INTELLIGENT TRANSPORTATION SYSTEM (ITS) DEVICES

1202ATMS ITS DEVICE INTEGRATION

PA · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 1360–0 Save this section

Ask about Section 1202

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

1202.1DESCRIPTION—This work is the coordination and documentation activities required to facilitate

integration of ITS Devices into the Advanced Traffic Management System (ATMS) and to furnish information regarding the characteristics of all relevant ITS devices installed within the project . The ATMS is the common platform used by the Department to monitor, control , and utilize all functionalities of ITS devices installed within the Commonwealth. Work to integrate the ITS device(s) must be a collaborative effort between the Contractor responsible for installation of the ITS device(s), the construction services team, and the ATMS vendor. All coordination with the ATMS vendor must go through PennDOT’s Systems and Performance Unit in the Operations and Performance Section of the Bureau of Operations. The ATMS vendor, at no cost to the Contractor, will be responsible for performing the work to integrate the ITS device(s) into the ATMS. The Contracto r is responsible for furnishing all information pertaining to the ITS device(s) relevant to integration, as described herein, and as required by the ATMS vendor.

1202.2MATERIAL—

(a)Protocol Documentation. Furnish protocol documentation for all communication protocols used by

the ITS device(s).

(b)Integration Kit. Furnish integration kit (SDK, API, Software), if applicable, that the ATMS vendor

will need to integrate device(s). Furnish documentation for integration kit.

(c)Licenses. Furnish licenses, if applicable, to support the integration of the device(s) by the ATMS.
(d)ITS Device Configuration Information. Furnish all information required herein for the respective

device(s) being installed. Information must be provided for each device being installed as part of the ITS project. Omission of any information required for integration will be considered incomplete. If information is incomplete at the time of integration activities as identified by the project schedule or plan, it will be considered a delay of the project. All information must be provided in the format described herein, or as directed by the Representative. Provide information in matrices in Microsoft Excel or comparable format, subject to approval by the Representative. Furnish one matrix per type of device being installed as part of the project. Transmit information to the Department through the Representative via electronic communications such as email, CD-ROM, or as directed by the Representative.

(e)Device Vendor Point of Contact. Furnish point of contact for each device vendor.

1202.3CONSTRUCTION—

(a)General. Before the integration activities identified in the project schedule or plan, furnish the

information contained herein to ensure the successful integration of the ITS device (s). A template matrix identifying the integration information fields may be available from the Representative. This information is required to be provided to the ATMS vendor as soon as it is available. Systems Acceptance Testing will not commence until all information contained herein has been provided. Failure to provide the information required herein will be considered a delay to the project and be subject to liquidated damages.

(b)ITS Devices. Supply all information as indicated. If information is not readily available, it is the

Contractor’s responsibility to seek out and obtain the missing information, including performing all necessary coordination with the device(s) manufacturer(s), and performing coordination with the Representative. For fields not applicable to the project, clearly indicate within the matrix the particular cell is not applicable by filling

the field with the text “N/A.” Provide all latitude and longitude information with accuracy to the nearest 5 feet.

1.CCTV Cameras. Furnish the following information:

Location Information General Characteristics Communications Statewide Device ID Manufacturer PTZ Communication Type Type (permanent vs. portable) Model Camera Address District (Location) Serial Number/ Manufacturer ID PTZ Communications Protocol District (Owner) Power Type PTZ Connection Type Descriptive Location Encoder Manufacturer (where applicable) PTZ Connection Parameters (Serial Only) Roadway Roadway Direction Camera Firmware Mile Marker (where applicable) PTZ IP Address State Route Number PTZ IP Port Name Latitude Subnet Mask Longitude Gateway Exit Number (nearest) Multicast or Unicast County NTCIP Community String (if NTCIP) NTCIP Protocols Supported Username/ Password (where applicable) Video Format Video Transport

2.CMS. Furnish the following information:

Location Information General Characteristics Communications Statewide Device ID Manufacturer Communication Type Type (permanent vs. portable vs. semi-permanent) Model Communications Protocol (include version if applicable) Structure Type Serial Number/ Manufacturer ID Connection Type District (Location) Power Type Connection Parameters (Serial Only) District (Owner) Number of Display Lines Controller Address Descriptive Location Matrix Type (line or full) Controller Firmware Roadway Number of Pages Possible IP Address Roadway Direction Sign Height (by number of pixels) IP Port Name Mile Marker (where applicable) Sign Width (by number of pixels) Subnet Mask Next Downstream Exit Number For all available Fonts: • Font Dimensions • Font Height • Font Width • Font Character Spacing • Font Line Spacing Phone Number (if Dialup Communications) State Route Number NTCIP Protocols Supported Latitude NTCIP Community String (if NTCIP protocol) Longitude Gateway

Exit Number (nearest) County

3.HAR Transmitter. Furnish the following information:

Location Information General Characteristics Communications Statewide Device ID Manufacturer Communication Type Type (permanent vs. portable vs. semi-permanent) Model Communications Protocol (include version) District (Location) Serial Number/ Manufacturer ID Connection Type District (Owner) Power Type Connection Parameters (Serial Only) Descriptive Location Broadcast Radius Controller Address Roadway Vendor Control Software - Type and Version Controller Firmware Roadway Direction IP Address Mile Marker (where applicable) IP Port Name Exit Number (nearest) Subnet Mask County Gateway State Route Number NTCIP Protocols Supported Latitude NTCIP Community String (if NTCIP) Longitude Phone Number (if Dialup)

4.HAR Beacon. Furnish the following information:

Location Information General Characteristics Communications Statewide Device ID Manufacturer Communication Type Type (permanent vs. portable vs. semi-permanent) Model Communications Protocol (include version) District (Location) Serial Number/ Manufacturer ID Connection Type District (Owner) Power Type Connection Parameters (Serial Only) Descriptive Location Associated HAR Transmitter Statewide ID Controller Address Roadway Controller Firmware Roadway Direction IP Address Mile Marker (where applicable) IP Port Name Exit Number (nearest) Subnet Mask County Gateway State Route Number NTCIP Protocols Supported Latitude NTCIP Community String (if NTCIP) Longitude Phone Number (if Dialup) On Code (where applicable) Off Code (where applicable)

5.Vehicle Detectors. Furnish the following information for the respective detector types:

5.a Microwave/Radar Detectors, Inductive Loops, and Video Detection units.

Location Information General Characteristics Communications Statewide Device ID Detector Type Communication Type Type (permanent vs. portable vs. semi-permanent) Manufacturer Communications Protocol (include version) District (Location) Model Connection Type District (Owner) Serial Number/ Manufacturer ID Connection Parameters (Serial Only) Roadway Descriptive Location Power Type Controller Address Roadway Direction Vehicle Classification Capable and number of classification bins to be configured and value Controller Firmware Mile Marker (where applicable) Number of Zones/Lanes IP Address Exit Number (nearest) For each Zone/Lane: • Lane Number • Lane Type • Direction IP Port Name County Subnet Mask State Route Number Gateway Latitude NTCIP Protocols Supported Longitude NTCIP Community String (if NTCIP) Phone Number (if Dialup)

5.b RFID Tag Readers . Applicable only for IAG/Mark 4 manufactured RFID tag readers based upon the E-Z Pass electronic toll collection system.

Location Information General Characteristics Communications Statewide Device ID Detector Type Communication Type Type (permanent vs. portable vs. semi-permanent) Manufacturer Communications Protocol (include version) District (Location) Model Connection Type District (Owner) Serial Number/ Manufacturer ID Connection Parameters (Serial Only) Descriptive Location Power Type Controller Address Roadway Controller Firmware Roadway Direction IP Address Mile Marker (where applicable) IP Port Name Exit Number (nearest) Subnet Mask County Gateway State Route Number NTCIP Protocols Supported Latitude NTCIP Community String (where applicable) Longitude

5.c Bluetooth Readers.

Location Information General Characteristics Communications Statewide Device ID Detector Type Communication Type Type (permanent vs. portable vs. semi-permanent) Manufacturer Communications Protocol (include version) District (Location) Model Connection Type District (Owner) Serial Number/ Manufacturer ID Connection Parameters (Serial Only) Roadway Power Type Controller Address Descriptive Location Controller Firmware Roadway Direction IP Address Mile Marker (where applicable) IP Port Name Exit Number (nearest) Subnet Mask County Gateway State Route Number NTCIP Protocols Supported Latitude NTCIP Community String (where applicable) Longitude

6.NETWORK Switch. Furnish the following information:

Location Information General Characteristics Communications Statewide Device ID Manufacturer WAN Communication Type Type (permanent vs. portable vs. semi-permanent) Model LAN Communication Type Enclosure ID Serial Number/ Manufacturer ID MAC Address District (Location) Port Types Firmware Version District (Owner) Port Quantity Default Gateway Descriptive Location Power Type IP Address Roadway IP Port Names Roadway Direction Subnet Mask Mile Marker (where applicable) Gateway Next Downstream Exit Number Time Configuration State Route Number Discovery Protocol Latitude Logging Protocol Longitude Exit Number (nearest) County

(c)Testing. Section 1201.3(b) and as follows:
1.General. Conduct the System Tests in conjunction with District ITS staff, the Operations and

Performance Section , and the ATMS vendor. Coordinate with District ITS staff and the Operations and Performance Section to ensure the ITS device(s) installed within the project is(are) integrated into ATMS. Furnish all information prescribed herein in addition to all additional information required by the ATMS vendor to perform the integration. The System Test will be considered complete upon completion of the following:

2.System Test. Complete comprehensive test of the subsystem to demonstrate full functionality of

the ITS device(s) and subsystem, and compliance with the project specifications. Conduct the test using vendor-provided device control software or other equivalent software installed on a Commonwealth-provided computer or workstation in the TMC with access to the ATMS and the PennDOT WAN. Demonstrate full functionality of the subsystem including all components, such as the workstation and all communications to and from the field. The Contractor is responsible for demonstrating full compliance with project

documents, and full functionality of the ITS device and subsystem from the TMC to the field . Coordinate with District ITS staff and the Operations and Performance Section to demonstrate full ITS device control and functionality using the ATMS platform. The ATMS vendor is responsible for physical integration of the ITS device(s) into the ATMS. Ensure integration occurs within the project schedule and according to the project documents. Provide a minimum of 2 weeks advanced notice to District ITS staff and the Operations and Performance Section before integration of ITS device(s) or subsystem(s). Coordinate integration so as many devices as practical are integrated simultaneously.

1202.4MEASUREMENT AND PAYMENT —Incidental to the measurement and payment as specified in

Sections 1201.4, 1204.4, 1210.4, 1211.4, 1220.4, 1230.4, 1231.4, and 1240.4.

Get an email when 1202 changes

Pennsylvania revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Publication 408 Highway Construction Specifications, 2026 Edition. Pages 1360–0 of 1,522. View official source ↗

Ask about this section

Scoped to Pennsylvania Publication 408 — Specifications, Section 1202 — ATMS ITS DEVICE INTEGRATION. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.