201.01 124 SECTION 201 – CLEARING AND GRUBBING
201.01 Description ................................ ................................ ................... 124
201.02 Reserved ................................ ................................ ....................... 124
201.03 Clearing and Grubbing ................................ ................................ . 124
201.04 Disposal of Debris ................................ ................................ ........ 127
201.05 Method of Measurement ................................ .............................. 128
201.06 Basis of Payment ................................ ................................ .......... 128
DESCRIPTION
201.01 Description
This work consists of clearing, grubbing, removing, and disposing of all vegetation and debris within the designated limits, except such objects that are to remain or are to be removed according to other items of work. This work also includes preserving from injury or defacement all vegetation and objects designated to remain.
201.02 Reserved
CONSTRUCTION REQUIREMENTS
201.03 Clearing and Grubbing
201.04 Disposal of Debris
Properly dispose of wood debris t hat is chipped on site so that does not become part of embankment. If burning perishable material, follow applicable laws and ordinances. Ensure burning operations proceed under the constant care of competent watchmen, at times and in a manner that will not harm the surrounding vegetation, adjacent property, or anything designated to remain within the right-of-way. If the construction is through land subject to scour, the Engineer may direct the Contractor to dispose of stumps, logs, brush, and similar material in the scoured ditches within the right -of-way, and to cove r the material so deposited with suitable excavation or borrow material. If the Contractor obtains permission to dispose of such material in scoured ditches on private property that is within view of the roadway, the Contractor shall thoroughly cover the material so deposited with suitable material at no cost to the Department. All merchantable timber in the clearing area that has not been removed from the right-of-way before the start of construction shall become the property of the Contractor unless othe rwise specified. 201.05 128 COMPENSATION
201.05 Method of Measurement
If the Contract contains an item for Clearing and Grubbing on a lump sum basis, the Department will not measure the area cleared and grubbed. In cases where changes in the Contract documents affect the right -of-way area or when additional Clearing and Grubbing is required in conjunction with Road and Drainage Excavation (Additional Material) under 203, the Departme nt will make a proportionate adjustment for the increased or decreased area; however, if the bid schedule includes the item for Adjusted Clearing and Grubbing, then the Department will measure and pay for these area adjustments by the acre. Unless otherw ise shown on the Plans, no separate measurement or payment will be made for the items of work defined under Clearing and Grubbing. For Contractor -supplied borrow pits, the Contractor shall include clearing and grubbing costs in the unit price bid for Borr ow Excavation under 203. For Department -obtained designated borrow pit areas, the Department will measure and pay for clearing and grubbing by the acre, provided the item for Clearing and Grubbing (Borrow Pits) is in the Con tract. If the item for Clearing and Grubbing (Borrow Pits) is not in the Contract, the Contractor shall include the costs of clearing and grubbing such designated borrow pit areas in the unit price bid for Borrow Excavation. If the Contract does not conta in an item for Clearing and Grubbing, the Department will consider all Clearing and Grubbing required within the construction limits as incidental to other items of work.
201.06 Basis of Payment
The Department will pay for accepted quantities at the contr act prices as follows: Item Pay Unit Clearing and Grubbing Lump Sum Clearing and Grubbing (Borrow Pits) Acre Adjusted Clearing and Grubbing Acre Such payment is full compensation for providing all materials, equipment, labor, and incidentals to complete th e work as specified. 202.01 129 SECTION 202 – REMOVAL OF STRUCTURES AND OBSTRUCTIONS
202.01 Description ................................ ................................ ................... 129
202.02 Reserved ................................ ................................ ....................... 129
202.03 General ................................ ................................ ......................... 130
202.04 Removal of Bridges, Culverts, and Other Drainage Structures .... 131
202.05 Removal of Pipe ................................ ................................ ........... 133
202.06 Removal of Pavement, Sidewalks, and Curbs Constructed of
Portland Cement Concrete ................................ ........................... 133
202.07 Removal of Underground Storage Tanks ................................ ..... 133
202.08 Water Well Abandonment ................................ ........................... 134
202.09 Method of Measurement ................................ .............................. 136
202.10 Basis of Payment ................................ ................................ .......... 136
DESCRIPTION
202.01 Description
This work consists of removing, entirely or partially, and disposing of all buildings, fences, structures, old pavements, abandon ed pipelines, and other obstructions not designated or permitted to remain, except for obstructions to be removed and disposed of under other contract items. The work also includes backfilling the resulting trenches, holes, and pits, and salvaging designated materials. If the Contract does not include pay items for Removal of Structures and Obstructions, include such work in the prices bid for other items of construction.