8−180 Engineer. SECTION 835 SCUPPERS
835.01 DESCRIPTION . This work consists of providing scuppers and connections to their drains
at the locations indicated on the Plans or as directed by the Engineer, all in accordance with these Specifications. 835.02 MATERIALS . Scupper frames and grates shall conform to the requirements of Para. c and Para. d, respectively, of Subsection M.05.04.9 of these Specifications.
835.03 CONSTRUCTION METHODS . The scupper assembly shall be installed, anchored and
supported as shown on the Plans. 835.04 METHOD OF MEASUREMENT . "Scuppers" will be measured by the number of such assemblies actually installed in accordance with the Plans and/or as directed by the Engineer.
835.05 BASIS OF PAYMENT . The accepted quantity of "Scuppers" will be paid for at the contract
unit price per each assembly as listed in the Proposal. The price so-stated constitutes full and complete compensation for all labor, materials and equipment, and all incidental s required to finish the work, complete and accepted by the Engineer. BY EPOXY-RESIN BASE ADHESIVE INJECTION
836.01 DESCRIPTION . This work consists of repairing cracks in concrete by furnishing and
injecting epoxy-resin base adhesives into such cracks. The work also incl udes surface preparation, setting injection ports and cleaning surfaces followi ng repairs. Crack repair work shall be performed at locations indicated on the Plans or as directed by the Engineer, all in accordance with these Specifications. 836.02 MATERIALS . All products indicated below must be listed in the Department’s Approved Materials List. 8−181836.02.1 Injection Material . Injection material shall be a low viscosity, two-part epoxy-resin system conforming to the requirements of ASTM C-881, Type IV. The material shall also be the required grade and class to satisfactorily perform its function.
836.03.2 Component Ratio Calibration Test . The mixing head of the injection equipment shall be
disconnected and the two adhesive components shall be pumped simultaneously through two independent valved nozzles. Both adhesive com ponents shall be simultaneously discharged during the same time period such that they may be compared to determine the volume. The Engineer, at any time and without prior notification to the Contractor, may request the Contractor to conduct the calibration test specified above. 836.03.3 Epoxy Injection. Epoxy injection shall be performed in accordance with the manufacturer’s recommended methods. If a recommended application procedure is not available, the Contractor shall use the following epoxy injection technique: 8−182
836.05 BASIS OF PAYMENT . The accepted quantity of “Structural Concrete Crack Repair by
Epoxy-Resin Base Adhesive Injection” will be paid for at the concrete unit price per linear foot as listed in the Proposal. The price so-stated constitutes full and complete compensation for all labor, tools, materials, equipment, including scaffolds, and all incidentals required to finish the work, complete and accepted by the Engineer. 8−183SECTION 837 REPAIRS TO STRUCTURAL CONCRETE MASONRY WITH INTEGRALLY COLORED CONCRETE OR PATCHING MORTAR 837.01 DESCRIPTION . This work consists of removing all deteriorated, disintegrated, soft, honeycombed, fractured, or otherwise defective concrete and replacing it with integrally colored Portland cement concrete, or Portland cement mortar at locations indicated on the Plans or as directed by the Engineer. The concrete or mortar shall be of a color, texture and have aggregates from approved sources that closely match the predominant color, texture and aggregates of the existing concrete structure. Repairs shall include, but will not be limited to: removal and disposal of damaged concrete, cleaning and preparing of the bonding surface, cleaning of existing reinforcing steel, placing of additional reinforcing steel where required, application of a bonding agent slurry, and placement of new concrete repair materials to restore the structural elements to the original line, grade, and surface finish (color and texture). The Contractor shall submit a repair plan for each specific type of repair in accordance with the Plans and these Specifications. 837.02 MATERIALS . All proposed repair materials shall conform to the applicable requirements of Subsection 817.02 of these Specifications and/or be listed on the Department’s Approved Materials List. 837.02.1 Aggregate . The fine and coarse aggregates must be approved by the Engineer as to color and texture. 837.02.2 Integrally Colored Concrete . Integrally colored Portland cement concrete shall conform to the applicable requirements of SECTION 601 of these Specifications. The concrete classification and location used shall be as specified on the Plans and/or as directed by the Engineer. 837.02.3 Integrally Colored Patching Mortar . Patching mortar shall conform to the applicable requirements of Subsection 817.02.2 of these Specifications except that the maximum water cement ratio shall not exceed 0.40 by weight. The consistency of the mortar shall meet the application requirements. 837.02.4 Coloring Pigment . Coloring pigments for integrally colored concrete or patching mortar shall meet the requirements of ASTM C979 and be approved by the Engineer. Coloring pigments shall be used in accordance with the manufacturer’s recommendations. 837.02.5 Portland Cement Bonding Grout Slurry . The bonding grout slurry shall have the cement and mortar sand proportioned 1-to-1 by vo lume. Water shall be added in sufficient quantity to form a slurry.
837.02.6 Concrete Anchors. Mechanical concrete anchors shall be hooked type expansion bolts
galvanized in accordance with the applicable requirements of Subsection M.05.04.4, Para. d of these Specifications and shall be of a type approved by the Engineer. 837.02.7 Wire Mesh Reinforcement. Wire mesh shall be galvanized or epoxy coated, in accordance with ASTM A884, welded fabric No. 12 gauge wire (minimum size) spaced two inches