SECTION 209 — STORM DRAIN INLET PROTECTION — STORM DRAIN INLET PROTECTION
209.01 Description.
This work includes providing temporary storm drain inlet protection facilities . Ensure that all erosion, sediment, and pollution prevention controls and devices are in place before the start of excavation when required by the SWPPP/SESC. Storm drain inlet protection facilities include the following types. SECTION 907 addresses dust control to reduce dust nuisance and hazards. Silt Fence Inlet Protection. This work includes placing a temporary filter fabric fence around inlet grates. Baled Straw Inlet Protection. This work includes placing baled straw around storm drain inlets. Sack Insert Inlet Protection and High Flow Sack Insert Inlet Protection. This work includes placing a reusable geotextile sack installed in drainage structures for the protection of wetlands and other resource areas and for the prevention of silt and sediment from the construction site from entering the storm water collection system.
209.02 Materials.
Silt Fence Inlet Protection. Provide a filter fabric material suitable for sediment control applications , selected from the Department’s Approved Materials List. Provide wooden posts that are oak, 2-in. × 2-in. in section and at least 4½ ft in length. Provide s upport netting that is heavy-duty plastic mesh. For prefabricated silt fence, 1-in. × 1-in. wooden posts are permitted. Baled Straw Inlet Protection. Ensure that baled straw and wooden stakes conform to Subsection 206.02.1. Sack Insert Inlet Protection. Provide Sack Insert Inlet Protection with a permeable geotextile that allows water to pass but prevents silt, sediment , and trash from passing. Provide s acks that are woven polypropylene geotextile and sewn by a double needle machine using high strength nylon. Sacks include overflow holes to make the silt sack effective even in the most extreme weather events. Ensure that that sacks meet the following stipulations: • Minimum puncture strength, ASTM D4533 of 130 lb • Minimum sieve size of No. 20 • Minimum flow rate, ASTM D4491 of 100 gal/min/sq ft
Part 200 — Earthwork and Erosion Control August 2025
SECTION 209 — STORM DRAIN INLET PROTECTION 200-69
209.03 Construction Methods.
Install the erosion and pollution controls before initiating any drainage, roadway, or bridge construction or for the disturbance of any soils. Silt Fence Inlet Protection.
Part 200 — Earthwork and Erosion Control August 2025
200-70 SECTION 209 — STORM DRAIN INLET PROTECTION discharges. Before this removal, remove all silt, mud, and debris entrapped by the baled straw and clean the area according to SECTION 212. Sack Insert Inlet Protection.
209.04 Method of Measurement.
Silt Fence/Baled Straw Inlet Protection. Silt Fence Inlet Protection and Baled Straw Inlet Protection will be measured by the linear feet of the protection installed. Sack Insert Inlet Protection. Sack Insert Inlet Protection will be measured by the number of inlets protected with sacks.
209.05 Basis of Payment.
The Department will pay for the completed and accepted quantities at the Contract unit prices as follows. Pay Item Pay Unit Silt Fence Inlet Protection LF Baled Straw Inlet Protection LF Sack Insert Inlet Protection EA
Part 200 — Earthwork and Erosion Control August 2025
SECTION 209 — STORM DRAIN INLET PROTECTION 200-71 Silt Fence Inlet Protection. The price constitutes full compensation for all labor, materials, and equipment, including excavation, stakes, support netting, filter fabric, backfill, the subsequent removal of the entire temporary facility, removal and disposal of entrapped material, and all incidentals required to finish the work, complete and accepted. Baled Straw Inlet Protection. The price constitutes full compensation for all labor, materials, and equipment, including excavation, straw bales, stakes, backfill, the subsequent removal of the entire temporary facility, removal and disposal of entrapped material, and all incidentals required to finish the work, complete and accepted. Sack Insert Inlet Protection and High Flow Sack Insert Inlet Protection. The price constitutes full compensation for all materials, including sacks, labor, equipment, and all incidentals required to finish the work, including final removal of the inlet protection device and removal and disposal of entrapped material, complete and accepted. Cleaning and Maintenance. The cleaning and maintenance of Silt Fence Inlet Protection, Baled Straw Inlet Protection, and Sack Insert Inlet Protection will be paid under SECTION 212. Payment will not be made for repairs and replacements necessary due to Contractor operations and damage or lack of proper maintenance.