SECTION 825 — PAINTING STRUCTURAL STEEL — PAINTING STRUCTURAL STEEL
825.01 Description.
This work includes the thorough cleaning, preparation of surfaces, painting or repainting of new or existing steel, galvanized, and metalized structures, its components or other steel materials at the required locations. Submittals. Submit the items listed below to the Department for approval before performing any work. This list does not include required submittals that are a part of other related Specifications: • Contractor applicator qualifications and material certifications. Refer to Subsection 825.01.5 and SECTION M06 • Topcoat color samples • Product Data Sheets (PDS) and Safety Data Sheets (SDS) according to SECTION M06 • Quality Control Plan according to Subsection 825.03.8 • Scaffolding/work platforms • Removal/repair procedures for unsatisfactory material (if required) Toxic Substances. Existing paint systems on the Department’s bridges may contain toxic substances such as lead, chromium, or cadmium, and these substances are considered hazardous to personnel, the environment, and the public proximate to the Project. P lan and take appropriate precautions during the painting operations and for waste disposal to meet the State and Federal requirements for the protection of workers, the public, and the environment. See SECTION 826 for a thorough discussion. Protection of Personnel, Public, Environment, and Structure. This provision addresses the requirements for removal and containment of paint and/or corrosion products from any steel bridge or other specified appurtenances during surface preparation and painting operations . Conduct all activities associated with the coating work specified herein according to all applicable Federal, State, and local regulations, SECTIONS 107 and 826, the Contract Special Provisions and the SSPC-PA Guide 10, “Guide to Safety and Health Requirements for Industrial Painting Projects.” Protect pedestrians from injury, vehicular, and/or other traffic on or under the bridge or structure, surrounding property, surfaces, buildings, grounds, etc., against damage or disfigurement from surface preparation media, or spatters, splashes, overspray , and smears of paint or material . Furnish adequate containment materials for protection. Remove paint drips, spills, or overspray from concrete or other surfaces not designated to receive coatings. Remove and dispose of debris from cleaning operations, and empty paint containers and other refuse at no additional cost to the Department.
Part 800 — Bridge Structures August 2025
SECTION 825 — PAINTING STRUCTURAL STEEL 800-151 Pollution Controls. Prevent environmental pollution of air, soil, and water caused by surface preparation media, paint spills or overspray, paint chips, dust, or other harmful materials. See SECTION 107. Contractor Applicator Qualification. Ensure that all painters are SSPC certified or AISC certified. Demonstrate that the Contractor(s) performing coating application has qualifications by obtaining either the Society for Protective Coatings (SSPC) QP 1 “Standard Procedure for Evaluating Painting Contractors (Field Application to Complex Industrial Structures) ” for field painting or SSPC QP-3 “Certification Standard for Shop Application of Complex Protective Coating Systems” as appropriate, or the American Institute of Steel Construction (AISC) Sophisticated Paint Endorsement (SPE). Demonstrate that the Contractors involved in the removal of paint containing lead or other toxic metals are certified SSPC QP2, “Standard Procedure Evaluating the Qualifications of Painting Contractors to Remove Hazardous Paint. ” For field work involving abrasive blast cleaning and painting , follow the requirements of the SSPC CAS QP1 Implementations Schedule as defined on the SSPC Web site (www.sspc.org) . Maintain the qualification throughout the painting portion of the Project. If the qualification expires or is revoked for any reason, notify the Engineer, who may require that a qualified Contractor complete the coating portion of the Project.
825.02 Materials.
Provide materials that conform to SECTION M06 and to the manufacturer’s recommendations as applicable. If there is a conflict between the manufacturer ’s recommendations and the requirements of this Section, comply with this Section unless the requirements of the manufacturer are more restrictive. In these cases, advise the Engineer of the discrepancies, in writing, and comply with the Engineer’s written resolution. Paint Supplier. Provide all paint material products including primer, intermediate coat, topcoat, and thinners from the same paint supplier and ensure compatibility of components . Use the same paint manufacturer throughout all work. Provide paints that are lead and chromium free. Use a coating system that is an approved NEPCOAT Qualified Product from List A or B according to SECTION M06. Topcoat Color. Provide a semi-gloss topcoat in the color specified. Provide color chips and the Munsel and/or Federal Standard color designation for verification of the color of the topcoat . Ensure that t he color of the primer does not affect the color of the topcoat.
Part 800 — Bridge Structures August 2025
800-152 SECTION 825 — PAINTING STRUCTURAL STEEL VOC Compliance. Ensure that all paint products conform to all Federal, State, and local requirements at the point of application as determined using EPA Method 24.
825.03 Construction Methods.
Surface Preparation.
Part 800 — Bridge Structures August 2025
SECTION 825 — PAINTING STRUCTURAL STEEL 800-153 Substrates” to ensure that detectable chloride levels are less than 10 micrograms per square centimeter. Equip compressed air supply lines with oil traps and moisture separators. Conduct a white blotter test according to ASTM D 4285 to verify the cleanliness of the compressed air. Conduct the test at least once per shift for each compressor system . Sufficient freedom from oil and moisture is confirmed if no soiling or discoloration is visible on the paper. Paint Application.
Part 800 — Bridge Structures August 2025
800-154 SECTION 825 — PAINTING STRUCTURAL STEEL ● There is or will be rain, mist, fog, or snow during application and/or cure. ● The manufacturer’s requirements for reaction time after mixing are not satisfied.
Part 800 — Bridge Structures August 2025
SECTION 825 — PAINTING STRUCTURAL STEEL 800-155 ● Abrasion damage ● Peeling ● Blistering ● Wrinkling ● Excessive runs ● Sags ● Evidence of application under unfavorable conditions ● Poor workmanship ● Use of unauthorized coating material ● Other defects as determined by the Engineer Submit repair procedures for unsatisfactory material to the Department for approval in writing before performing related work. Remove and replace unsatisfactory coating layers at no additional cost to the Department as specified below: ● Bare Steel Exposed Less Than 4 in. × 4 in. Area. When the defective paint or damage extends to the bare steel or if bare steel is exposed in areas less than 4 in. × 4 in. in size, clean the surface by power tool cleaning according to SSPC-SP11. Feather the surrounding paint to expose a minimum of ½ in. of each coat a round the entire perimeter of the repair area and to provide a smooth transition into the surrounding intact, adherent material. Select a primer recommended by the manufacturer for the intermediate and topcoat. For new steel, apply a spot coat of zinc -rich primer to the prepared surface. Follow with a spot coat of the intermediate and topcoat. ● Bare Steel Exposed Greater Than 4 in. × 4 in. Area. When the defective paint or damage extends to the bare steel in areas greater than 4 in. × 4 in. in size, blast clean the area according to SSPC SP10, feather the surrounding paint , and repair as described above. ● Primer or Intermediate Coat Exposed. When the damaged or defective paint extends to the primer or intermediate coat, and for primed areas around and on connection plates, clean the surface by hand or power tool cleaning. Clean according to SSPC SP2 or SSPC SP3 to remove oxidation, zinc-salts, and contamination from the surface. Do not burnish or polish the surface. Supplement hand and power tool cleaning with pressure washing (1500 psi minimum) accompanied by scrubbing with stiff bristled brushes or other means as necessary. Feather the surrounding material to expose a minimum of ½ in. of each coat and to provide a smooth transition into the surrounding intact, adherent coating material. ● All Repairs. For all repairs, roughen the paint in overcoat areas with 80 grit sandpaper to ensure good adhesion of the overcoat material to the underlying paint. Also, solvent clean according to SSPC SP1 and repaint the affected areas with the intermediate and topcoat.
Part 800 — Bridge Structures August 2025
800-156 SECTION 825 — PAINTING STRUCTURAL STEEL
Part 800 — Bridge Structures August 2025
SECTION 825 — PAINTING STRUCTURAL STEEL 800-157 Surface Preparation Requirements for Fasteners and Bolts Item Fasteners Installed Before Cleaning & Primer Application Fasteners Installed After Primer Application Coating System Surface Preparation Coating System Surface Preparation Black Iron Bolts OZ or IOZ, I, T SSPC-SP10 IOZ, OZ, I, T SSPC-SP 1 & 10 Galvanized (Mechanical or Hot Dip) OZ or IOZ, I, T SSPC-SP 1 I, T SSPC-SP 1 & 2/3 Key: • OZ = Organic Zinc-Rich Primer • IOZ = Inorganic Zinc-Rich Primer • I = Intermediate Coat • T = Topcoat If the zinc coating on shop- installed galvanized bolts is damaged during shop abrasive blast cleaning or tightening, the coating may remain as is only if the entire coating system (including the zinc-rich primer) will be applied over the fasteners. Remove the lubricant from bolts . Obtain from the fabricator the identity of solvents and methods needed to remove the lubricant. Consult with the coating supplier to assess the compatibility of the coating with any lubricant residue. Supply to the shop and field painters, the Engineer, and other interested parties the information concerning the lubricant removal and the cleanliness necessary for satisfactory adhesion of the subsequent coat as described in the Table above. Use a white cloth wipe test with no color transfer to confirm that all lubricant and non - absorbed dye has been removed; only residual stain is permitted to remain on the surface.
Part 800 — Bridge Structures August 2025
800-158 SECTION 825 — PAINTING STRUCTURAL STEEL Existing Steel Structures. Work under this section is only applicable to structures that are not addressed under Subsection 825.03.3.
Part 800 — Bridge Structures August 2025
SECTION 825 — PAINTING STRUCTURAL STEEL 800-159
Part 800 — Bridge Structures August 2025
800-160 SECTION 825 — PAINTING STRUCTURAL STEEL Prepare galvanizing according to SSPC SP-16 before painting. Remove white corrosion deposits, such as wet storage stains , before coating. Overcoat with any of the NEPCOAT approved intermediate coats followed by applying the compatible NEPCOAT-approved topcoat. The natural profile of metalized surface will not require any surface preparation. For any process that reduces the metalized or galvanized thickness below the specification limit, remove and re-apply the metalize or galvanize, as applicable, to meet the specification. Apply the intermediate coat to the surface as soon as possible after the Engineer has accepted the metalizing or galvanizing surface preparation and no later than eight hours after the preparation. If more than eight hours elapses, provide written recommendations from the intermediate coat manufacturer that identify the required steps to compensate for any oxidation and make the surface suitable for the intermediate coat application. Do not implement the steps without written approval from the Engineer. Apply a stripe coat of urethane to all edges of bolted connections and other areas followed by a full approved finish coat of urethane. Stenciling of Topcoat. After the topcoat has fully cured, provide stencil information on the inside surface of the fascia member at each abutment location. Use suitable black paint or other color as approved by the Engineer to contrast with the topcoat for visibility. Stencil uniform block lettering on the surface, 2 in. to 3 in. in height, with the following information: • The bridge identification number as shown on the Plans • The month and year of completion of the coating system (MM/YYYY) • The SSPC identification of the cleaning method • Identification of the coating system (for example: IOZ/OZ, E, U) with the name of the manufacturer; use the following designations: ○ IOZ = Inorganic Zinc Rich Primer ○ OZ = Organic Zinc Rich Primer ○ M = Metalized ○ G = Galvanized ○ E = Epoxy ○ U = Urethane Lighting. Provide adequate lighting for all surface preparation, paint application, and inspection work. Maintain a minimum of 10 ft-candles for surface preparation and painting, and a minimum of 30 ft-candles of general area lighting for inspection. Increase the lighting if workers or other personnel have difficulty seeing. Use explosion-proof lighting. Quality Control. Document and conduct an on-going Quality Control plan for the process and for the inspection of the materials, surface preparation, coating applications storage, and shipping of components as
Part 800 — Bridge Structures August 2025
SECTION 825 — PAINTING STRUCTURAL STEEL 800-161 necessary to ensure that all work is performed in compliance with the Contract Documents and the manufacturer’s recommendations. At a minimum, address the following: • Qualifications, authority, and responsibilities of the QC Manager • Qualifications, responsibilities, and training for workers (Include the frequency of checks on the quality of work) • Documentation of the proposed equipment and calibration records • How the QC documentation and supporting records are maintained • How the surface preparation of the steel before the application of the paint system, especially the profile, is verified and monitored (e.g., frequency). For galvanized steel, include the method of profiling • How the environmental conditions (e.g., ambient temperature, dew point, relative humidity) for various stages of the paint process are monitored and maintained throughout the duration of the Project • How the coating materials and abrasives are verified and monitored for receipt, storage, and control • How the coating materials are verified and monitored for batch numbers, mixing, pot life, mix reaction time, dry time, curing, recoat time, and cleanliness of each coat before the application of the subsequent coat • How the coating materials, including galvanize and metalize, are inspected and accepted for appearance, film thickness, adhesion, etc. For galvanized surfaces, include the galvanize thickness after the surface preparation. • How the coating films are inspected for defects • How the faying surfaces are treated and protected • How the coatings of steel components are protected from damage during storage, shipping, and erection Equipment and Standards. If requested by the Engineer, f urnish the following equipment and standards , which will be returned to the Contractor when the Engineer is finished with the inspection: • Magnetic contact surface thermometer • A portable instrument capable of measuring and digitally displaying the temperature, humidity and dew point • SSPC VIS Standard appropriate for the specified degree of cleaning: ○ SSPC VIS 1, “Visual Standard for Abrasive Blast Cleaned Steel” ○ SSPC VIS 3, “Visual Standard for Power- and Hand-Tool Cleaned Steel” ○ SSPC VIS 4/NACE ○ SSPC VIS 4/NACE VIS 7, “Guide and Reference Photographs for Steel Surfaces Prepared by Waterjetting”
Part 800 — Bridge Structures August 2025
800-162 SECTION 825 — PAINTING STRUCTURAL STEEL • Wet film thickness comb or combs of a suitable scale for the coatings being applied • A digital display dry film thickness gauge with a scale suitable for the coatings being applied and probes suitable for the surface to be measured • NIST (NBS) Calibration Standards • SSPC Surface Preparation Standards appropriate for the surface preparation requirements of the Contract Documents • A microscope with an illuminated graduated scale suitable for the dry film coating thicknesses to be measured; provide suitable cutters to create scratches of the geometry needed to take measurements with the microscope. Provide current certificates of calibration for the instruments. Pre-Painting Meeting. Arrange a meeting at the site where the surface preparation and painting will be performed at least one month in advance of starting the work to discuss the P roject requirements with the Department and the manufacturer’s technical representative and for an examination of the surface preparation and paint application equipment. The meeting will address: • Methods of operation • Weather-related concerns • Health and safety • Proper storage of material and equipment • Location of recycling, dust collection, and storage equipment • Treatment of inaccessible areas • Visual standards to be satisfied Provide the QCP to the Engineer for review at least two weeks before this meeting. Do not proceed with the work until this meeting has been completed to the satisfaction of the Engineer.
825.04 Method of Measurement.
Painting Existing Structural Steel. Painting Structural Steel will be measured by the number of square feet of steel painted. Cleaning, surface preparation, and paint systems on new steel will be considered as incidental to the painting work and, therefore, will not be measured separately. Surface Preparation for Existing Steel. Surface Preparation for Existing Steel will be measured by the number of square feet of steel surface prepared. Separate levels of surface preparation necessary to accomplish the final specified surface preparation will not be measured separately for payment but will be considered included in the single square foot measurement.
Part 800 — Bridge Structures August 2025
SECTION 825 — PAINTING STRUCTURAL STEEL 800-163 Lump Sum Alternative. In some cases, any or all of the above items of work may be paid on a lump sum basis. In these cases, no measurement will be required. Personnel and Environmental Protection. Personnel and environmental protection will be measured according to SECTION 826.
825.05 Basis of Payment.
The Department will pay for the completed and accepted quantities as follows. Pay Item Pay Unit Painting Existing Structural Steel SF Surface Preparation for Existing Steel SF Painting Existing Structural Steel. The price constitutes full compensation for all labor, materials, and equipment including cleaning, surface preparation, selection of paint system, painting, and all incidentals required to finish the work, complete and accepted. Surface Preparation for Existing Steel. The price constitutes full compensation for all labor, materials, equipment, and all incidentals required to finish the work, complete and accepted.