903Fences

RI · 2022 (Aug 2025 compilation) Standard Specifications✓ Full text on BuildSpecBook pages 616–621 Save this section

Ask about Section 903

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

SECTION 903 — FENCES 900-9 — FENCES

903.01 Description.

General. This work includes providing woven wire fence of the chain link design, including gates, posts and post foundations, hardware, and appurtenances of various types (e.g., snow fence), colors and configurations at the required locations. This Section addresses fencing for temporary and permanent locations on roadways. It does not address fencing on bridges. Permanent Chain Link Fence. This work includes the furnishing and installation of permanent chain link fencing for protecting and controlling access. Temporary Chain Link Fence. This work includes the furnishing, installation, and removal and disposal of temporary chain link fencing for protecting and controlling access. This work also includes the relocation of temporary fencing to various locations within the Project limits over the duration of the Project, as necessary. Split Rail Fence. This work includes constructing split rail fencing and gates, including posts, post foundations, and all necessary hardware. Fence Post Replacement. When a fence post requires replacement at locations as directed by the Engineer but continuous sections of fence do not require replacement, installing and attaching a new fence post to existing fabric is a separate Pay Item. This work consists of performing all operations necessary to furnish and install all components of the fence post replacement, including attachment to existing fence fabric at locations as directed by the Engineer and the removal and disposal of the existing fence post off site. This includes all types, materials, and finishes of fence posts. The types include, but are not limited to, end, corner, intermediate, line, and gate posts. Gate posts are part of the gate items and will only be paid for separately if the gate post but not the gate requires replacement. Fence Fabric Replacement. When fence fabric requires replacement at locations as directed by the Engineer but continuous posts do not require replacement, installing and attaching new fence fabric to existing posts is a separate item. This work consists of performing all operations necessary to furnish and install all components for the replacement of fence fabric , including attachment to existing posts and the removal and disposal of the existing fence fabric off site. This includes all types, materials, and finishes of fence fabric.

Part 900 — Incidental Construction and Services August 2025

900-10 SECTION 903 — FENCES

903.02 Materials.

Use m aterials for chain link fences, gates, posts and post foundations, hardware , and appurtenances that conform to SECTION M08. Chain Link Fence. For permanent and temporary chain link fencing, use gates, posts, fittings, and related hardware that conform to Subsection M08.02. For fittings and other hardware not specifically included in these specifications, use standard commercial grade. Split Rail Fence. Use materials for split rail wood fences, gates, posts, and all related hardware that conform to Subsections M08.04 and M08.06. Fence Post/Fabric Replacement. Use materials and finishes that match the existing fence’s original application.

903.03 Construction Methods.

General. Perform clearing as necessary to construct the fence to the required grade and alignment. At locations with small streams or drainage ditches where it is not practical to conform the fence to the general contour of the ground surface, span the opening below the fence with wire fastened to stakes of the length required. Tie new fence to the terminals of existing fences, and stake down the chain link fence at several points between posts. At each location where electric al transmission or distribution lines cross any fence type covered by this Specification, furnish and install a ground conforming to Section 9 of the National Electric Safety Code. Installing Posts. Set p osts in Class A concrete w hen the Contract requires that posts, braces , or anchors be imbedded in concrete, and install temporary guys or braces as required to support the posts in proper position until the concrete has set sufficiently to anchor the posts. Do not place materials on posts or place strain on guys and bracing that are set in concrete until directed by the Engineer. Extend concrete footings to the required depth and dimensions. Where rock is encountered within the required depth to which the post will be erected, drill a hole of a diameter slightly larger than the largest dimension of the post into the rock , and grout the post in. Place the regular dimensioned concrete footing between the top of the rock and required grade. Use hollow pipe and tube type post that is fitted with post tops. Ensure that the bases of the post tops have flanges that fit around the outside of the posts and are secured.

Part 900 — Incidental Construction and Services August 2025

SECTION 903 — FENCES 900-11 Use tension wires in sections of chain link fence. Place the top and bottom tension wire, stretched taut and secured at ends, to all posts in a satisfactory manner before fabric is placed. Installing Fabric. Place the fabric on the outside of the fence. Splice the rolls of fabric together. At end, corner, or gate posts, slip the stretcher bar through the end picket of the fabric and the stretcher bar bands at the same time. Tighten t he bolts in the stretcher bar bands. Stretch the fence at intervals of 100 ft. Secure one end of the fabric and apply sufficient tension to remove all slack before making the subsequent attachments. Tie the fabric to the tension wire with fabric ties spaced not more than 24 in. apart. Attach the fabric to the line posts with fabric ties spaced not more than 14 in. apart. Place the topmost clip on the line post as near to the top of the fabric as possible and the lowest clip as near to the bottom of the fabric as possible. At terminal sections (end, corner , and pull) and gate posts, fasten the fabric stretcher bars and bands. Space the fastenings not more than 14 in. on center for terminal sections (end, corner , and pull) and gate posts. Place t he topmost band on these posts as near to the top of the fabric as possible and the lowest band as near to the bottom as possible. Before making a closure, fasten the other end of the run to the end, corner, or gate post as described previously. Use the following for t he operation of making a closure of a run. Clamp the stretching equipment on the ends of the fabric parallel to each other and approximately 5 ft apart when the tension is first applied. Continue the stretching until the slack has been removed from both sections of the fabric. If the ends overlap, cut the fabric to match. Join the ends by the insertion of a picket. Braces. When top rail is not used, place braces 12 in. down from the top of the terminal posts and extend from the terminal (end, corner, and pull) post and gate posts to the brace post. Fasten the braces to the post, and truss the braces from the brace post back to terminal post with round rod and turnbuckle. Gates. Place the lower hinge (ball and socket type) on top of the concrete in which the gate post is set. Set the sockets for the cone and foot bolt in concrete so that the plunger pin will fit perfectly in the socket when the gate is in a closed position. Erect the g ates to swing in the direction indicated and provide with gate stops. Ensure that all hardware is secured, properly adjusted, and left in perfect working order. Adjust hinges and diagonal bracing in gates so that gates will hang level. Existing Fence Connection. Where a new fence joins an existing fence, set the corner post with brace post at the junction and brace the corner posts . If the connection is made at other than the corner of the new fence, ensure that the last span of the old fence contains a brace span.

Part 900 — Incidental Construction and Services August 2025

900-12 SECTION 903 — FENCES Chain Link Fence. Permanent or temporary chain link fence may be supported by fence posts that provide adequate support. When used, fence posts set in the ground may be stabilized with grout or concrete or may be supported by holes cored into asphalt or concrete pavement when specified in the Contract or permitted by the Engineer. Fence sections may be fabricated in modular panels if the panels are fastened together with approved clamping devices. Split Rail Fence. Set posts plumb at a minimum depth of 3 ft - 0 in. in concrete footings or in holes backfilled and compacted, and set in alignment with the horizontal rail elements. Repair and/or Replace Fencing. If existing, permanent fences are damaged by traffic, wildlife, vandals, etc., after installation but before Final Acceptance of the Contract, repair or replace the damaged elements based on Subsection 104.05. Repair or replace existing fencing that is damaged by traffic, wildlife, vandals, etc., and/or perform maintenance of the system if required as determined by the Engineer. This work includes 1) repairing components of an existing fence, or 2) replacing the existing fence with new fence and removal of the existing components and/or system. Complete repairs required as a result of manufacturing defects, installation defects, or Contractor operations at no additional cost to the Department. When required, furnish replacement parts and repair the fence as necessary, but in no case more than 10 working days after notification from the Engineer. Once the Contractor has initiated repairs, ensure that the area is protected and that the work continues until all repairs are complete. Notify the Engineer if the work cannot be completed within the required timeframe.

903.04 Method of Measurement.

Fence. Fence of the various types indicated will be measured in linear feet, end to end along the top of fence, of continuous sections installed. Gates. Gates will be measured by the number of units installed. Post Holes in Ledge for New Fence. Post Holes in Ledge for New Fence will be measured by the number of holes installed.

Part 900 — Incidental Construction and Services August 2025

SECTION 903 — FENCES 900-13 Chain Link Fence and Gate. Chain Link Fence will be measured in linear feet, end to end along the top of fence of continuous sections installed. Chain Link Gate will be measured by the number of units installed. Split Rail Fence and Gate. Split Rail Fence will be measured in l inear feet along the top of fence between post centerlines for the sections installed. Split Rail Gate will be measured by the number of units installed. Fence Post. Fence Post will be measured by the number of posts installed when installed and attached to existing fence fabric. When installing new fence posts and new fence fabric, refer to Subsection 903.04.1. Fence Fabric. Fence Fabric will be measured in linear feet, end- to-end along the top of fence, of continuous fence fabric installed and attached to existing posts. When installing new fence fabric and new posts, refer to Subsection 903.04.1.

903.05 Basis of Payment.

The Department will pay for the completed and accepted quantities as follows. Pay Item Pay Unit Fence LF Gates EA Post Holes in Ledge for New Fence EA Chain Link Fence LF Chain Link Gate EA Split Rail Fence LF Split Rail Gate EA Fence Post EA Fence Fabric LF

Part 900 — Incidental Construction and Services August 2025

900-14 SECTION 903 — FENCES Fence. The price constitutes full compensation for all labor, materials, foundations or supports (all types), and equipment, including clearing and all incidentals required to finish the work, complete and accepted. Gates. The price constitutes full compensa tion for all labor, materials, equipment, and incidentals required to finish the work, complete and accepted. Post Holes in Ledge in New Fence. The price constitutes full compensation for all labor, materials, and equipment, including nonshrink grout, and all incidentals required to finish the work, complete and accepted. Chain Link Fence and Gate. The price constitutes full compensation for all labor, material s, tools, equipment, foundations or supports (all types), and incidentals required to finish the work, complete and accepted. No separate payment will be made for relocating and resetting fencing required by the C ontract or to accommodate the Contractor ’s operations or for removal at the conclusion of the P roject. Install, maintain and/or remove the fences and gates throughout the duration of the Contract at no additional cost to the Department. Split Rail Fence and Gate. The price constitutes full compensation for all labor, material, tools, equipment , foundations or supports (all types), and incidentals required to finish the work, complete and accepted. Fence Post. The price constitutes full compensation for all labor, materials, hardware, tools and equipment, clearing and grubbing, surface preparation, removal of existing fence post and disposal off site, removal of debris and disposal off site, removal of snow up to a depth of 13 in. and disposal off site, and all other incidentals required to finish the work, complete and accepted. When installing new fence posts and new fence fabric, refer to Subsection 903.05.1. Fence Fabric. The price constitutes full compensation for all labor, materials, hardware, tools and equipment, clearing and grubbing, surface preparation, removal of existing fence fabric and disposal off site, removal of debris and disposal off site, removal of snow up to a depth of 13 in. and disposal off site, and all other incidentals required to finish the work, complete and accepted. When installing new fence fabric and new fence posts, refer to Subsection 903.05.1.

Referenced in this section
Sections that cite this one

Get an email when 903 changes

Rhode Island revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Road and Bridge Construction (Blue Book), 2022 (Aug 2025 compilation) Edition. Pages 616–621 of 951. View official source ↗