Part 800 — Bridge Structures

839Remove and Dispose Asphalt Concrete Pavement From Concrete Bridge Decks – Partial-Depth and Full-Depth

RI · 2022 (Aug 2025 compilation) Standard Specifications✓ Full text on BuildSpecBook pages 560–561 Save this section

Ask about Section 839

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

SECTION 839 — REMOVE AND DISPOSE ASPHALT CONCRETE PAVEMENT FROM CONCRETE BRIDGE DECKS – PARTIAL-DEPTH AND FULL-DEPTH 800-191 — REMOVE AND DISPOSE ASPHALT CONCRETE PAVEMENT FROM CONCRETE BRIDGE DECKS – PARTIAL-DEPTH AND FULL-DEPTH

839.01 Description.

Partial-Depth Removal. This work includes the removal and disposal of a portion of the existing asphalt pavement overlay from the concrete bridge deck within the required limits. Full-Depth Removal. This work includes the complete removal and disposal of the existing asphalt pavement overlay, including the waterproofing membrane, from the concrete bridge deck within the required limits.

839.02 Materials.

Not applicable.

839.03 Construction Methods.

Partial-Depth Removal. Ensure that the process of partial pavement removal will not cause any damage to the waterproofing membrane, underlying concrete deck, and/or bridge joints to remain. Ensure that the method proposed will remove the specified layer thickness of the asphalt wearing surface. Full depth removal is prohibited. Submit t he specifications, including gross weight(s) of the proposed equipment and/or machinery to be used for the removal operation, to the Engineer for consistent with Subsection 105.02 before the start of work; the Engineer will respond to the Contractor consistent with Subsection 105.02. Ensure that the proposed equipment and/or machinery loads do not exceed the legal load limit or the posted load limit for the bridge, whichever is less. Use equipment and/or machinery that has the capability and precision necessary to adhere to the pavement removal depth requirements. Where required, saw cut the pavement to prevent overbreakage into the vehicular traveled way. If this type of over-breakage does occur, immediately patch the damaged asphalt areas using an asphalt patching material that conforms to SECTION 410. Full-Depth Removal. Ensure that the process of remov ing the pavement and the waterproofing membrane will not cause any damage to the underlying concrete deck and/or bridge joints to remain. E nsure that the method proposed will completely remove the existing waterproofing membrane to allow for the proposed deck patching repairs and new waterproofing system installation. Submit the specifications, including gross weight(s) of the proposed equipment and/or machinery to be used for the removal operation, to the Engineer for approval consistent with Subsection

105.02 before the start of work; the Engineer will respond to the Contractor consistent with

Part 800 — Bridge Structures August 2025

800-192 SECTION 839 — REMOVE AND DISPOSE ASPHALT CONCRETE PAVEMENT FROM CONCRETE BRIDGE DECKS – PARTIAL-DEPTH AND FULL-DEPTH Subsection 105.02. Ensure that the proposed equipment and/or machinery loads do not exceed the legal load limit or the posted load limit for the bridge, whichever is less. Where required, saw cut the pavement to prevent overbreakage into the vehicular traveled way. If this type of overbreakage does occur, immediately patch the damaged asphalt areas using an asphalt patching material that conforms to SECTION 410.

839.04 Method of Measurement.

Partial-Depth Removal and Disposal of Asphalt Pavement from Concrete Bridge Decks and Full- Depth Removal and Disposal of Asphalt Pavement from Concrete Bridge Decks will be measured by the number of square yards of each removed.

839.05 Basis of Payment.

The Department will pay for the completed and accepted quantities as follows. Pay Item Pay Unit Partial-Depth Removal and Disposal of Asphalt Pavement from Concrete Bridge Decks SY Full-Depth Removal and Disposal of Asphalt Pavement from Concrete Bridge Decks SY The prices constitute full compensation for the complete removal and disposal of asphalt pavement and all materials, labor, tools, equipment, saw cutting, and incidentals necessary for the proper completion of the work specified, complete and accepted.

Referenced in this section

Get an email when 839 changes

Rhode Island revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Road and Bridge Construction (Blue Book), 2022 (Aug 2025 compilation) Edition. Pages 560–561 of 951. View official source ↗

Ask about this section

Scoped to Rhode Island RIDOT Standard Specifications for Road & Bridge Construction, Section 839 — Remove and Dispose Asphalt Concrete Pavement From Concrete Bridge Decks – Partial-Depth and Full-Depth. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.