and against which ACP is to be placed with an asphalt tack coat meeting the requirements of 00745.11(a) or as recommended by the membrane manufacturer.
00745.45 785 Protect all existing Structures from the overlay operation and check and clean as necessary after the overlay.
00745.43Drying and Heating Aggregates :
fuel so the Aggregate and asphalt are not contaminated and the asphalt is suitably aged.
by the JMF. Measure the mixture temperature at the discharge of the mixer. Measure the placeme nt temperature behind the paver. The allowable production temperatures may be adjusted based on the asphalt cement Supplier 's recommendation if approved by the Engineer. The maximum mixture temperature of the ACP and the minimum placement temperature sha ll be as follows:
AC Temperature °F Maximum Minimum Grading Type At Mixer Behind Paver HMAC 350 240 WMAC – 215 Within the above limits, the Contractor with approval of the Engineer, or the Engineer may adjust this temperature in 10 °F increments from the JMF as follows:
• Up - If the Aggregate coating, moisture content, workability or compaction requirements are not attained. • Down - If the Aggregate coating, moisture content, workability and compaction requirements are attained.
00745.44Asphalt Conc rete Pavement Storage - Temporary storing or holding of ACP in storage
silos will be allowed if the Contractor complies with the following:
stopping plant production, or at any other time necessary, so improperly proportioned mixture or incompletely mixed portions of the mixture do not enter the silo.
segregation of ACP as it enters the silo.
to placing is less than 6 hours.
atmosphere is maintained in the silo at all times which prevents damage to the mixture or asphalt properties.
prevented. If the ACP is segregated, dispose of segregated ACP and stop temporary storage of the ACP at no additional cost to the Agency.
00745.45Control of Line and Grade - Use a floating beam device of adequat e length and sensitivity
to control the grade of the paver. Where this method is impracticable, manual control of grade will be allowed when approved.
00745.46 786 00745.46 Hauling, Depositing, and Placing - Haul, deposit, and place ACP as follows:
and placement.
ACP wi ll be rejected before placing if one or more of the following occurs:
• Below temperature limit specified in 00745.43 • Slumping or separating • Solidifying
Dispose of rejected loads at no additional cost to the Agency. Deliver the mixture to the paving machine at a rate that provides continuous operation of the paving machine, except for unavoidable delay or breakdown. If excessive stopping of the paving machine occurs during paving operations, the Engineer may suspend paving operations until the mixtur e delivery rate matches the paving machine operation.
When ACP is windrowed, the pick -up Equipment shall:
• Pick up substantially all of the ACP deposited on the Roadway . • Be self -supporting, not exerting any vertical load on the paving machine, or causing vibrations or other motions which could have a harmful effect on the riding quality of the completed Pavement .
paver is impractical.
Do not place ACP during rain or other adverse weather conditions, unless allowed by the Engineer. ACP in transit at the time adverse conditions occur may be placed if:
• It has been covered during transit. • The ACP temperature is satisfactory. • It is placed on a foundation free from pools or flow of water. • All other requirements are met.
When Leveling irregular surfaces and raising low areas, do not exceed 2 inches actual compacted thickness of any one Lift, except the actual compacted thickness of intermittent areas of 1,000 square feet or less may exceed 2 inches, but not more than 4 inches. This may require portions of the mixture to be laid in two or more Lifts.
Place the mixture in the number of Lifts and Courses, and to the compacted thickness for each Lift and Course, as shown. Place each Course in one Lift unless otherwise specified. Do not exceed a compacted thickness of 4 inches for any Lift . Limit the minimum Lift thickness to four times the nominal maximum Aggregate size in the mix.
Do not intermingle ACP produced from more than one JMF. Each Base Course Panel placed during a working shift shall conform to a single JMF. The wearing Course shall conform to a single JMF, except for adjustments in the JMF according to 00745.16(b)(1).
00745.48 787 00745.47 Longitudinal Joints - At longitudinal joints, bond, compact and finish the new ACP equal to the ACP against which it is placed.
minimum. Offset the longitudinal joints i n one Panel by at least 6 inches from the longitudinal joints in the Panel immediately below.
or within 12 inches of the center of a lane, except in irregular areas, unless otherwise shown.
or directed.
• Provide warning signs and markings according to Sections 00221, 00222, 00224 and 00225 where abrupt or sloped edge drop-offs greater than 1 inch in height occur. • Protect edges from being broken down. If unable to complete the Pavement without drop-offs according to 00745.47(c) do the following:
• Construct and maintain a wedge of ACP at a Slope of 1V:10H or flatter along the exposed longitudinal joint. • Remove and dispose of the wedge before continuing paving operations. • Construct, maintain, remove, and dispose of the temporary wedge at no additional cost to the Agency. ACP for the temporary wedge will be paid for at the Contract unit price.
nominal thickness being laid as follows:
the area being paved, including Shoulders, is completed to the same elevation with no longitudinal drop-offs.
one Panel of new travel lane Pavement does not extend beyond the adjoining Panel of new travel lane Pavement more than the distance normally covered by each shift. At the end of each week complete the full width of the area to be paved, including Shoulders, to the same elevation with no longitudinal drop-offs.
00745.48Transverse Joints:
Courses, except Leveling Courses, as follows:
the selected transverse joint location, and from that point, wedge down on the appropriate Slope until the top of the Course being laid meets t he underlying surface (assuming a Pavement Course thickness of 2 inches) as follows:
• For wedges that will be under traffic for less than 24 hours, construct an 8 foot long wedge (1V:50H taper rate). • For wedges that will be under traffic for 24 hours or longer, construct a 25 foot long wedge (1V:160H taper rate). 00745.49 788 • Construct, maintain, remove, and dispose of the temporary wedge at no additional cost to the Agency. ACP for the temporary wedge will be paid for at the Contract unit price.
When the Pavement Course thickness is different than the above 2 inch example, use the appropriate taper rate to compute the length of the wedge. The wedge length plus the 4 feet or longer Panel form the temporary end Panel.
• Provide a smooth, vertical face the full depth of the Course being laid at the location selected for the joint by sawing, cutting or other approved method. • Remove the ACP material from the joint to the end of the Panel. If remove d before resuming paving beyond the joint, reconstruct the temporary end Panel immediately by placing a bond-breaker of paper, dust, or other suitable material against the vertical face and on the surface to be occupied by the temporary end Panel. Construct a full -depth Panel at least 4 feet long, beginning at the sawed or cut joint, and taper it on a 1V:50H Slope to zero thickness.
specified, dispose of unused, remaining AC P as directed. Payment will be made for the entire load of ACP, but will be limited to only one load for each joint of each Panel.
any bond- breakers. Clean the surfac e of all debris and apply a tack coat to the vertical edge and the surface to be paved.
with a straightedge placed across the joint, the joint surface shall conform to 00745.70.
in the longitudinal direction and either transverse or diagonal direction, as directed.
bridge decks, bridge end joints and approach slab end joints as soon as practical but within 48 hours of paving each stage of the wearing Course, unless otherwis e directed. Saw the cut 3/8 inch wide, ± 1/8 inch, by 1/2 inch less than the thickness of the Panel of Pavement depth or 1 1/2 inches deep, whichever is less. Flush the sawcut thoroughly with a high-pressure water stream after the cut has been made. Before the cut dries out, blow it free of water and debris with compressed air. Fill the sawcut joint with a hot applied joint sealant from the QPL.
00745.49Compaction :
defects remedied, roll it uniformly until compacted as specified.
temperature drops below 180 °F, unless otherwise directed or required based on the control strip. For WMAC, complete breakdown and intermediate compaction before the WMAC temperature drops below 160 °F. When the rolling causes tearing, displacement, cracking or shoving, make necessary changes in compaction temperature, type of compaction Equipment , and rolling procedures.
00745.49 789 (2) Rolling - Provide sufficient rollers of the types appropriate to compact the mixture while it is still within the specified temperature. Do not use equipment which crushes the Aggregate. Do not displace the line and grade of edges. Moisten steel roller wheels with a minimum amount of water, or other approved material, necessary to prevent the ACP from sticking to them and spotting or def acing the ACP.
Operate rollers at a slow, uniform speed recommended by the manufacturer. Drive rolls or wheels shall be nearest the paver unless otherwise approved. Operate pneumatic rollers no faster than 3 mph. Operate vibratory rollers at frequencies of at least 2,000 vibrations per minute.
Begin rolling at the sides and proceed longitudinally, parallel to the road centerline, gradually progressing to the center, unless otherwise directed. On superelevated curves, begin rolling at the low side and progress to the high side. When paving in echelon, or when abutting a previously placed lane, roll the longitudinal joint first, followed by the regular rolling pattern. Do not make sharp turns or park rollers on hot ACP. Stop each Pass at least 5 feet longitudinally from preceding stops.
Perform finish rolling with rollers meeting the requirements of 00745.24(a) or 00745.24(b), and continue until all roller marks are eliminated.
random testing of the compacted road surface with calibrated nuclear gauges. Use the MAMD method of compaction measurement.
Construct a control strip at the beginning of Work on each JMF o n the Project according to ODOT TM 306. The purpose of the control strip is to determine the maximum density that can be achieved for the JMF, paving conditions, and Equipment on the Project . Additional control strips are necessary when there is a change in compaction Equipment or when JMF targets are adjusted according to 00745.16(b)(1)(a). The Engineer may waive the control strip for irregular areas or areas too small to establish a reasonable roller pattern. Stop paving if three consecutive control strips fail to achieve the specified density. Take all actions necessary to resolve compaction problems. Do not resume paving until allowed by the Engineer.
A pneumatic tired roller is not required for Level 1 and Level 2 ACP. Have at least one available pneumatic tired roller conforming t o 00745.24(c) on the Project and in good operating condition for Level 3 and Level 4 ACP.
Have the CDT notify the Engineer and CAT -II when the average density for a sublot exceeds 95 percent of MAMD. Initiate an investigation to determine if the results indicate that a problem with the mix is developing. An adjustment to the JMF is not allowed unless MDV testing supports a required change.
performed at random locations with the nuclear gauge operated in the backscatter mode. Lots and sublots shall correspond with those defined in 00745.02. In addition, perform at least one density test each Day of production. The additional testing may be waived by the Engineer.
locate the center of a density test less than 1 foot from the Panel edge. Complete density testing before traffic is allowed on the new mat. 00745.49 790
Project for each Lift when requested or required. Perform core correlations and determine core correlation factors according to AASHTO T 355 and ODOT TM 327. Provide bulk specific gravity val ues to the Engineer within 24 hours of coring. If an Aggregate source or the asphalt cement source changes , new core correlations are required.
Apply correlation factors to all nuclear gauge readings for the Lift on which the core correlation was performed.
Both the Engineer and the Contractor may request additional core correlation of nuclear gauge readings . Core correlations requested by the Contractor or that are required due to a change in Aggregate or asphalt cement source will be at no additional cost to the Agency . The party requesting the core correlation pays the costs of coring and lab testing of the cores. The party performing nuclear gauge testing pays the costs of the nuclear gauge testing.
MDT and, if available, the four previous MDT's for the JMF used. Determine each MDT using the Gmm determined according to AASHTO T 209 and calculate the MAMD according to ODOT TM 305.
When this method is used, compact the ACP to at least the percent of the MAMD applicable for the mix type and Lift as follows:
Course of Construction ACP First ACP Lift less than 3 inches placed on Aggregate Base 91.0 * All other 92.0
* If any part of the width of a Lift at a station requires 91.0 percent, then the entire width of that Lift at that station shall be 91.0 percent
middle of the foll owing working shift.
or where the nominal compacted thickness of a Course of ACP will be less than 2 inches.
Perform breakdown and intermediate rolling unt il the entire surface has been compacted by at least four Coverages of the rollers. Perform additional Coverages, as directed, to obtain finish rolling of the ACP.
guardrail flares, mailbox turnouts, road approaches, Pavement repair, and areas less than 8 feet wide or limited length, regardless of thickness. Compact these surfaces according to 00749.45.
for ACP placed on bridge decks and approach slabs. Perform the same rolling pattern, without vibration, as established by 00745.49(b)(1). In the absence of a rolling pattern established by 00745.49(b)(1), perform b reakdown and intermediate rolling until the entire surface has been compacted by at least six Coverages of the rollers. Perform additional Coverages, as directed, to obtain finish rolling of the ACP.
00745.70 791 Temporary
00745.50Temporary Surfacing Course - Provide ACP for temporary Surfacing that is a
well-graded, uniform, durable commercial mix. All new Materials, or a combination of new Materials and reclaimed Materials, may be used, according to 00745. 10(b) . The Contractor is responsible for the quality of M aterial furnished according to Section 00165 and for maintaining the surface in a condition appropriate for the facility. Mix used for temporary Surfacing will not be eligible for price adjustment under 00745.95.
Maintenance
00745.60Correction of Defects - Correct all defects in Material and Work , as directed, at no
additional cost to the Agency, according to the following:
prevent full bond between successive Lifts of mixture.
oversized Material with fresh mixture.
occurring in the finished mat. If segregation continues to occur, stop production until a plan for providing uniform surface texture is approved.
additional fresh mixture or by other approved means.
constructed or when the elevation of the two sides of a longitudinal joint does not match. If problems with the longitudinal joint continue to occur, stop production until a plan for providing tight, equal elevation longitudinal joints is approved.
density is not being achieved.
• Is loose, broken, or mixed with dirt. • Shows visually too much or too little asphalt.
Finishing and Cl eaning Up
00745.70Pavement Smoothness - Furnish a 12-foot straightedge and, when required a 12-foot
rolling straightedge, and test as specified. Additional testing may be required. Mark areas not meeting the surface tolerance.
perpendicular to the centerline, as directed. The Pavement surface shall not vary by more than 1/4 inch.
and perpendicular to the centerline, as directed. The Pavement surface shall not vary by more than 1/4 inch. 00745.75 792
Course is placed according to 00745.70(a).
Test the wearing surface with the rolling straightedge in the designated wheel path of a 0.1 mile strip of each travel lane per mile, where directed, and on each transverse joint throughout the Project . Operate the rolling straightedge parallel to the centerline. The surface shall not vary more than 0.015 foot. Also test the wearing surface with a 12-foot straightedge placed perpendicular to the centerline at least once within the above- mentioned 0.1 mile strip. It shall not vary by more than 1/4 inch. If the 0.1 mile testing strip meets the Specifications, no further testing of the mile represented by the testing strip will be required, except at the transverse joints. If any part of the testing strip does not meet the Specifications, test both wheel paths of the entire mile.
covers, and valve boxes, the tolerances of 00745.70(a) and 00745.70(b) apply. If the Utility appurtenances are adjusted by others, these tolerances do not apply.
straightedge parallel to and perpendicular to the centerline for Shoulders and paved Medians where perm anent traffic barriers will be located. The Pavement surface shall not vary by more than 1/4 inch.
00745.75Correction of Pavement Roughness - Correct Equipment or paving operation
procedures when tests show the Pavement smoothness does not comply with 00745.70. In addition, do the following:
methods as approved by the Engineer:
• Profile to a maximum depth of 0.4 inch with Equipment meeting the requirements of 00620.20. • Profile to a maximum depth of 0.4 inch with abrasive grinders equipped with a cutting head comprised of multiple diamond blades. • Remove and replace the Base Lift.
• Remove and replace the wearing surface Lift . • Profile to a maximum depth of 0.3 inch with abrasive grinders equipped with a cutting head comprised of multiple diamond blades and apply an emulsion fog seal as directed.
notification, unless otherwise directed.
00745.90 793 Measurement
00745.80Measurement - The quantities of ACP will be measured on the weight basis, with separate
measurement being made for the asphalt concrete mixture and the asphalt cement contained in the mixture. No deduction will be made for lime or any other additive used in the mixture.
The quantities of ACP shown in the Contract Schedule of Items are based on the estimated bulk specific gravity of Aggregates listed in the Special Provisions . Determine the actual bulk specific gravity for the Aggregates, recompute the quantities of ACP to be used, and inform the Agency in writing. The quantities of ACP will be adjusted accordingly with no adjustment in Contract unit prices.
When listed in the Contract Schedule of Items, extra or additional Work for appr oaches, driveways, walks, and other miscellaneous asphalt appurtenances will be measured according to 00749.80 through 00749.82. If there is no separate item listed in the Contract Scheduled of Items for L eveling Work, the quantities will be included in t he appropriate ACP items.
Payment
00745.90Payment - The accepted quantities of ACP incorporated into the Project, whether or not
recycled Materials are used, will be paid for at the Contract unit price, per unit of measurement, for the following items: Pay Item Unit of Measurement
In item (a), the following will be inserted in the blanks:
• The level of ACP (1, 2, 3, 4) will be inserted in the first blank. • The type of ACP (3/4 inch, 1/2 inch, 3/8 inch) will be inserted in the second blank. • The words "Lime Treated" will be inserted in the third blank when applicable. • The words "in Leveling", "in Temporary", or "in Leveling and Temporary" will be inserted in t he fourth blank when applicable.
In item (b), the performance graded asphalt binder will be inserted in the first blank. The level and type of ACP will be inserted in the second blank. This item applies to all asphalt used in ACP, including residual asphalt in RAP, RAS, or combined RAP and RAS. Substituted asphalt cement described in 00745.11(a) will be paid for under the asphalt specified in the Contract Schedule of Items.
Payment will be payment in full for furnishing and placing all Materials, and f or furnishing all Equipment , labor, and Incidentals necessary to complete the Work as specified.
No separate or additional payment will be made for:
• reconditioning existing R oadway • Leveling Work • lime • QC testing • sawing, cleaning, and filling joints on bridge deck overlays 00745.95 794 When specified by other Pay Items in the Contract Schedule of Items, separate payment will be made for Work described in 00745.42, 00749.91 and 00749.92.
When a P anel consists of both temporary and permanent Courses, payment for the entire Panel will be based on the permanent Course .
Anti-stripping asphalt cement additives will be paid for at the Contractor's actual documented costs with no percentage allowance or markup allowed. No additional payment will be made for anti - stripping additives or treatments that are not anti -stripping asphalt cement additives.
00745.95Price Adjustments - The Composite Pay Factor (CPF), calculated according to 00165.40,
, and 00745.95, will be applied to the Contract unit price for Pay Items (a) and (b) of 00745.90
and to the applicable lot quantities. The CPF will be made available to the Contractor within 24 hours of receipt of the required quality control test results. If less than three samples are tested, the CPF will be computed as outlined in 00745.17 and 00745.95, the maximum CPF for Material represented by less than three samples will be 1.0.
To accommodate the lot definition of 00745.02, interpret the upper specification limit (USL) and the lower specification limit (LSL) in 00165.40 to allow adjustments to a JMF according to 00745.16 without changing lots. Include all Material from the original JMF and revisions of that JMF in the statistical analysis unless a change in the lot is required by 00745.02. If JMF target values are modified according to 00745.16, the CPF will be calculated in the following manner:
• The adjus ted target value will be evaluated as zero with the USL and LSL representing the allowable tolerances of 00745.14. All sample test values for the changed constituents will be compared to the target for each sublot. The differences between the target values and sample test values are the adjusted sample test values for each sublot. These will be analyzed for determination of the pay factor for the constituent. The Pay Factor (PF) for compaction will be:
Maximum Type/Method PF PF Normal Pavement Control Strip Method ........................................................ 1.00 MAMD Method ................................................................. 1.05 Thin Pavement ........................................... 1.00 Other Areas ................................................ 1.00 Use the following table to determine price adjustments in the CPF for constituents of ACP. 00745.95 795 Gradation Constituents All Aggregate Passing 3/4" 1/2" 3/8" 1 1/2" 1" 1 3/4" 1 1 1/2" 1 1 1 3/8" − − 1 No. 4 5 5 5 No. 8 5 6 6 No. 30 3 3 3 No. 200 12 12 12 Other Constituents Asphalt Content 28 28 28 Moisture Content * − − − Compaction 44 44 44 *Report moisture content to calculate the asphalt cement pay quantity
Those ACP constituents statistically evaluated will be eligible for a maximum PF of 1.05 (see 00165.50(b)(1)), unless otherwise specified.
When the CPF is greater than 1.000 for Material used in Leveling Courses for ACP, it will be reduced as follows: Reduction in CPF = (CPF -1) x 0.5
If the Specifications do not require measurement of a constituent, its individual PF will be considered 1.00 in calculating the CPF according to 00165.40.
A price adjustment will be determined by the following formulas:
(CPF - 1) x [(JMF% ÷ 100 x Asphalt Unit Price) + (ACP Unit Price)] x (LQ) = ____
Where:
JMF% is the asphalt cement % from the JMF LQ is the quantity of mixture in the lot