SECTION 503 — REPAIRING DETERIORATED/DAMAGED JOINTS BETWEEN 1 INCH AND 8 INCHES WIDE IN FINISHED PORTLAND CEMENT CONCRETE PAVEMENT — REPAIRING DETERIORATED/DAMAGED JOINTS BETWEEN 1 INCH AND 8 INCHES WIDE IN FINISHED PORTLAND CEMENT CONCRETE PAVEMENT
503.01 Description.
This work includes performing all operations required for cleaning, saw cutting, concrete removal, rebuilding, and sealing joints in existing Portland cement concrete pavement that are between 1 in. and 8 in. wide at designated locations.
503.02 Materials.
503.03 Construction Methods.
Removal of Existing Concrete.
Part 500 — Concrete Pavements August 2025
SECTION 503 — REPAIRING DETERIORATED/DAMAGED JOINTS BETWEEN 1 INCH AND 8 INCHES WIDE IN FINISHED PORTLAND CEMENT CONCRETE PAVEMENT 500-5 is still a competent part of the concrete slab. If the load transfer device has failed as determined by the Engineer, remove and dispose of the device. Preparatory Work. Just before sealing, clean each joint or crack to the full depth of the concrete pavement to remove all foreign material. Ensure that the exposed concrete and reinforcing steel surface is free of rust, oil, solvent, grease, dirt, dust, bitumen, loose particles, and other foreign matter before the application of the epoxy bonding agent. Correct any disturbance of the gravel su bbase or any undermining of the existing concrete slab at no additional cost to the Department. Joint Filler Placement. Before placement of the fast -set repair mortar, install one 1 -in. or two ½ -in. thick lengths of a preformed asphalt joint filler in a straight line, perpendicular to the reinforcing steel for the full width of the existing concrete slab(s). Extend the preformed asphalt joint filler in a plumb vertical direction from the gravel subbase to the surface of the existing concrete slab. Application of the Epoxy Bonding Agent. For cracks greater than 1 in., apply an epoxy bonding agent to the prepared concrete surface to be repaired to a thickness of approximately 20 mils or according to the manufacturer’s recommendations. Do not coat the reinforcing steel with epoxy. Follow the manufacturer’s recommendations for curing the epoxy bonding agent before placing the concrete repair material. Do not place the repair material if the bonding agent has passed the manufacturer’s recommended contact time. If the time has been e xceeded, follow the manufacturer’s recommendations for re-application. Use an epoxy bonding agent with an extended contact time if required by the timing of concrete placement and/or weather conditions. Application of Fast Setting Mortar.
Part 500 — Concrete Pavements August 2025
500-6 SECTION 503 — REPAIRING DETERIORATED/DAMAGED JOINTS BETWEEN 1 INCH AND 8 INCHES WIDE IN FINISHED PORTLAND CEMENT CONCRETE PAVEMENT Sealing Joints. Upon placement and proper curing of the fast set concrete repair mortar, remove the top 1 in. of preformed asphalt joint filler and replace with a joint sealer. Clean and dry each joint before placing the sealing compound. Perform any required cleaning by blowing out all dirt, dust, or deleterious matter. Do not place the hot extruded joint sealing material unless approved by the Engineer. Remove all material and debris exiting from the joint from the pavement surface. Apply the joint seal by hot extrusion with a wand type instrument. Use a system that includes a flow control valve that fills all cracks to refusal. Fill all cracks to refusal to eliminate all voids or entrapped air. Ensure that the hot seal completely fills the joint so that, after cooling, the level of the sealer is flush with the pavement surface. Raise all depressions in the seal to the surface with additional hot seal. Seal the joints so that the final appearance presents a neat fine line. Do not overfill the joints and avoid spillage of the sealer. Remove and discard all excess or spilled sealer from the pavement. Do not seal joints if frost, snow, or ice is present. Store materials according to the manufacturer's recommendations.
503.04 Method of Measurement.
Repairing Deteriorated/Damaged Joints Between 1 Inch and 8 Inches Wide in Finished Portland Cement Concrete Pavement will be measured by the number of cubic feet of fast set concrete repair mortar placed in the repaired joints.
503.05 Basis of Payment.
The Department will pay for the completed and accepted quantities as follows. Pay Item Pay Unit Repairing Deteriorated/Damaged Joints 1 to 8 Wide in Finished PCC Pavement CF Payment at the Contract unit price is full compensation for all resources, labor, materials, equipment, and incidentals required to finish the work, complete and accepted.