B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Part 600 — Concrete

601Portland Cement Concrete

RI · 2022 (Aug 2025 compilation) Standard Specifications✓ Full text on BuildSpecBook pages 280–306 Save this section

Ask about Section 601

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

SECTION 601 — PORTLAND CEMENT CONCRETE 600-1

Part 600

CONCRETE SECTION 601 — PORTLAND CEMENT CONCRETE

601.01 Description.

This work consists of furnishing, placing, curing, and finishing Portland cement concrete for bridges, pavements, structures, and incidental construction. Concrete consist s of a homogeneous mixture of Portland cement, coarse aggregate, fine aggregate, air entrainment, water, chemical and mineral admixtures (when used), mixed in the required proportions. Proportion Portland cement concrete with the required cement content for each class and mix to the consistency specified. Use the classes of concrete required for the work. The Engineer will approve all concrete mixes. Various sizes of coarse aggregate for the classes of concrete may be combined during the batching operation in each fraction of aggregate size required to obtain the specified gradation. When testing aggregates to determine compliance with a specified gra dation, fractions will be tested separately and combined mathematically or combined mechanically in predetermined proportions and tested.

601.02 Materials.

Portland Cement. Provide Portland cement that conforms to SECTION M02 and is listed on the Department ’s Approved Materials List. For bridge projects, provide one brand of Portland cement and use for all visible portions of a structure; however, this is not required for interior deck slabs, beams, or corresponding elements that are semi-exposed. Provide suitable means for storing and protecting the cement against dampness. Supply all Portland cement from mill silos that have cement that has been tested. Provide a copy of a certified Mill Test Report to the Engineer for the cement being used. Deliveries may be directed to the site or through a regional distribution base. In addition, comply with the following:

a.Provide a manufacturer’s Mill Test Report, signed by the company representative having legal binding authority , with each shipment of cement . Copies of a standard form are available from the Department upon request.
b.Under all steps and conditions, make delivery in weatherproofed and sealed transporting equipment. Protect all cement from moisture and contaminants. Any cement that fails to meet any of these requirements will be rejected and removed from the work. Retest any

Part 600 — Concrete August 2025

600-2 SECTION 601 — PORTLAND CEMENT CONCRETE hydraulic cement stored for a period longer than 120 days according to AASHTO M85. An independent laboratory shall perform the retest at no cost to the Department , which must be approved by the Engineer before being used on the work. Chemical Admixtures. Use admixtures in Portland cement concrete that conform to SECTION M02. Perform all work according to the recommendations of the manufacturer. Do not use admixtures unless approved by the Engineer. Ensure that the physical and chemical properties of admixtures are uniform throughout their use in the work. If an admixture as furnished is not uniform in properties, discontinue its use. If more than one admixture type or brand is used, ensure that admixtures are compatible with one another so that the desirable effects of all admixtures used will be realized. When using a brand and type of admixture on the Department’s Approved Materials List, furnish a Certificate of Compliance from the manufacturer, certifying that the admixture furnished conforms to the chemical and physical requirements. The Engineer may take samples for testing at any time. Dispense chemical admixtures, including air -entraining admixtures, in liquid form. If more than one chemical admixture is used in the concrete mix, provide a separate dispensing measuring unit for each admixture. Ensure that dispensers for chemical admixtures have sufficient capacity to measure at one time the prescribed quantity required for each batch of concrete. Ensure that each dispenser includes a graduated measuring unit into which liquid admixtures are measured to within ±2 percent of the prescribed quantity (volume or weight, as applicable) for each batch of concrete. Locate and maintain dispensers so that the graduations can be accurately read from where proportioning operations are controlled to permit a visual check of batching accuracy before discharge. Mark each dispensing unit for the type and quantity of admixture. Equip e ach liquid admixture dispensing system with a sampling device consisting of a valve located in a safe and readily accessible position s o that a sample of the admixture may be withdrawn by the Engineer. For all types of admixtures, incorporate the water content as determined by the manufacturer’s recommendations when calculating the total amount free water of the concrete mix. Mineral Admixtures. Mineral admixtures such as fly ash, blast furnace slag, and silica fume may be permitted as a partial replacement of Portland cement in any concrete as approved by the Engineer. Ensure that m ineral admixtures conform to Subsection M02.06 and are listed on the Department ’s Approved Materials List. Provide suitable means for storing and protecting the mineral admixture s against moisture. Mineral admixtures that become partially hydrated or contain lumps will be rejected. Ensure that the handling and storage of all mineral admixtures conform to Subsection 601.02.1.

Part 600 — Concrete August 2025

SECTION 601 — PORTLAND CEMENT CONCRETE 600-3 Provide t he manufacturer’s Mill Certificate, signed by a company representative having legal binding authority, with each shipment of mineral admixtures. Retest any mineral admixture stored for a period longer than 120 days for compliance with the required specifications. An independent laboratory shall perform the retest at no additional cost to the Department, which must be approved by the Engineer before use on the work. Aggregates. Provide coarse and fine aggregates that conform to Subsections M01.05 and M02.02. Obtain aggregates from sources that have been previously tested by the Department. Results and information on the tests may be obtained from the Engineer upon request. If the Contractor proposes to obtain aggregates from sources that have not been tested by the Department, comply with the following: • Notify the Department three months in advance of use, including test results according to SECTIONS M01 and M02. An AASHTO accredited laboratory shall perform the test , which must be signed by a Rhode Island Registered Professional Engineer. • Submit the results of tests based on ASTM C295 , Petrographic Examination of Aggregates for Concrete for the proposed aggregates. An AASHTO accredited laboratory shall perform the tests, which must be signed by a Rhode Island Registered Professional Engineer. • Provide a sufficient quantity of aggregate samples to the Engineer for verification testing three months in advance of use. • Assume all costs for sampling and testing, except for the cost of verification testing, which will be borne by the Department. Test all proposed aggregates and produce concrete that has freeze-thaw durability of 80 percent as determined by the relative dynamic modulus (ASTM C215, Transverse Method) at 300 cycles as tested according to ASTM C666 - Procedure A, as modified by the Department. Copies of the modifications may be obtained from the Engineer upon request. Handle and transport aggregates from stockpiles or other sources to the batching plant to ensure a uniform grading of the material. Ensure that t he batch plant site, layout, equipment , and provisions for transporting material provides a continuous supply of material to the work. Buildup stockpiles in layers of not more than 3 ft in thickness. Ensure that each layer is in place before beginning the next. Do not allow any layer to cone down over the next lower layer. Provide safe and suitable facilities for obtaining and storing samples of aggregates. Ensure that the facilities provide safe access to the samples. Do not stockpile aggregates together from different sources and of different gradings. Do not use aggregates that have become segregated, mixed with foreign materials, or contaminated by aggregates of different gradings. Stockpile or bin for draining all aggregates produced or handled by hydraulic methods at least 12 hours before being batched. Rail shipments requiring more than 12 hours will be accepted as adequate binning only if the car bodies permit free drainage. If the

Part 600 — Concrete August 2025

600-4 SECTION 601 — PORTLAND CEMENT CONCRETE aggregates contain a high or nonuniform moisture content, the Engineer may require storage or stockpile periods in excess of 12 hours. Water. Ensure that water used in mixing and curing concrete conforms to Subsection M02.07.

601.03 Construction Methods.

Proportioning.

a.General. Ensure that all concrete used on State of Rhode Island projects is air entrained. Adhere to the classes and proportions of materials per cubic yard of concrete in the following Table. Classes and Proportions of Concrete Materials Class1,5,9 B A XX HP MC2 Z X Minimum Cementitious Content3, lb/cu yd 400 400 500 500 500 500 50011 Maximum Cementitious Content6, lb/cu yd 700 700 700 7006 600 700 700 Maximum w/cm 0.55 0.45 0.42 0.40 0.40 0.42 0.40 Acceptance Criteria Consistency Range4, AASHTO T119 Slump, in. 2 - 4 2 - 4 2 - 4 2 - 4 2 - 4 < 1 2 - 4 AASHTO T23 Minimum, Compressive Strength, psi 28 days 3000 3000 4000 5000 3500 5000 5000 56 days ― ― ― ― 5000 ― -- Air Content Range, AASHTO T152, % 5 - 9 5 - 9 5 - 9 5 - 9 5 - 9 ― 5 - 9 Concrete Prequalification Criteria7 Surface Resistivity, (4 in. × 8 in. cylinder) AASHTO T358, k-cm (minimum) 28-day standard cure ― ― ― 15 15 ― -- 56-day standard cure ― ― ― 21 21 ― -- Maximum 28-day drying shrinkage,8, AASHTO T160, % ― ― ― -0.04 -0.04 ― -- Aggregate Prequalification Criteria9 Maximum 14-day expansion ASTM C1567, % ― 0.1 0.1 0.1 0.1 0.1 0.1 Footnotes:
1.A single concrete mixture may be used for multiple classifications if performance and prequalification criteria are satisfied.
2.Class MC concrete may have a total supplementary cementitious content of 75 percent by weight of total cementitious material when using either ground -granulated, blast-furnace slag meeting the requirements of AASHTO M 302, or combinations of slag and other supplementary cementitious materials. Maximum cement replacement by fly ash or other mineral admixture meeting requirements of AASHTO M 295 is 30 percent by weight. Maximum cement replacement by silica fume meeting the requirements of AASHTO M 307 is 7 percent by weight.
3.Portland cement and all other mineral admixtures.

Part 600 — Concrete August 2025

SECTION 601 — PORTLAND CEMENT CONCRETE 600-5

4.Slump range measured at the point of discharge. Do not exceed a s lump of 4 in. for surfaces sloped greater than 4 percent. I f additional workability is desired , the Engineer may allow an increase of the maximum specified slump to 6 in. if an AASHTO M 194 Type A - Water Reducing Admixture is used, or an increase of up to 9 in. if an AASHTO M 194 Type F or G - High Range Water Reducing admixture is used.
5.AASHTO M 194 Type F or G - High Range Water Reducing Admixture is required when concrete will be placed by pumping equipment.
6.The maximum cementitious content for Class HP may be exceeded for the fabrication of precast/prestressed concrete structures as approved by the Engineer.
7.Concrete prequalification testing will not be required for the following concrete items ― Flared Ends, Highway Bounds, Fence Post Footings, Guardrail Anchorage, Unreinforced Footings, Paved Waterways, Thrust Blocks, Precast Elements for Collars, Catch Basins, Manholes, Drop Inlets, Sumps, Electrical Handholes, Curbing, Pipe, Headwalls, End-walls, High Capacity Inlets, and Temporary Traffic Barriers.
8.Drying shrinkage prequalification is not required for precast/prestressed structures.
9.Aggregate prequalification is required for all concrete classifications.
10.Self-Consolidating Concrete (SCC) may be used for all classes of concrete except for Classes B and
Z.Ensure that SCC meets all mix performance requirements listed in the Table for the respective concrete class. Test SCC for slump flow according to ASTM C1611; ensure that the visual stability index (VSI) is 0 in. or 1 in.
11.Class X is used only for precast drainage structures.
b.Design and Approval of Concrete Mixtures. Design the concrete mixtures for each class of concrete specified. Proportion t he concrete mix components using the absolute volumes method according to the requirements for each class as specified herein and methods in the American Concrete Institute’s Manual of Concrete Practice, latest edition; Standard 211.1, “Recommended Practice for Selecting Proportions for Normal, Heavyweight, and Mass Concrete ”; and Standard 301, “Specifications for Structural Concrete in Buildings – Section 4.2.3.” ● Step 1. Laboratory Testing. At least 60 days before production, submit in writing the concrete mix design on Department forms and trial batch reports supported by laboratory test data from an AASHTO accredited laboratory to the Engineer for review. Provide the following information in the trial batch test reports: ○ Contractor/testing laboratory name ○ The coarse and fine aggregate gradations and sources ○ The fine aggregate fineness modulus (FM) ○ Any other pertinent information ( e.g., aggregate specific gravities, unit weights, absorptions, any other material properties) ○ Date of mixing ○ Mixing equipment and procedures used

Part 600 — Concrete August 2025

600-6 SECTION 601 — PORTLAND CEMENT CONCRETE ○ The size of batch in cubic yards ○ Weight/volume, type, source/manufacturer of all ingredients used in the mix ○ Slump/spread ○ Air content of the mix ○ Concrete temperature ○ Unit weight of fresh concrete ○ Curing method, age at time of testing, and compressive strength of concrete Note: Ensure that a ll testing conform s to the applicable AASHTO and/or ASTM requirements listed in these Specifications. For o riginal copies of concrete mix designs and trial batch reports submitted for approval to the Department, provide an original Rhode Island Professional Engineer’s stamp and signature. ● Step 2. Trial Runs . Once the concrete mix design has been reviewed and no exception taken by the Engineer, conduct trial runs before production using the mix design’s component materials and proportions, including the amount of admixtures that will be necessary to meet the specifications and produce concrete of the required plasticity, workability, air content, compressive strength, flexural strength, or any other specified concrete property. Conduct the trial runs by employing the concrete batch plant, mixer , and handling equipment propose d to use in production. Calibrate a ll equipment employed in the batching, mixing, transporting, and testing , and meet the requirements listed herein before initiating the trial runs. Pursue the goal of producing concrete using the maximum amount of water and air content specified in the submitted mix design during the trial runs. Notify the Engineer at least 48 hours in advance of performing the trial runs so that the test procedures can be witnessed. Once the concrete temperature, slump, and air content are tested and compliance with the Specifications has been established , the Engineer will fabricate compressive strength specimens to be tested by the Engineer. When all specified concrete parameters have been met, the Engineer will accept the proposed mix design for production. The accepted mix design proportions will govern during the progress of the work. Do not make any changes in the sources or proportions of the materials, including aggregate size, without written approval of the Engineer. Do not use n ew materials until the Engineer approves a revised mix design and new proportions based on a trial batch and laboratory tests and a minimum 3 cu yd batch plant trial run. Trial batch laboratory testing shall be conducted by an AASHTO accredited laboratory at no additional cost to the Department. The testing requirements are:

Part 600 — Concrete August 2025

SECTION 601 — PORTLAND CEMENT CONCRETE 600-7 ○ No testing is required for changes in admixture dose provided that the proposed dose does not exceed the manufacturer’s recommendations. ○ Slump, air content, concrete temperature , and unit weight are required for all modifications. ○ 28-day (56-day for Class MC ) compressive strength is required for all modifications. ○ AASHTO T358 and AASHTO T160 testing is required for any change to cementitious material source, cementitious material proportion, or water quantity for concrete Classes HP and MC. ○ ASTM C 1567 is required for all concrete classes for the following changes: + aggregate source + aggregate size + single aggregate proportions greater than 300 lb/cu yd + cementitious material source + cementitious material proportions + water content ● Heat development, as determined by Adiabatic Temperature Rise or calorimetry, is required for any change in cementitious material content or source for Class MC concrete.

c.Concrete Prequalification Requirements . Proportion all concrete mixtures to meet the minimum prequalification requirements in the Table in Para. a . The Concrete Producer shall conduct all prequalification trial batches and prequalification testing using the materials in the submitted mix design. Trial batch and prequalification testing shall be performed by an AASHTO accredited laboratory. The Concrete Producer shall submit complete mixture proportions and prequalification test results of all plastic an d hardened concrete properties in Para. b and the Table in Para. a to the Engineer for review. The Engineer reserves the right to perform testing for any of the specified prequalification properties. ● Ensure that concrete mixtures have an AASHTO T358 surface resistivity greater than or equal to the value in the Table in Para. a for the class of concrete. Report a minimum of two 4 in. × 8 in. cylinder specimens for the AASHTO T358 testing. ● Ensure that c oncrete mixtures have a 28 -day drying shrinkage value less than the value in the Table in Para. a for the class of concrete. Determine drying according to the procedure in AASHTO T160 with the following clarifications: Specimens are 3 in. × 3 in. × 11.25 in. prisms. Moist cure all specimens in a saturated lime water bath for seven days before exposure to the drying environment. The specimen length is taken upon demolding after the curing period and weekly for 28 days while placed in the drying environment. Calculate t he shrinkage value after 28 days of drying as the percent change in length from the time the specimen is removed from curing.

Part 600 — Concrete August 2025

600-8 SECTION 601 — PORTLAND CEMENT CONCRETE ● Ensure that all combinations of aggregate and cementitious materials used in concrete mixes are innocuous to alkali -aggregate reactivity as demonstrated by a mean expansion not greater than or equal to 0.10 percent after 14 days of soaking using the ASTM C 1567 test method. Ensure that this requirement is satisfied for an aggregate if the mean expansion in an AASHTO T303 test after 14 days of soaking is less than or equal to 0.10 percent. Test coarse and fine aggregates separately. A series of tests with the reactive aggregate and different cement replacement levels may be required to determine the minimum cement replacement level necessary to mitigate expansion for a given combination of materials. Do not d etermine the minimum replacement level by interpolation between tested levels. Batching Plants and Equipment.

a.General. Ensure that batching plants meet AASHTO M 157 and are certified by the National Ready Mix Concrete Association (NRMCA). Weigh cement independently on a separate scale. Ensure that the weighing hopper is properly sealed and vented.
b.Cement Silos. Provide separate silos or holding bins for each cement type and mineral admixture. Ensure that the bins protect the cement and mineral admixture from rain and moisture. On a weekly basis, m aintain a log documenting deliveries, which will include the brand, supply, location, type, quantity, and date to document the cement on hand. Ensure that all received cement conform s to the specified quality requirements. Ensure that the log also contains data on the quantitative distribution of all cement used on both private and State projects. Submit copies of the log to the Engineer upon request, attested to by the Contractor or its representative.
c.Scales. Calibrate all plant scales and water meters, including truck scales, involved in the plant operation using a registered scale company as follows: ● Annually before use in State work ● At intervals of not more than 180 calendar days ● At any time ordered by the Engineer Note: Every 180 days, the plant owner shall submit to the Engineer a certificate from the registered scale company making the checks attesting to the accuracy of all plant scales. The certificate shall be signed by the technician or a responsible representative of the scale company making the check.
d.Automation and Recordation. Ensure that plants producing Portland cement concrete for the Department conform to the following plant equipment requirements: ● Automatic Proportioning. Produce Portland cement concrete in batch type mixing plants equipped with approved automatic proportioning devices. Ensure that the devices include equipment for accurately proportioning batches of the various components of the mixture by weight or volume in the proper sequence. Proportion

Part 600 — Concrete August 2025

SECTION 601 — PORTLAND CEMENT CONCRETE 600-9 cement and aggregates by weight. Proportion water and admixtures by weight or volume. Adjust the batch weights as needed when aggregate moistures change to account for the actual moisture content of the aggregates at time of use. Equip plants automatically to control the batching sequence and timing of operations. Provide an auxiliary interlock cutoff circuit to interrupt and stop the automatic cycling of the batching operations when an error in weighing occurs, when an aggregate bin becomes empty, or when there is a malfunction of any portion of the control system. ● Recording Equipment . Equip t he plant with a recording device that automatically records the required data for delivery tickets and reproduces the reading of the scale being recorded within ±0.1 percent of scale capacity: Provide ticket information electronically in accordance with SECTION 941. The Engineer may also request sufficient printed copies of delivery tickets to provide a copy for the plant inspector and a copy for the Construction Manager for the permanent Project record. ● Equipment Failure. If at any time the recording devices become inoperative, the plant may be allowed to batch materials for a period of not more than one work day from the time of breakdown, if approved by the Engineer. Written permission of the Engineer will be required for periods of operations without automatic proportioning facilities longer than one work day. As a condition for continued use with inoperative recording devices, manually record all required information on all delivery tickets. ● Batching Controls. Ensure that batching controls are electrically interlocked with the scales to prevent cycling or recycling of batching until scales tare zero. Ensure that the batching controls meet the following tolerances with respect to the various components weighed in each batch: ○ Coarse Aggregate: ±2.0 percent of required weight of the total coarse aggregate being weighed ○ Fine Aggregate: ±2.0 percent of required weight of the total fine aggre gate being weighed ○ Portland Cement: ±1.0 percent of required weight of cement being weighed ○ Mineral admixtures: ±1.0 percent of required weight of mineral admixtures being weighed ○ Water: ±1.0 percent of required weight or volume of water being weighed ○ Admixtures: ±3.0 percent of required weight or volume of each admixture being used Ensure that the total weight of the batch does not vary more than ±1.0 percent from the theoretical design weight.

Part 600 — Concrete August 2025

600-10 SECTION 601 — PORTLAND CEMENT CONCRETE Concrete Mixing, Delivery, and Discharge. Concrete may be mixed at the site of construction, at a central point, or in transit mixers, all according to the Specifications.

a.Equipment — Mixers and Agitators . Provide mixers and agitators that meet the requirements of AASHTO M 157 . When the concrete is truck -mixed, ensure that the volume of concrete mixed per batch does not exceed the mixer ’s nominal capacity as shown on the manufacturer’s standard rating plate on the mixer. An exception is that an overload of up to 10 percent above the mixer’s nominal capacity may be permitted, if the concrete test data for strength, segregation, and uniform consistency are satisfactory and if no spillage of concrete occurs. Equip truck mixers and agitators so that the number of revolutions of the drum, blades, or paddles may be readily verified. Ensure that t ruck mixers can measure the amount of water added during retempering such as a water meter or other method.
b.Mixing and Delivery. Mix and deliver ready-mixed concrete according to AASHTO M 157. Ensure that ready -mix concrete delivery trucks are National Ready Mixed Concrete Association (NRMCA) (nrmca.org) certified via a non-expired certificate affixed to the truck in a location readily visible to the inspector (see Section 5 of NRMCA Plant Inspe ctor’s Guide).
c.Discharge. ● Time and Rate. Ensure that the elapsed time from when water is added to the mix until concrete is discharged into the forms at the site of work does not exceed 90 minutes when hauled in truck -mixers or truck agitators or 30 minutes when concrete is hauled by non-agitating equipment. Waste any concrete that is not discharged into its final place within 90 minutes (30 minutes when using non-agitating equipment) after batching. Approved set -control admixtures may be used to extend the maximum time of discharge for ready -mixed concrete delivered in truck mixers to 120 minutes , if the Contractor submits trial mix data subject to the following conditions: ○ The concrete mixture proportions and prequalification test results have been approved according to Subsection 601.03.1(b). ○ Set-control admixture usage is according to the admixture manufacturer ’s instructions and guidelines. ○ Trial batches of the concrete mixture without the admixture (control) and additional batches covering the anticipated range of admixture doses are conducted. Ensure that trial batch volume is a minimum of 3 cu yd and that trial batches are conducted at the maximum water content for the approved mixture. ○ For the control batch, only sample after initial mixing.

Part 600 — Concrete August 2025

SECTION 601 — PORTLAND CEMENT CONCRETE 600-11 ○ For batches containing the set -control admixture, sample after initial mixing and after 30, 60, 90, and 120 minutes. Keep t he truck mixer in motion between sampling intervals. ○ Include for each trial batch data for plastic properties (slump, air content, unit weight, and temperature) after initial mixing and after 30, 60, 90, and 120 minutes of slow mixing. Report the number of drum rotations at each sampling interval. ○ If plastic properties are outside of the specification limits at any time interval, retesting after high speed mixing for up to five minutes will be allowed. ○ Provide data for each trial batch that includes seven-day and 28-day (56 days for Class MC concrete) compressive strength results sampled after initial batching for the control and after initial batching and 120 minutes of slow mixing for batches containing the set-control admixture. ○ Ensure that trial batch test results that indicate the concrete properties of mixtures containing the set -control admixture meet specification requirements after 120 minutes of slow mixing. ● Retempering. Retempering is defined as adjusting concrete properties by the addition of water or chemical admixtures after initial batching. Retempering concrete by adding water or other means may be permitted only 1) after concrete arrival and initial testing on the jobsite, 2) when delivered in truck mixers, and 3) if permitted by the Engineer. When authorized, additional water or chemical admixtures may be added to the batch materials with additional mixing to i ncrease slump or air entrainment to meet the specified requirements, if: ○ The maximum water-cementitious materials ratio is not exceeded. ○ The admixture doses do not exceed the manufacturer’s recommendations. ○ All retempering and retesting operations are completed at least 30 minutes before the maximum allowable discharge time limit. Add all admixtures at the plant. The Engineer may approve the addition of withheld mixing water at the jobsite with a metered pressurized wand. Do not add admixture during retempering that is not present in the approved mixture. Before allowing retempering with water -reducing admixtures on the Project, conduct trial batches to simulate the impact of delayed additions as follows: ○ Both the control and retempered batch contains the same plant-added admixture dose. ○ The retempered batch has the second dose of admixture added at least 30 minutes before the maximum discharge time. ○ The combination of plant added admixture dose and retempered admixture dose does not exceed the maximum manufacturer’s recommended dose.

Part 600 — Concrete August 2025

600-12 SECTION 601 — PORTLAND CEMENT CONCRETE ○ Plastic properties are sampled initially at the time of retempering and maximum discharge time. ○ Specimens for strength and time of set for both the control and retempered mixture are sampled at the maximum allowed discharge time. No trial batches are required for retempering with air entrainment admixtures. If additional water will be incorporated into the concrete, revolve the drum not less than 30 revolutions at the mixing speed immediately after retempering the concrete and before discharge is commenced. If additional admixtures are incorporated into the concrete, revolve the drum between 30 to 60 revolutions at the mixing speed immediately after retempering the concrete and before discharge is commenced. Do not use concrete that is not within the specified slump or air content limits at the time of placement. Retemper the concrete at the site as permitted by the Engineer. Retempering with admixtures will be permitted only with the approval of the Engineer or when specifically provided for in the Contract. Limitations for Mixing and Placement. Do not mix, place , or finish concrete when the natural light is insufficient, unless an adequate artificial lighting system is operational. During and immediately after placement, protect the concrete from the adverse effects of rain. When there is a probability of air temperature 40°F or less at the time of placement, or when there is a local forecast indicating that the temperature will be below 40 °F during the five-day (cast in place masonry) or 14 -day (bridge deck) curing period , cold weather concreting, as defined in Subsection 601.03.5 , will apply. At least 24 hours before placement, submit a request for approval by the Engineer to use a cold weather concreting and curing plan detailing the methods and equipment to ensure that the concrete temperature does not fall below 50°F during the curing period after placement, which is considered the protection period. Ensure that concrete mixing operations conform to Subsection 601.03.5. Cold Weather Concrete.

a.Plant Procedures. When concreting is authorized during cold weather, the aggregates and/or water may be heated by either steam or dry heat before being placed in the mixer. Ensure that t he apparatus heat s the mass uniformly and is arranged to preclude the possible occurrence of overheated areas that might damage the materials. Ensure that the temperature of the mixed concrete is not less than 50°F and not more than 90°F at the time of placement in the forms. Do not use frozen aggregates in the concrete. Stockpiled aggregates may be heated by the use of dry heat or steam. Do not heat aggregates directly by gas or oil flame or on sheet metal over fire.

Part 600 — Concrete August 2025

SECTION 601 — PORTLAND CEMENT CONCRETE 600-13 When aggregates are heated in bins, steam-coil, water-coil heating, or other methods that will not be detrimental to the aggregates may be used. Do not use live steam on or through binned aggregates without the approval of the Engineer.

b.Concrete Placement Procedures . Do not place concrete on frozen subgrade. Install sufficient heating devices under an enclosure or covering that are capable of maintaining at all times and under all weather conditions during the protection period a uniform concrete temperature of not less than 50 °F. From days 8 to 14 of the concrete bridge deck curing period , maintain a minimum concrete temperature of not less than 40 °F. Arrange h eating devices to prevent overheating any forms or concrete. Before any concrete is placed, ensure that the enclosure and heating apparatus are as nearly complete as the placement of concrete will permit. Ensure that the minimum temperature is continuously maintained around deposited concrete for the curing period of five days (cast in place masonry) or 14 days (bridge deck) or 56 days (Class MC concrete) immediately after concrete has been pl aced and then reduced gradually so that the concrete will not be subjected to a sudden change in temperature. The heating period may be reduced when the concrete units will not be subjected to any appreciable bending stress from dead or live load until after seasonal conditions have permitted normal curing. A steam heating system may be used to supply heat during the protection period to ensure a minimum temperature of 40°F before concrete placement. Heat for protection may be supplied by any method that will maintain the required concrete temperature of not less than 50°F. When methods other than live steam are used, make provisions in the enclosure being heated to maintain a humid condition of sufficient vapor (maintain humidity of 100 percent) content to prevent evaporation of the moisture in the concrete. Provide adequate fire protection when heating is in progress and provide watchmen or other attendants to keep heating units in continuous operation. Do not use open fires. Maintain a daily permanent record of the concrete surface temperatures throughout the curing period with the use of a 24 -hour, continuous temperature recording device. The Engineer will retain these records. During freezing weather, seal all keyways, anchor bolt holes , or other depressions in exposed horizontal concrete surfaces against the admission of water. Repair damage to the concrete from freezing water in the depressions if practical, or replace the concrete as directed by the Engineer. Hot Weather Concrete. Hot weather is defined in The American Concrete Institute , Standard 305. During concreting operations in hot weather, take appropriate measures to reduce the hazards of an increased rate of cement hydration, flash set, loss of water due to evaporation, high concrete ingredient temperatures, and the increased difficulty of concrete placing and finishing. Comply with t he following requirements during concrete placement operations in hot weather:
a.Concrete Temperature . Ensure that t he temperature of the concrete at the point of discharge does not exceed 90°F.

Part 600 — Concrete August 2025

600-14 SECTION 601 — PORTLAND CEMENT CONCRETE

b.Cooling Materials. The Contractor may reduce the temperature of the concrete by cooling one or more of several ingredients. Use chipped or crushed ice in the mix as a portion of the mixing water on a pound for pound basis, provided that the measurement is determined at the time of placement in the mix. If used, melt all ice before the batch is discharged from the mixing unit.
c.Concrete Plac ement. Immediately before the concrete is placed, cool the forms and reinforcement steel by spraying with water. Do not allow any standing water in the concrete forms from the spraying procedures. Ensure that sufficient skilled staff and adequate equipment are available to place the concrete without delays.
d.Finishing. To prevent thermal and shrinkage cracking resulting from moisture loss, use effective means to supply moisture. Ensure that finishing operations follow as closely as practical behind the placing operation so that curing may begin as soon as possible. Curing.
a.Curing. Ensure that the temperature on the surface of the hardened concrete does not fall below 50°F at any time during the first five days of curing. Initiate c uring operations on all exposed surfaces immediately after the placing and finishing operations have been completed. Select a method of curing that does not damage the concrete surface before final set occurs and continue its use throughout the work, unless the Engineer determines that the curing plan results in unsatisfactory concrete curing. Any changes in the method of curing must be authorized in writing. When curing requires the use of water, ensure that the curing has priority for all water supply or suppliers. Failure to provide sufficient cover material or lack of water to adequately protect both curing and other requirements will result in immediate suspension of concreting operations. Do not allow the concrete to remain exposed for more than ½ hour between stages of curing and during the curing period.
b.Water Method. Ensure that the concrete remains continuously wet by the application of water for a minimum period of seven days after the concrete has been placed. A curing medium meeting the requirements of Subsection M02.04 may be used to retain the moisture during the curing period. When a curing medium will be used to retain the moisture, ensure that the entire surface of the concrete remains damp by applying water with a nozzle so that the flow is atomized in the form of a mist rather than a spray until the surface of the concrete is covered with the curing medium. Do not apply t he moisture from the nozzle under pressure directly upon the concrete and do not allow moisture to accumulate on the concrete in a quantity sufficient to cause a flow or wash the surface.
c.Curing Compound Method . Use a c uring compound that complies with Subsection M02.04. For concrete that is treated with any additional coatings or overlays, do not cure as provided in this Section.

Part 600 — Concrete August 2025

SECTION 601 — PORTLAND CEMENT CONCRETE 600-15 Spray the s urfaces of the concrete that are exposed to the air uniformly with a curing compound. Apply the curing compound according to the manufacturer’s recommendation. Evaluate runs, sags, thin areas, skips, or holidays in the applied curing as evidence that the application is not satisfactory. If a clear color curing compound is used, add a fugitive dye to the curing compound to ensure complete coverage. Apply t he curing compound to the concrete following the surface finishing operation immediately before the moisture sheen disappears from the surface, but before any drying, shrinkage, or craze cracks begin to appear. If any drying or cracking of the surface is evident, immediately apply water with an atomizing nozzle as specified above for the Water Method, and continue until application of the compound is started or resumed. However, do not apply the compound over any resulting freestanding waters. If the film of compound is damaged from any cause before the expiration of seven days after the concrete is placed for structures and 72 hours for pavement, repair the damaged portion immediately with additional compound. Do not dilute or alter the curing compound after manufacture. When the curing compound is shipped in tanks or tank trucks, provide a shipping invoice with each load. Ensure that the invoice contains the same information as that required for container labels. Curing compounds may be sampled by the Engineer at the source of supply , at the job site, or at both locations. Use the curing compound within 120 days of its manufacture. All tests will be conducted by the Engineer according to the latest test methods of the American Society for Testing Materials.

d.Waterproof Membrane Method . Spray the exposed finished surfaces of concrete with water, using a nozzle that atomizes the flow so that a mist and not a spray is formed, until the concrete has set, after which place the curing membrane. Ensure that t he curing membrane remains in place for a period of not less than 72 hours. Use sheeting material for curing concrete that conforms to Subsection M02.04.2. Use sheeting material that has been fabricated into sheets of a width to provide a cover for the entire concrete surface. Securely cement together all joints in the sheets to provide a waterproof joint. Ensure that the joint seams have a minimum lap of 6 in. Securely weigh down the sheets by means satisfactory to the Engineer. Do not use rocks, sand, or loose debris as ballast. Should any portion of the sheets be broken or damaged before the expiration of 72 hours after being placed, repair the broken or damaged portions with new sheets properly secured into place.

Part 600 — Concrete August 2025

600-16 SECTION 601 — PORTLAND CEMENT CONCRETE Do not use s ections of membrane that have lost their waterproof qualities or have been damaged that renders them unfit for curing the concrete.

e.Forms-In-Place Method. Formed surfaces of concrete may be cured by retaining the forms in place. Ensure that t he forms remain in place for a minimum period of seven continuous days after the concrete has been placed, except that, for members over 20 in. in least dimension , ensure that the forms remain in place for a minimum period of five continuous days. Remove the forms no later than three weeks after the concrete has been placed. Ensure that all joints in the forms and the joints between the end of forms and concrete remain moisture tight during the curing period. Reseal any cracks in the forms and cracks between the forms and the concrete by methods approved by the Engineer. Quality Assurance (QA).
a.Concrete Manufacturing Plant Quality Control (QC). ● General. The Concrete Producer shall establish, implement , and maintain a QC program to control all equipment, materials , and processes during concrete production. The Concrete Producer ’s QC program shall include sampling, testing, inspection, monitoring, documentation , and corrective action procedures during the handling, blending, and mixing operations. Develop a written Quality Control Plan (QCP) that details the Concrete Producer ’s QC program. Do not produce c oncrete without an approved QCP and a QC technician present at the plant for production. QC is not required for optionally tested items in the latest edition of the RIDOT Master Schedule of Testing. Failure to comply with the provisions of this Subsection will result in the rejection of the concrete produced until the Concrete Producer ’s operations comply. ● Personnel. At a minimum, the QC staff shall include the following personnel: ○ QCP Administrator. The Concrete Producer shall employ a QCP Administrator with five years minimum of Materials QC experience and meeting one or more of the following criteria: + Professional Engineer licensed in the State of Rhode Island + Certification by the National Institute for Certification of Engineering Technologies (NICET) at Level III or above for concrete + Certification by the North -East Transportation Training and Certification Program (NETTCP) as a QA Technologist ○ For p restress concrete facilities , employ a QCP Administrator with five years minimum of prestress concrete production QC experience and meeting one or more of the following criteria: + Precast/Prestress Concrete Institute (PCI) Level III Certification for prestressed concrete production (PCI Level II for non-prestressed precast)

Part 600 — Concrete August 2025

SECTION 601 — PORTLAND CEMENT CONCRETE 600-17 + Certification by the National Institute for Certification of Engineering Technologies (NICET) at Level III or above for concrete + Certification by the North -East Transportation Training and Certification Program (NETTCP) as a QA Technologist ○ The QCP Administrator shall have the authority to direct all actions necessary for the successful implementation of the QCP, including administering, implementing, monitoring, and adjusting processes as necessary to ensure compliance with the Contract Documents. ○ QC Technicians. The Concrete Producer shall employ QC Technician(s) who test concrete specimens and concrete materials. QC Technicians shall possess a current certification as American Concrete Institute (ACI) Concrete Laboratory Testing Technician Level I or NETTCP Concrete Technician. + For precast/prestressed concrete facilities, employ additional QC technician(s) who sample and test concrete at the point of placement. QC technicians shall possess a current certification as ACI Concrete Field Testing Technician Grade I or NETTCP Concrete Technician. + QC technicians shall report directly to the QCP Administrator and shall be responsible for performing required QC activities and preparation of associated QC documentation. ● QC Testing Facilities and Equipment . The Concrete Producer shall maintain a separate QC laboratory and associated sampling, testing, and measuring equipment necessary to perform the required QC activities. Provide s ampling, testing , and measuring devices according to specified standards and properly calibrated and verified. The Concrete Producer shall maintain records of the calibration and maintenance of all sampling, testing, and measuring equipment. Use back-up equipment if a device is found to be defective. Ensure that d efective equipment is clearly tagged and/or removed from the site until repaired and the calibration is verified. If non -standard or alternative sampling methods, testing procedures, or equipment are proposed to be used, detail these in the QCP and approved by the Engineer before use. ● QC Activities . Implement QC activities for monitoring, inspection, sampling , and testing, which will cover all aspects that affect the quality of the concrete, including: ○ Component materials: + Fine and coarse aggregates + Portland cement + Mineral and chemical admixtures + Water ○ Production and delivery equipment ○ Mixing and transportation ○ Formwork (precast/prestress plants only) ○ Prestressing steel, reinforcement, inserts (precast/prestress plants only)

Part 600 — Concrete August 2025

600-18 SECTION 601 — PORTLAND CEMENT CONCRETE ○ Tensioning prestressing steel (precast/prestress plants only) ○ Plastic and hardened concrete properties (precast/prestress plants only) ○ Placement and consolidation (precast/prestress plants only) ○ Finishing and curing (precast/prestress plants only) ○ Finished product (precast/prestress plants only) The two following Tables provide the minimum QC activities and frequencies. Minimum Production Equipment QC Requirements Equipment Control Requirement Minimum Frequency

1.Plant Central Mixer Blades Visual Inspection Annually
2.Plant Scales and Meters Calibrate Every 180 days
3.Batch Plant and Mixer Trucks NRMCA Certification Annually
4.Truck Water Meters Calibrate Annually
5.Tensioning Gauges Calibrate Precast/Prestressed Concrete — Every 180 days
6.Hydraulic Jacks Calibrate Precast/Prestressed Concrete — Every 180 days Minimum Materials QC Requirements Item Control Requirement Minimum Frequency
1.Fine and Coarse Aggregates Gradation Moisture Content Visual Inspection of stockpiles and bins for segregation and contamination Ready Mix Concrete – Daily/before start of production and randomly every 160 cu yd of concrete. Precast/Prestressed Concrete – Daily/before start of production and randomly every 50 cu yd of concrete.
2.Portland Cement Mill Text Report – Verify conformance to specifications Each delivery
3.Mineral Admixtures Certificate of Compliance – Verify conformance to specifications Each delivery
4.Chemical Admixtures Certificate of Compliance – Verify conformance to specifications Each delivery
5.Concrete Batching Verify Mix Proportions and Batch Weights Computer maximum allowable retempering water and maximum discharge time Each batch
6.Plastic Concrete Air Content Yield (Unit Weight) Slump/Spread Concrete Temperature Air Temperature Precast/Prestressed Concrete — First two loads then randomly every 50 cu yd for each concrete class delivered and placed on a calendar day from a single supplier.

Part 600 — Concrete August 2025

SECTION 601 — PORTLAND CEMENT CONCRETE 600-19 *Compressive Strength Specimens Precast/Prestressed Concrete — One set for the first 50 cu yd inclusive and one set for each additional 50 cu yd or fraction thereof and as necessary for formwork removal, stress transfer and shipping (include concrete temperature, air content and slump test results) * The Concrete Producer shall determine the quantity of cylinders necessary for process control of construction operations. ● Concrete Producers Quality Control Plan (QCP). The Concrete Producer shall submit a detailed written QCP to the Engineer for approval annually, at least 60 days before the first concrete placement. Provide a QCP that details the Concrete Producer ’s plans, policies, procedures , and organization deemed necessary to measure and control materials, equipment, and concrete production processes. Ensure that t he QCP reflect s the current status of the operations; submit proposed changes to the QCP to the Engineer. Changes must be approved by the Engineer before implementation. At a minimum, provide a QCP that details the following: ○ Scope of QC Plan . Reference all applicable specifications, including the latest revision of the Standard Specifications plus all applicable compilations and supplements. ○ QC Organization . Include a QC organizational chart identifying all personnel responsible for implementing the QCP and how staff integrate and communicate within the Concrete Supplier ’s management structure and with the Engineer. Include a list of QC personnel and their names, qualifications, responsibilities, levels of authority, certifications, telephone contact number(s) , and e -mail addresses. ○ QC Testing Facilities and Equipment. Include the location and qualifications of QC testing facilities and a list of all QC testing equipment with the frequency of calibration and verification. ○ Materials Control. Include the source(s) for all materials used in the production of Portland cement concrete and receiving, storage, and handling practices. For fine and coarse aggregates , describe stockpile management practices, including stockpile identification, separation, segregation mitigation, and loading. ○ Concrete Production. Provide a description of the concrete plant and concrete batching operations, including: + Plant location and layout + Production equipment + Method and sequence of batching + Mixing capacity and minimum mixing time + Method of monitoring ingredients and recording batches + Methods of delivery

Part 600 — Concrete August 2025

600-20 SECTION 601 — PORTLAND CEMENT CONCRETE ○ QC Activities. Describe QC activities deemed necessary to control all aspects of concrete production. Include the locations, methods, frequency , and personnel responsible for conducting QC sampling, testing, and inspection. Identify lot/sublot sizes, the sample identification system, and sample storage/retention procedures. The minimum required QC activities are listed in the preceding Tables. ○ Pre-Placement (Precast/Prestressed Plants only) . Include source, storage , and handling procedures for steel reinforcement, prestressing strand, hardware , and inserts. Describe procedures and equipment for tensioning and detensioning of prestressing steel strands. ○ Concrete Placement (Precast/Prestressed Plants only) . Describe methods, equipment, and materials for placement, consolidation, finishing , and curing of concrete. Include sequencing of work and maximum discharge times. Include procedures for determination of concrete strength for formwork removal and application of load. See Subsection 809.03.8 for the curing of precast and prestressed concrete members. ○ Post Production (Precast/Prestressed Plants only). Describe procedures for post- production inspection, including product condition assessment, measurement of product geometry, and camber (as applicable). Include procedures for handling and storage of finished products. ○ Documentation. Describe documentation and reporting procedures for all QC activities. Include samples of all QC forms, reports, and control charts. ○ Non-Conformance and Corrective Action. Establish and maintain an effective and positive system for controlling non-conforming material and products as indicated by inspection and test results. Investigate the cause of any non-conformance to prevent recurrence, and take prompt corrective action to correct conditions that have resulted, or could result, in the incorporation of non-conforming materials and products into the work. Positively identify a ll non -conforming materials and products to prevent use, shipment, and intermingling with conforming materials and products. Provide segregated holding areas, subject to the approval of the Engineer. Include criteria for identifying non -conforming materials and products and procedures for isolation, disposition, and documentation. Include procedures and personnel responsible for directing corrective action, including suspension of work, disposal, and reclaiming or reworking of non -conforming materials and products. Detail how the results of QC inspections and tests will be used to determine corrective actions, and define rules to gauge when a process is out of control and the associated corrective action to be taken. At a minimum, establish corrective action procedures for each control requirement listed in the preceding Tables. ● Records and Documentation. The Concrete Producer shall maintain complete records for all QC tests and inspections. Ensure that t he QC records contain all test and inspection reports, forms and checklists, equipment calibrations, component material certificates of compliance and mill test reports, and non -conformance and corrective

Part 600 — Concrete August 2025

SECTION 601 — PORTLAND CEMENT CONCRETE 600-21 action reports. Ensure that the QC records will document the nature and number of observations made, the number and type of deficiencies found, the quantities of conforming and non -conforming, and the nature of corrective action taken, as appropriate. Make the QC records available to the Engineer at all times, and retain the records for the life of the Contract. The Concrete Producer ’s documentation procedures will be subject to approval by the Engineer before the start of the work and to compliance checks by the Engineer during the progress of the work. ○ Forms and Reports . Document all QC inspection and test results on NETTCP forms and reports or equivalent as approved by the Engineer. Additionally, generate a non-conformance and corrective action report for each instance where test or inspection results indicate a non -conformance. Ensure that t he report indicates the nature of the non -conformance and corrective actions taken to resolve it. Prepare forms and reports that are complete and on a standardized, publicly used format , and submit to the Enginee r as the work progresses (or weekly, at a minimum). ○ Control Charts . Document a ll conforming and non -conforming test results on control charts, and ensure that they are complete and available to the Engineer at all times during production. Present test data for Portland cement concrete on control charts, including critical gradation(s) (i.e., passing No. 4, No. 100, No. 200 sieves), air content, unit weight , and 28 -day compressive strength for precast/prestressed concrete. Provide control charts that indicate lots and sub - lots, target values, and control limits, all in chronological order with a legend. The Concrete Producer may use other types of control charts as deemed appropriate and as approved by the Engineer. Complete testing and charting within 24 hours after sampling. ○ Certification. At the conclusion of the Project, the Concrete Producer shall certify to the Engineer that all Portland cement concrete and precast/prestressed products have been produced, inspected , and tested according to the requirements of the Contract specifications. ● Engineer’s Acceptance Sampling, Testing , and Inspection . The Engineer is responsible for sampling, testing, and inspection for acceptance, except for furnishing the necessary materials, which shall be the Contractor’s responsibility as directed by the Engineer and at no additional cost to the Department. Acceptance is based on the Engineer’s inspection of the construction, monitoring of the Contractor’s Quality Control Program, and acceptance test results. Provide the Engineer with reasonable access to the records without charge. Samples of fresh concrete for testing will be taken after all concrete retempering is performed. When sampling from within the forms is impractical, samples will be taken at the nearest accessible point in the conveyance system before placement into the forms. Acceptance sampling and testing will meet the requirements of the Contract and the Master Schedule for the Preparation of a Project Schedule for Sampling, Testing, and Certification of Materials.

Part 600 — Concrete August 2025

600-22 SECTION 601 — PORTLAND CEMENT CONCRETE Compressive strength test specimens will be standard 4 in. × 8 in. cylinders for all placements.

b.Engineer’s Acceptance , Sampling, Testing, and Inspection . The following is the acceptance plan necessary to obtain samples, perform tests , and provide inspection of the work. The terms used in this acceptance plan are defined as follows: ● Placement. For a given class of concrete, the portions of a concrete structure constructed during one continuous concrete operation. ● Acceptance Plan. The method of taking measurements of samples to determine the acceptability of a placement of material or construction. Acceptance plans include random sampling plans. ● Random Sample. A sample chosen so that each increment in the lot has an equal probability of being selected. The Engineer reserves the right to take more samples in addition to the samples taken according to the random sampling plan. ● Acceptance. As defined in Para. c below. ● Rejection. When used in this context, “rejection” means remove, dispose, and replace at no cost to the Department or, at the discretion of the Engineer , “rejection” means acceptance at a lower price determined by Pay Factors, as specified herein. ● Lot. An isolated quantity of material from a single source or a measured amount of construction produced by the same process. For placements less than 750 cu yd, the Lot is 150 cu yd or less. For placements of 750 cu yd or greater, the Lot is 250 cu yd or less. Lots will be determined as follows: ○ The total cubic yards for the placement will be divided by 150 for placements less than 750 cu yd, and 250 for placements greater than or equal to 750 cu yd. ○ The result will be rounded up to the next whole number. This number is the number of Lots in the placement. ○ The total cubic yards for the placement in the first bullet will be divided by the number in the second bullet to determine Lot size. ○ Each Lot size will be adjusted by rounding to the nearest 10 cu yd (or other number representing one truck load), and this adjusted Lot size will be used to determine the number of trucks in the Lot. ○ For the acceptance plan , the total cubic yards of concrete placed for all Lots will be the placement volume. ● Sublots. Equal divisions or portions of a Lot are as defined below. The Sublot size for each Lot will be calculated by dividing each Lot into thirds rounded to the nearest truck.

Part 600 — Concrete August 2025

SECTION 601 — PORTLAND CEMENT CONCRETE 600-23 ○ Cylinders will be cast for each placement less than or equal to 150 cu yd of concrete delivered for each class of concrete according to the following: + 1 truck = 4 cylinders from the truck (6 cylinders for Class MC concrete) + 2 trucks = 4 cylinders from 1 randomly selected truck (6 cylinders from 1 randomly selected truck for Class MC concrete) + 3 trucks = 2 cylinders from each of 2 randomly selected trucks (3 cylinders from each of 2 randomly selected trucks for Class MC concrete) + 4 thru 10 trucks = 2 cylinders from 1 randomly selected truck from the first half of the placement and 2 cylinders from 1 randomly selected truck from the second half of the placement. (3 cylinders from 1 randomly selected truck from the first half of the placement and 3 cylinders from 1 randomly selected truck from the second half of the placement for Class MC concrete). + 11 thru 15 trucks = 2 cylinders from 1 randomly selected truck from the first third of the placement, 2 cylinders from 1 randomly selected truck from the second third of the placement and 2 cylinders from 1 randomly selected truck from the final third of the placement. ○ Cylinders will be cast for each placement greater than 150 cu yd and less than 750 cu yd of concrete delivered for each class of concrete according to the following: + 2 cylinders from 1 randomly selected truck from the first third of the Lot, 2 cylinders from 1 randomly selected truck from the second third of the Lot, and 2 cylinders from 1 randomly selected truck from the final third of the Lot. ○ Cylinders will be cast for each placement greater than or equal to 750 cu yd of concrete delivered for each class of concrete according to the following: + 2 cylinders from 1 randomly selected truck from the first third of the Lot, 2 cylinders from 1 randomly selected truck from the second third of the Lot, and 2 cylinders from 1 randomly selected truck from the final third of the Lot. Sidewalk placements will have a minimum of one set of four cylinders taken from one randomly selected truck per Project per day.

c.Placement Acceptance Compressive Strength Evaluation . The 28 -day or 56 -day compressive strengths (fc′) specified in the Table in Subsection 601.03.1 are the strengths used in the design calculations. The Engineer will verify design strengths by tests made during the progress of the work according to AASHTO T23 (Standard Practice for Making and Curing Concrete Test Specimens in the Field) and AASHTO T22 (Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens). Acceptance for Class MC concrete will be based on a 56-day compressive strength test.

Part 600 — Concrete August 2025

600-24 SECTION 601 — PORTLAND CEMENT CONCRETE Three cylinders randomly selected from each set of 4 or 6 cylinders, as determined under “Sublots,” will be tested for either 28-day or 56-day compressive strengths. Case A: Single Lot Placement. The average 28-day or 56-day compressive strength of 3 cylinders selected from a set of 4 or 6 cylinders will be used to calculate the acceptance of the Single Lot Placement. The following formulas will be used to calculate the Placement Acceptance Test Result (PATR). The Engineer has the authority to use Formula – B for any Lot size when more than one set of 3 cylinders are tested. Formula – A PATR = X = X1 + X2 + X3 Symbols: X = individual test value , which is the 28 -day or 56 -day compressive strength of each cylinder tested X̅ = the mean (average) 28-day or 56-day compressive strength of a set of 3 cylinders PATR = Placement acceptance test result Case B: Multiple Lot Placements. For Multiple Lot Placements, 3 cylinders from each set of 6 cylinders from each Lot will be tested for 28 -day or 56 -day compressive strength. The mean value of the sum of the average compressive strengths will be used to calculate the acceptance of the placement. The following formula will be used to calculate the Placement Acceptance Test Result (PATR). Formula – B PATR = X = X1 + X2 + ⋯ Xn n Symbols: X̅ = the mean (average) 28-day or 56-day compressive strength of a set of 3 cylinders for each Lot. X = the mean (average) of the sum of the average 28-day or 56-day compressive strength test result of each Lot. n = number of sets Strength Pay Factors

Part 600 — Concrete August 2025

SECTION 601 — PORTLAND CEMENT CONCRETE 600-25 PATR % of (fc ’ ) Placement Pay Factor (PPF) (%) 95 or greater 1.00 (100) 90 to 94.9 0.90 (90) 85 to 89.9 0.85 (85) When the PATR of structural concrete falls below fc′ submit an investigative plan stamped by a Professional Engineer holding a valid license to practice engineering in the State of Rhode Island outlining how to demonstrate that the in -place concrete’s compressive strength is structurally adequate. The Engineer will approve the investigative plan before the execution of the investigation. After the investigation is completed, submit a report to the Engineer presenting the results of the Professional Engineer’s analysis, testing, and conclusions and any recommended actions proposed for the concrete that did not meet the specified strength requirements. If the Engineer’s analysis demonstrates that the in -place concrete is structurally inadequate , remove the concrete and replace it at no additional cost to the Department. The Contractor may elect to remove and dispose of any non-conforming material and replace it with new material to avoid a PPF of less than 1.00. Any such new material will be sampled, tested, and evaluated for acceptance according to the applicable requirements of SECTION 601. The Engineer may reject any quantity of material that appears to be non -conforming based on visual inspection or test results. Do not use the rejected material in the work. The results of the tests on the rejected material will not be included in the calculation of the Placement Acceptance Test Results.

601.04 Method of Measurement.

Portland Cement Concrete will be measured as provided for in the Contract for the specific item or items under which it is paid. If the measurement is not stipulated elsewhere in the Contract, it will be measured by the cubic yard.

601.05 Basis of Payment.

Portland Cement Concrete, complete and accepted, will be paid for as provided in the Contract. If not stipulated elsewhere in the Contract, it is paid by the cubic yard. The payment constitutes full compensation for furnishing all labor, materials, equipment, tools, and incidentals to produce, place, and protect the concrete as specified, in addition to any requirements for specific use, except that a reduction in payment will be made for each placement of concrete not fully accepted. This reduction in payment for placement will be based on the following: Case 1: For concrete for which a unit price is provided in the Proposal: Unit price reduction = PPF × number of cu yd that the PATR represents × the unit bid price in the Proposal

Part 600 — Concrete August 2025

600-26 SECTION 601 — PORTLAND CEMENT CONCRETE Case 2: For concrete that is paid for as part of a lump sum item or lump sum items as listed in the Proposal: PPF × number of cu yd that the PATR represents × the price of the various items of concrete per cubic yard as provided in the approved Contractor’s lump sum breakdown PPF is the pay factor determined in Subsection 601.03.8(c).

Part 600 — Concrete August 2025

SECTION 602 600-27 SECTION 602 This Section has been Reserved for Future Use.

Get an email when 601 changes

Rhode Island revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Road and Bridge Construction (Blue Book), 2022 (Aug 2025 compilation) Edition. Pages 280–306 of 951. View official source ↗

Ask about this section

Scoped to Rhode Island RIDOT Standard Specifications for Road & Bridge Construction, Section 601 — Portland Cement Concrete. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.