SECTION 840 — DECK SURFACE CONCRETE REMOVAL BY HYDRODEMOLITION 800-193 — DECK SURFACE CONCRETE REMOVAL BY HYDRODEMOLITION
840.01 Description.
This work includes the removal of deteriorated concrete from reinforced concrete bridge deck surfaces using hydrodemolition methods, the provision of adequate containment measures under the bridge deck, the control and diversion of runoff during the hydrod emolition operations, disposal of all concrete and other materials removed by hydrodemolition, and all other incidentals as necessary to complete the work.
840.02 Equipment.
Remove the concrete by hydrodemolition equipment that produces a high-pressure water stream capable of removing concrete, asphalt, oil, dirt, concrete laitance, and rust from the exposed reinforcing bars by direct impact. Do not use rotary milling or mechanical abrading machines. Use hydrodemolition equipment that includes filtering and pumping units operating in conjunction with a remote-controlled robotic device and, if applicable, that can use river, stream, or lake water. Do not withdraw water from any body of water under the jurisdiction of the RI Department of Environmental Management (RIDEM) or the Coastal Resources Management Counc il (CRMC) unless authorized by a permit issued by the appropriate regulatory agency. Use hydrodemolition equipment that can produce a water jet through an orifice at a pressure of at least 17,000 psi. Ensure that the machine can move the jet transversely across the area and forward or backward so that the entire deck is exposed to the water jet. Use mechanical means to move the jet; do not manually move the water jet except at inaccessible areas such as proximity to the curb and temporary barriers or at bridge deck expansion joints. Use equipment that operates at a noise level of less than 90 decibels at a distance of 50 ft from either the powerpack unit or the remote robot. Controls. Ensure that the hydrodemolition equipment has sufficient controls to control and vary the following functions of the machine: • Water pressure • Angle and distance of the orifice relative to the deck surface • Limits of transverse and longitudinal movement of the orifice • Speed of the orifice in the transverse and longitudinal direction Submissions and Qualifications. Assume responsibility for any delay if the post-qualification criteria are not satisfied. Submit the required post-qualification information on the hydrodemolition operations for approval by the Engineer. The Contractor may submit more than one set of documentation. Adhere to the following requirements:
Part 800 — Bridge Structures August 2025
800-194 SECTION 840 — DECK SURFACE CONCRETE REMOVAL BY HYDRODEMOLITION
840.03 Construction Methods.
Concrete Removal. Adjust the hydrodemolition equipment so that the depth of concrete removed from areas of sound concrete is approximately ½ in. Where deteriorated concrete is encountered, the Engineer will establish the removal depth. Use the following trial test procedure to ensure that the correct amount of sound concrete is removed by the hydrodemolition machine:
Part 800 — Bridge Structures August 2025
SECTION 840 — DECK SURFACE CONCRETE REMOVAL BY HYDRODEMOLITION 800-195 surface for soundness in the presence of the Engineer and following the removal of the asphalt wearing surface.
Part 800 — Bridge Structures August 2025
800-196 SECTION 840 — DECK SURFACE CONCRETE REMOVAL BY HYDRODEMOLITION Use methods for the control, maintenance, and disposal of hydrodemolition runoff that conform to SECTION 214. Ensure that the runoff control features are in place and operational before beginning concrete removal. Prevent runoff across traveled way, into bridge drainage devices, or into areas below or adjacent to the bridge, except for the containment basin. Reinforcing Steel. Following the hydrodemolition operation, inspect all exposed reinforcing steel to ensure that it has been cleaned of all rust and corrosive products, including oil, dirt, concrete fragments, laitance, loose scale, and other coatings that could destroy or inhibit the bond with the new concrete. Reclean exposed reinforcing steel not adequately cleaned by the initial hydrodemolition process. If the bars are deteriorated such that they have lost 25 percent or more of their original diameter, replace the steel as specified according to either the Contract or SECTION 818. When cleaned reinforcing steel is exposed for more than seven calendar days, protect the steel from contamination by the type of materials listed above. A light coating of rust can be expected to form on the reinforcing; this is not considered contamination. Concrete Placement. Conduct the placement and finishing of concrete for deck repairs and deck overlays as specified in SECTION 818.
840.04 Method of Measurement.
Deck Surface Concrete Removal by Hydrodemolition will be measured by the number of square feet of deck surface removed.
840.05 Basis of Payment.
The Department will pay for the completed and accepted quantities as follows. Pay Item Pay Unit Deck Surface Concrete Removal by Hydrodemolition SF The price constitutes full compensation for the removal of the bridge deck surface concrete to the limits shown i n the Contract, including all labor, equipment, tools, design and installation of protective shields, runoff diversion and incidentals necessary for proper completion of the work, complete and accepted. Supplemental steel reinforcement will be paid separately under SECTION 810. No additional payment will be made for the removal of deteriorated concrete in excess of 2 in. with the hydrodemolition equipment unless specified on the Plans or for any miscellaneous trim
Part 800 — Bridge Structures August 2025
SECTION 840 — DECK SURFACE CONCRETE REMOVAL BY HYDRODEMOLITION 800-197 work along the curb, temporary barriers, or on the deck, as required to fulfill the requirements of this Specification.
Get an email when 840 changes
Rhode Island revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.