201.01Description

This work shall consist of clearing, grubbing, removing, and disposing of all vegetation and debris within the construction limits shown on the plans, except such objects that are designated to remain or are to be removed in accordance with other sections of these specifications. If no construction limits are shown, the right-of-way and easement areas will be the construction limits. This work shall include the preservation from injury or defacement of all vegetation and objects designated to remain. Disposal of material shall be in accordance with 203.08. 10

CONSTRUCTION REQUIREMENTS

201.02General

Right-of-way lines and construction limits will be established. Trees, shrubs, plants, seeded or sodded shoulders, slopes or other items to remain will be designated. All such designated items and vegetation sh all be preserved. All areas outside the construction limits shall remain in their original condition. All damage to natural terrain, vegetation, objects designated to remain, or areas outside the construction limits which have subsequently eroded or been damaged, shall be repaired or replaced 20 in accordance with 621.11. Tree wound dressing required for cut or scarred surfaces of trees or shrubs selected for retention shall be in accordance with 914.09(c).

201.03Clearing and Grubbing

Surface objects, trees, stumps, roots, and other protruding obstructions not designated to remain shall be cleared a nd grubbed, including mowing as required. Undisturbed sound stumps, roots, and non-perishable solid objects, which are a minimum of 3 ft below the final subgrade or slope of embankments, may be left, provided they are as nearly flush as possible. However, they shall not extend more than 4 in. above the ground line or low water level. Sound stumps may be cut off at 30 ground level outside the construction limits of cut and embankment areas if approved.

Except in areas to be excavated, stump holes and other holes from which obstructions are removed shall be backfilled with suitable material and compacted in accordance with 203.23.

Burning of perishable material shall be done in accordance with applicable laws, ordinances, rules, and regulations. All necessary permit approvals shall be obtained prior to burning.

Unless burned in accordance with the requirements herein, perishable materials and debris shall be removed from the right-of-way and disposed of in accordance with

203.08. If allowed, sod may be disposed of within the right-of-way

201.03

All merchantable timber in the clearing area, which has not been removed from the right-of-way prior to the beginning of construction, shall become the property of the Contractor, unless otherwise provided. The value of the timber shall be taken into account when the bid is prepared.

Low hanging branches and unsound or unsightly branches on trees or shrubs 50 designated to remain shall be removed as directed. Branches of trees extending over the roadbed shall be trimmed to give a clear height of 20 ft above the roadbed. All trimming shall be done by skilled workers and in accordance with good tree surgery practices.

201.04Scalping

Areas where excavations are to be made, or embankments are to be placed, shall be scalped to a maximum of 4 in. Scalping shall include the removal of material such as brush, roots, sod, grass, residue of agricultural crops, sawdust, and decayed vegetable matter from the surface of the ground. 60

201.05Hedge Removal

Hedges and shrubs shall be pulled or grubbed in such a manner as to ensure complete and permanent removal.

201.06Method of Measurement

When specified as a pay item, measurement of this work will be made by one or more of the following methods.

(a)Area Basis 70

The work to be measured will be the number of acres and fractions thereof acceptably cleared and grubbed within the limits shown on the plans or staked for clearing and grubbing. Areas not shown on the plans or not staked for clearing and grubbing will not be measured for payment.

(b)Lump Sum Basis

If clearing and grubbing is specified as a lump sum pay item, no measurement of area will be made.

(c)Individual Unit Basis 80
1.The diameter of trees will be measured at a height of 24 in.

above the ground. Trees of less than 4 in. in diameter will be classified as brush.

2.Stumps will be measured by determining the average diameter

at the cutoff location.

3.Scalping will be measured by the acre.

201.04

4.If the Schedule of Pay Items shows measurement to be on an

individual unit basis, the units will be designated and measured in accordance with the schedule of sizes as follows: Measured Diameter at Height of 24 in. Pay Diameter 4 to 8 in. 6 in. Over 8 to 12 in. 10 in. Over 12 to 24 in. 18 in. Over 24 to 36 in. 30 in. Over 36 to 60 in. 48 in. Over 60 in. 60 in.

201.07Basis of Payment

The accepted quantities of clearing and grubbing will be paid for as specified and described below.

Payment will be made under: 100

Pay Item Pay Unit Symbol

Clearing and Grubbing .............................................................. ACRE L S Clearing Right-of-Way .............................................................. LS Scalping ..................................................................................... ACRE ________, ________, Remove .................................................. EACH name size

(a)Area Basis

The determined quantities will be paid for at the contract unit price per acre respectively for each of the pay items shown in the Schedule of Pay Items.

(b)Lump Sum Basis

If the Schedule of Pay Items shows a lump sum pay item, the lump sum price will be paid for all work shown within the construction limits. All clearing the Contractor is directed to perform outside the construction limits, including clearing for utility relocation which is for the benefit of the Department, and not simply for the Contractor’s convenience, will be paid for in accordance with 104.03 or 109.03 unless 120 such clearing is shown on the plans, in the Contract Information book, or is for the construction of fence or right-of-way markers.

(c)Individual Unit Basis

If individual unit quantities are shown in the Schedule of Pay Items, the accepted quantities will be paid for at the contract unit prices for the respective pay items. 201.07

Payment for tree removal sizes as designated in requirement 4 of 201.06(c), which are larger than those sizes shown as pay items, will be made on the basis of the largest size shown in the Schedule of Pay Items except as set out below. 130

(d)Clearing Right-of-Way

If the Schedule of Pay Items contains a lump sum pay item for clearing right-of- way, such pay item shall include the cost of all work described in this section and all of the work performed in accordance with 202 within the construction limits except for such work set out specifically as pay items or as otherwise provided for herein. All clearing the Contractor is directed to perform outside the construction limits, including clearing for utility relocation which is for the benefit of the Department, and not simply for the Contractor’s convenience, will be paid for in accordance with 104.03 or 109.03 unless such clearing is shown on the plans, in the Contract Information book, or is for 140 the construction of fence or right-of-way markers.

Except as specified in 621, the cost of re pair or replacement of terrain, vegetation, objects designated to remain, or areas outside the construction limits which have been damaged by the Contractor or have subsequently eroded, shall be included in the cost of clearing right-of-way.

( e ) E x c l u s i o n s If the Schedule of Pay Items does not co ntain an estimated quantity or a lump sum pay item for work described herein except as set out above, such work will not be paid 150 for directly. The cost thereof shall be included in the cost of other pay items.

Get an email when 201 changes

Indiana revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Indiana Standard Specifications, 2024 Edition. Pages 147–0 of 1,248. View official source ↗

Ask about this section