00867.00 888 Section 00867 - Transverse Pavement Markings - Legends and Bars Description
00867.00 Scope - In addition to the requirements of Section 00850, install pavement markings for
legends and bars according to the following Specifications. Labor
00867.30 Manufacturer's Representative - Provide a manufacturer's representative according
to 00850.30.
00867.31 Manufacturer -Certified Installers - Provide certified installer's according to 00850.31.
Construction
00867.45 Installation - Place permanent markings only when the manufacturer's representative
determines that the Pavement is ready for the pavement marking material . Transverse joints will be allowed with no overlap or gap allowed at the joint. Minimum initial retroreflectivity shall conform to the following: White - 250 mcd/m2/lx Yellow - 200 mcd/m2/lx Apply one or more of the following marking material types: • Type A: Liquid, Hot -Laid Thermoplastic Material - For pavement bars, apply the thermoplastic material to the Pavement by a spray or extrusion method, to the full width shown, in a single application. For pavement legends, apply the thermoplastic material to the Pa vement by a spray method, to the full width shown, in a single application. Pavement markings shall be 90 mils to 120 mils in thickness, exclusive of projecting surface-applied reflective elements, with a continuous and uniform cross sectional configurati on, and with the upper surface slightly arched. Separately apply reflective elements to the material as it is placed at a sufficient rate to obtain an initial reflectivity reading of 250 mcd/m2/lx. Locate the dispenser behind the pavement marking extrus ion die and uniformly distribute the reflective elements over the entire width of the thermoplastic material . • Type B: Preformed, Fused Thermoplastic Film - Install preformed, fused thermoplastic film as shown. • Type B-HS: Preformed, Fused Thermoplastic Film High Skid - Install preformed, fused thermoplastic film high skid, that has intermixed reflective elements with factory installed crushed glass or Aggregate on the surface for all staggered continental crosswalks, bicycle lane stencils, bicycle railroad crossings, lane reduction arrows, and other transverse pavement markings as shown. Install the preformed, fused thermoplastic film high skid to achieve a minimum initial skid resistance greater than or equal to 50 British Pendulum Number (BPN) when tested according to ASTM E303. • Type AB: Install Type A, Type B or Type B -HS as the Contractor elects . 00867.75 889 • Type C: Cold -Applied Plastic Film (Tape) - On asphalt, appl y the tape on the fresh asphalt concrete surface prior to final rolling of the mat. Roll the tape into the fresh surface during the finish rolling of the mat. On concrete, install tape with primer as recommended by the manufacturer. Apply Type C - HS, c old applied plastic film that has intermixed reflective elements with factory installed crushed glass or Aggregate on the surface. On asphalt, apply the tape on the fresh asphalt concrete surface prior to final rolling of the mat. Roll the tape into the fresh surface during the finish rolling of the mat. On concrete, install tape with primer as recommended by the manufacturer. • Type D: Methyl Methacrylate - Apply the methyl methacrylate material to the Pavement by a gravity and extrusion method, to the f ull width shown, in a single application. Pavement markings shall be 90 mils to 120 mils in thickness, exclusive of projecting surface -applied reflective elements, with a continuous and uniform cross -sectional configuration, and with the upper surface sli ghtly arched. Provide intermixed reflective elements. Separately apply reflective elements to the material as it is placed at a sufficient rate to obtain an initial reflectivity reading of 250 mcd/m 2/lx. Locate the dispenser behind the pavement marking extrusion die and uniformly distribute the reflective elements over the entire width of the methyl methacrylate material.
00867.75 Manufacturer Warranty - Furnish a manufacturer warranty that unconditionally warrants
to the Agency the product(s) and installation under this Section against failure, according to this Subsection and 00170.85(c)(1). Use Agency -supplied warranty forms, available from the Engineer. "Unconditionally warrant" means that the warranty c overs all failures, regardless of the source or cause of the failure, including, without limitation, whether the source or cause is or may be related to workmanship, inspection, or choice of materials. The Agency inspection of any portion of the Work during the Contract and during the product installation, the Agency acceptance of the Work , corrections under the warranty, or expiration of the warranty shall not relieve the obligations under this warranty.
00867.80 Measurement - The quantities of pavement legends will be measured on the unit basis, by
actual count. The quantities of pavement bars will be measured on the area basis, for each stop bar and crosswalk bar. Payment
00867.90 Payment - The accepted quantities of Work performed under this Section will be paid for
at the Contract unit price, per unit of measurement, for the following items: Pay Item Unit of Measurement