203.01Description
This work shall consist of embankment construction and excavation, hauling, and disposal or compaction of all material not being removed under some other item which is encountered within the limits of the work and also from intersecting entrance approaches beyond the right-of-way limits necessary for the construction of the roadway in accordance with 105.03. All excavation will be classified as hereinafter described.
203.02Common Excavation
Common excavation shall consist of all excavation not included as rock excavation or excavation which is otherwise classified and paid for, including asphalt type pavement. Coal ash encountered within the project limits shall be used in embankments under the same conditions as borrow in accordance with 203.08.2. If coal ash is encountered within the project limits, appropriate measures as described in
203.23.1 shall be used to prevent movement of coal ash from the project
203.03Rock Excavation
Rock excavation shall consist of igneous, metamorphic, and sedimentary rock or 20 other sound mineral matter which cannot be readily excavated by the use of a crawler mounted hydraulic excavator of not less than 40,000 lb gross operating weight equipped with a general purpose excavator bucket of not less than 1 cu yd capacity, in satisfactory running condition and operated in accordance with the manufacturers recommended operating instructions. Rock ex cavation shall also include all boulders and other detached stones each having a volume of 1/2 cu yd or more.
203.04Unclassified Excavation
Unclassified excavation shall consist of the excavation and disposal of all materials of whatever character encountered in the work. 30
203.05Peat Excavation
Peat excavation shall consist of the neces sary excavation and satisfactory disposal of peat, muck, marl, or any other similar unsuitable material in peat deposits, together with any overlaying material, except pavement, which is not used in embankment construction, except as otherwise provided in 203.16.
203.06Waterway Excavation
Waterway excavation shall consist of the necessary excavation and satisfactory disposal of all material resulting from excavation for clearing waterways, making 40 channel changes, or both when such are itemized in the Proposal book, but shall not include class Y excavation, or excavation made for a structure in accordance with 206. If not otherwise specified, waterways shall be cleared for the entire distance within the right-of-way lines.
203.01
203.07Class Y Excavation
Class Y excavation shall consist of material encountered within the limits of waterway excavation which can be classified as rock in accordance with 203.03, or material which consists of conglomerate, concrete, masonry, or any similar material which is not part of an existing structure shown on the plans. Material as defined in 50
will not be considered as class Y excavation
203.08Borrow or Disposal
Borrow shall consist of approved material required for the construction of embankments or for other portions of the work and shall be obtained from accepted locations and sources outside the right-of-way. Borrow material shall be free of substances that will form deleterious deposits, or produce toxic concentrations or combinations that may be harmful to human, animal, plant or aquatic life, or otherwise impair the designated uses of a stream or area. Unless otherwise designated in the contract, arrangements shall be made for obtaining borrow. Borrow, as designated 60 herein, shall not include material excavated beyond the right-of-way limits at intersecting public roads, private and commercial drive approaches and material furnished as B borrow.
Disposal of material, other than regulated material and bridge painting debris, from within the right-of-way shall only be allowed at accepted locations. Disposal of regulated material shall be in accordance w ith 104.06. Disposal of bridge painting debris shall be in accordance with 619.
Proposed borrow and disposal sites shall be accepted by the Engineer prior to the 70 start of any borrow or disposal operations at the site. For each proposed site, an IC- Request for Acceptance of Borrow or Disposal Site form, available on the Department's website, shall be submitted to the Engineer a minimum of 14 days prior to the Contractor’s planned start of operations at the site. All requests for acceptance of a borrow or disposal site shall be in accordance with 203.08(a).
Acceptance of any proposed borrow or disposal site by the Engineer shall not relieve the Contractor of the responsibility to utilize an appropriate site and to comply with all applicable local, State and Federal laws and regulations.
The Contractor shall provide the Engineer a minimum of 14 days notice prior to opening borrow areas in order to obtain original cross-sections, measurements, and borrow material samples prior to borrow area use.
No extension of completion time will be granted due to any delays by the Contractor in securing acceptance of borrow and disposal sites.
Any proposed borrow or disposal site submitted for acceptance shall be presented as, and meet the requirements of one of the following site definitions. 90
203.08
A Solid Waste Site shall be defined as a solid waste facility, in accordance with 329 IAC 10-2-176, with a current IDEM operating number.
A request for acceptance of a Solid Waste Site shall include the following:
An Established Site shall be defined as an established location, other than as defined in 203.08(a)1, proposed for borrow or disposal activity that is disturbed or developed for public, municipal, governmental, commercial, industrial, construction or any other similar or related activity. The Established Site shall be operating under permits required by local, State and Federal laws for the activities proposed by the Contractor.
A request for acceptance of an Established Site shall include the following:
Rights-of-entry shall incl ude rights for access by Department personnel to the site.
disposal areas delineated.
for the delineated borrow or disposal area.
expiration dates for all permits under which the site operates.
archeological field survey, w ith record check, have been performed by qualified profes sionals shall be provided when borrow or disposal activities are identified for areas of the proposed site that remain undeveloped or undisturbed.
Any required wetlands delineation and archeological field surveys, with record check, shall be limited to those 203.08
undeveloped and undisturbed areas identified for borrow or disposal that are greater than 0.1 acres.
A General Site shall be defined as a location, other than as defined in 203.08(a)1 and 203.08(a)2, that has not been distur bed or developed for public, municipal, governmental, commercial, industrial, construction, or other similar or related activity. A General Site shall include private, residential, agricultural fields and pastures, or any other similar or related locations. General Sites shall require additional documentation for acceptance.
A request for acceptance of a Genera l Site shall include the following:
Rights-of-entry shall incl ude rights for access by Department personnel to the site.
right-of-way lines, all demarcated jurisdictional wetlands or 160 isolated wetlands, all demarcated archeological sites, existing and proposed finished contours and proposed finished slope grades.
the site, what equipment will be utilized, how the site will be accessed and any other information relevant to the operation of the site.
for the site.
stormwater features to be incorporated and the sequencing of the measures with respect to the operations plan for the site.
that the site has been insp ected for the presence of both wetlands and isolated wetlands and, if any are present, 180 specifying the area to be demarcated as jurisdictional or isolated wetlands.
203.08
record check, signed by a qualified archeologist including the limits and border of any archeological site discovered.
perform operations at the site.
certification from the property owner, that the proposed site is not currently an active remediation or corrective action site operating under an IDEM or EPA cleanup program, and that there are no environm ental liens, easements, deed restrictions, or environmental restrictive covenants against the proposed site location. If environmental liens, easements, deed restrictions, or environmental restrictive covenants exist for the proposed site location, the Contractor shall provide copies of the restriction and written 200 approval from the regulatory agencies having an interest in, or jurisdiction over the proposed site approving use of the site for the borrow or disposal operations.
When a General Site is identified for borrow or disposal, the Contractor shall obtain all permits required by local, State and Federal laws prior to the start of any operations at the site.
All proposed General Sites shall have an inspection of areas impacted by the borrow or disposal operations conducted by a qualified wetland professional to 210 determine if wetlands are present on the site. An Approved List of Wetland Delineators for INDOT Project Contractors is maintained on the Department's website. The wetlands inspection shall be in accordance with the Federal Manual for Identifying and Delineating Jurisdictional Wetlands. The inspection shall also determine if isolated wetlands as defined by IDEM are present. The Contractor shall demarcate the boundary of all wetlands identified within the proposed borrow or disposal site in a method acceptable to the Engineer.
Proposed General Sites shall have a qualified archeologist perform a field survey, with record check, to determine if any significant archeological sites exist within the 220 proposed site. The Indiana Department of Natural Resources Division of Historic Preservation and Archeology maintains a roster of qualified archeological consultants. If any archeological sites are identified, the archeologist shall establish the limits of the site along with a reasonable border. The Contractor shall demarcate the border of all identified archeological sites within the proposed borrow or disposal site in a method acceptable to the Engineer.
Identified archeological sites shall not be disturbed unless the site is cleared by
203.08
157
established procedures and written authorization to enter the site has been obtained230
from the Department’s Cultural Resources office. Archeological artifacts encountered
during operations shall be addressed in accordance with 107.10.
The Contractor shall install all temporary stormwater management control
measures at accepted borrow and disposal locations designated as Established Sites
and General Sites prior to the start of any earth disturbing activity. The Contractor
shall develop and construct all mitigation measures necessary to fulfill the
requirements of all permits obtained by the Contractor for operation of a borrow and
disposal site.
240
No excavation shall occur or no material shall be disposed of within the
boundaries of the demarcated wetlands and archeological areas unless the operations
are in compliance with all required permits and these specifications.
No extension of completion time will be granted due to any delays by the
Contractor in securing approval of borrow and disposal sites.
Unless written permission is granted, there shall be no excavation in a borrow area
below the elevation of the adjacent properties within 150 ft of the nearest right-of-way
line of an existing highway, county road, or city street; the nearest right-of-way line250
of a proposed highway, county road, or city street; or adjacent property lines. If the
properties adjacent to the borrow area are privately owned, the setback limit of 150 ft
may be lessened if written approval or permission is granted by the owner of the
adjacent property, the excavation is in accordance with local zoning laws and
requirements, and if lessening the limit is in the best interest of the State. Such
minimum distance shall not be closer than 50 ft to an adjacent property line. All
excavated slopes of a borrow area shall not be steeper than 3:1 down to 2 ft below the
groundwater elevation. All excavated slopes 2 ft below the groundwater elevation shall
not be steeper than 2:1.
260
Top soil from the borrow or disposal area shall be stockpiled for use in restoring
the disturbed area. A minimum encasement of 6 in. shall be placed on the 3:1 or flatter
slopes. Final restoration of borrow or waste disposal areas shall include grading,
seeding, or other necessary treatments that will blend the area into the surrounding
landscape. Restored areas within 150 ft of the nearest right-of-way line shall be well
drained. Areas beyond 150 ft shall be drained unless the landowner desires other
treatment of the borrow area. Construction of borrow or disposal areas shall be in
accordance with existing laws, regulations, and ordinances. Under no conditions shall
borrow sites detract from the appearance of the natural topographical features or
increase the potential hazard to a vehicle that has inadvertently left the highway.270
If granulated slag, dunes sand, or other granular material which is not suitable for
the growth of vegetation is used, such material shall not be placed within 1 ft of the
required finished surfaces of shoulders and fill slopes. Additional material required to
complete the embankment, such as sandy loam, sandy clay loam, clay loam, clay, or
203.08
158
other materials suitable for the growth of vegetation and free from clods, debris, and
stones, shall be furnished at the contract price for borrow.
Additional fill material may be secured from within the permanent or temporary
right-of-way in lieu of borrow or B borrow either from vertical or horizontal280
extensions, or both, beyond the lines and elevations of roadway and drainage
excavation as shown on the contract plans when authorized in writing. If additional
material has been obtained without written approval, the material will be classified
either as to source or use, to the best advantage of the Department.
.1 Linear Grading
Linear grading shall consist of:
has been resurfaced, widened, or replaced;290
for the posts;
median barrier.
These types of earthwork will not require benching.
.2 Coal Ash300
Borrow may also consist of coal ash.
Coal ash is defined as either fly ash, bottom ash, or a mixture of both. Fly ash is
further defined as coal ash with 70% or less passing the No. 200 (75 μm) sieve. Bottom
ash is further defined as coal ash with 20% or less passing the No. 200 (75 μm) sieve
and 10% or less retained on the No. 10 (2.0 mm) sieve.
Boron levels in coal ash shall be less than 5 ppm as determined using the Indiana
Neutral Leachate Testing, INLT, methodology.
310
The Contractor shall provide a copy of an IDEM waste classification certification
for Type III or Type IV material prior to use. The IDEM certification shall identify the
size and geographical location of the coal ash stockpile.
A Type A certification in accordance with 916 shall be provided for coal ash. The
results of the following shall be shown on the certification.
159
historical testing results.
Property Test Method
Gradation AASHTO T 88
Atterberg limits AASHTO T 89 and T 90
Standard Proctor AASHTO T 99
Level of boron INLT
All tests shall be performed by a laboratory from the Department’s list of
Qualified Geotechnical Consultants. Tests shall be submitted to the Engineer and to
the Department’s Geotechnical Engineering Division for approval at least five
business days prior to use.
330
If coal ash is obtained from a commercial source, such as a power plant, the
Contractor shall also provide a letter from the source allowing access by Department
personnel for the purpose of inspecting the processes used to produce the coal ash
stockpile and for sampling the stockpile for testing by the Department.
CONSTRUCTION REQUIREMENTS
203.09General Requirements
The excavation and embankments for the roadway, intersections, and entrances
shall be finished to reasonably smooth and uniform surfaces. Excavated materials shall340
not be wasted without permission. Excavation operations shall be conducted so that
material outside the limits of slopes will not be disturbed. Prior to beginning
excavation, grading, or embankment operations in any area, all necessary clearing and
grubbing in that area shall have been performed in accordance with 201.
The Contractor shall stabilize an area if disturbed ground is anticipated to be left
bare and unworked for seven consecutive calendar days or if directed. The stormwater
management control features shall be installed in accordance with 205 or as otherwise
directed. The area of the exposed materials shall be limited by the Contractor’s
capacity to adequately maintain permanent and temporary stormwater management350
control features.
Soils containing organic material greater than 6% by dry weight, or soils with a
maximum dry density of less than 90 pcf shall not be incorporated in the embankment.
Organic content will be determined in accordance with AASHTO T 267, and
maximum dry density will be determined in accordance with AASHTO T 99.
Frozen materials, stumps, roots, all or parts of trees, brush, weeds, sod, or other
perishable materials shall not be incorporated in the embankment. Rocks greater than
3 in. in any dimension shall not be left within 18 in. of the finished subgrade. The360
203.09
160
original ground surface, or the surface of any lift in place shall not be frozen and shall
be free of snow, ice, or mud.
All vegetation, all spongy, yielding, soft, and unstable materials, which are
encountered, shall be removed as shown on the plans or as directed. Removed
materials may only be used in embankment construction if they are constructed in
accordance with 203.23.
After clearing of the embankment area and prior to embankment placement, all
pronounced depressions left in the original ground shall be filled with suitable material370
and compacted in accordance with 203. Proofrolling of the natural ground surface shall
be performed in accordance with 203.26 within all areas where new fill shall be placed.
If the original ground cannot be compacted to the required strength because of
soft or unstable soils, the use of stabilizing materials consisting of coarse aggregate
No. 5 encapsulated in geotextile, in accordance with 214.03(a), or soil drying with a
chemical modifier in accordance with 217 shall be used as directed. The coarse
aggregate materials used for stabilization shall be 1 to 2 ft thick and shall allow the
encapsulated material in the embankment to drain.
380
When free water is encountered, backfilling shall be accomplished using B
borrow, in accordance with 904.06 with the exception that ACBF or GBF shall not be
used. Backfilling using B borrow shall occur to an elevation at least 2 ft above the free
water level. Compaction of the B borrow placed above the free water level shall be
accomplished using heavy vibratory equipment.
The use of hydraulic methods to construct embankments will be allowed only
when authorized in writing. Only B borrow without ACBF or GBF shall be placed
below the free water level. Backfill at structures shall be in accordance with 211.04.
390
The embankment shall be kept drained at all times by keeping the center higher
than the sides and uniformly graded.
Each embankment lift shall extend transversely over the entire area and shall be
kept smooth. When fill materials are deposited in large masses onto the embankment,
the materials shall be spread out in uniform lifts. Rock or shale used for embankment
construction shall be in accordance with 203.20.
When grading operations are performed in non-daylight hours, artificial lighting
shall be provided and maintained, to enable the construction and inspection of the400
operations.
When the embankment soils are granular, silty loam, sandy loam, silts, or when
the plasticity index of the material is less than 8, the embankment shall be encased
with materials consisting of silty clay loam, clay loam, sandy clay loam, or silty clay
of 12 in. minimum depth measured perpendicular to the face of the slope. The
203.09
161
plasticity index for these materials shall be equal to or greater than 8 and the organic
content shall not exceed 6%. The surface of any necessary encasement shall meet the
finished slope limits shown on the plans or as directed.
410
All slopes to be graded and not immediately stabilized with stormwater
management control measures shall be roughened, as described herein, until
stormwater management control measures are placed. The soil slopes shall be
roughened to create a series of ridges and depressions parallel to the contour by making
grooves at least 1 in. deep and not more than 15 in. apart. Slopes shall be stabilized in
accordance with 205. Roughening shall take place each day after work is performed
on the slopes, or as directed to re-establish the roughening.
Sufficient quantities of excavated materials suitable for the growth of vegetation
shall be preserved from within the planned excavation area and used on constructed420
cut, fill, and shoulder slopes to help develop the growth of vegetation. Materials
suitable for vegetative growth shall be at least 6 in. deep or as indicated within the
contract documents and shall be measured perpendicular to the face of the slope.
Unless otherwise provided, no additional compensation will be allowed for this work
except payment will be made for the class of excavation involved for authorized
undercutting of back slopes. Encasement of rock embankment and cut slopes will not
be required unless otherwise directed.
Material suitable for the growth of vegetation shall be in accordance with 914.01
prior to placement. The material placed on backslopes of cut sections shall be placed430
in accordance with 203.21.
If sufficient excavation materials suitable for the growth of vegetation and used
on constructed cut, fill, and shoulder slopes are not available, borrow or other material
suitable for vegetative growth shall be furnished. The sources of all borrow material
shall be in accordance with 203.08 and 914.01. Payment for borrow will be made in
accordance with 203.28. If the contract does not contain a pay item for borrow, a
change order will be executed for payment of borrow. Suitable portions of common
excavation may be preserved or borrow material may be furnished for encasement
provided all suitable excavation is used constructively.440
203.10Disposal of Excavated Material except Waterway and Peat
Excavation
Excavation material shall be used for the construction of embankments, shoulders,
special fill, or other places as may be specified or directed, depending on the nature of
the material. Excavated material that is suitable for embankment construction, that is
not required for maintenance of traffic, shall be placed in the embankment before
placing any borrow material, unless otherwise authorized in writing.
If more material is excavated from within required cut slopelines than is needed450
to construct embankments or special fills, the excess may be used to widen
embankments, flatten fill slopes, or be used otherwise as directed. All excess
203.10
162
excavated material that cannot be used constructively within the project limits shall be
disposed of off the right-of-way in accordance with 203.08.
Excavation obtained from the right-of-way and planned to be used in fills may be
wasted and replaced with borrow with no additional payment only after written
permission is obtained. All required samples of the borrow or the excavation materials
involved shall be furnished with no additional payment.
460
203.11Disposal of Waterway Excavation
Unless otherwise provided, material resulting from waterway excavation shall be
used, if suitable, in embankment, special fill, approach embankments, or any
combination of these, as specified or directed.
Any portion of waterway excavation material which is unsuitable for the above
uses, any portion which is suitable but is in excess of that required for such uses, or
when locations for such uses are not available, the material shall be disposed of in
accordance with 203.08.
470
203.12Disposal of Peat
All material removed as peat excavation, removed or displaced by machine
operation, or displaced by the advancing backfilling material shall be disposed of in
accordance with 203.08.
203.13Slides
When slides are encountered during construction, or when water is observed
seeping out of the slope or slope sloughing occurs, the Engineer shall be notified. The
Engineer will contact the Department’s Geotechnical Engineering Division. The
Department will provide the remedial measures to address the slope issues. Soil480
disturbed due to a slide shall be treated as directed. Excavation of material resulting
from a slide or sloughing event will be paid for as the class or classes of excavation
encountered.
If the contract involves paving, the omission or delay of paving operations may
be required at the location of a slide. If proper treatment of a slide has been completed
prior to constructing the remaining pavement, the slide section may be paved, and
payment will be at the contract unit price for pavement.
If the treatment of a slide has not been addressed prior to completion of the490
remaining pavement, the slide section shall become an exception to the contract item
for pavement.
203.14Drainage
Ditches shall be interpreted to mean open ditches and channel changes parallel to
and adjacent to the roadbed. Channel changes excavated under the classification of
waterway excavation are not included in this definition.
203.11
163
Lines, grades, and cross-sections of ditches shall be as shown on the plans, unless
otherwise established to obtain proper drainage.500
Ditches and gutters emptying from cuts onto embankment shall be constructed to
avoid eroding the embankment.
Exploration of underground drainage and sinkholes may be required, and payment
will be hereinafter provided. Should any underground drain be encountered, the
location of which is not shown on the plans, notification shall be made at once.
Drainage shall be explored as directed and, if deemed necessary, taken care of under
applicable provisions of these specifications, or as otherwise directed.
510
If existing surface drains, tile drains, sewers, or other underground drains, or parts
thereof, are not to be replaced or are not required by the terms of the contract or
directed to be changed, whether such drainage facilities are shown on the plans or not,
all such drainage facilities or parts thereof shall be protected, preserved, and
satisfactorily continued in use without change. If in the prosecution of the work such
existing drainage is changed or interrupted, or through negligence such drainage is
interrupted or damaged, satisfactory permanent repairs shall be immediately provided
or adequate temporary drainage facilities shall be maintained until permanent repairs
are made. If temporary facilities are provided, before the work is accepted, such
damage or interrupted drainage facilities shall be restored to the original condition or520
to an altered state which is at least equal to their original condition.
If slopes or ditches which were graded for a grading contract become eroded or
scoured during the paving contract work, the scoured or eroded areas shall be reshaped
to the original cross-section and reseeded or resodded as shown on the plans, all in
accordance with 208 and 621.
When so provided by the plans or special provisions, or when ordered, all tile
drains, sewers, or other underground drains encountered in the prosecution of the
contract shall be repaired, replaced, extended, reconstructed, connected, or otherwise530
changed.
Unless otherwise provided in the contract, the cost of replacing, restoring, or
connecting an underground drain which is substantially in its original location and
incidental to roadway and drainage excavation, structures, or other drains will not be
paid for directly, but the cost thereof shall be included in the cost of various pay items.
Unless otherwise provided, any necessary drainage change or restoration not
shown on the plans and not due to negligence or operations of the Contractor will be
paid for at the contract unit price or prices thereof. If there is no such contract unit540
price or prices, such work shall be done and payment made in accordance with 104.03.
203.14
164
203.15Excavating Rock
If material is encountered during excavation which appears to belong in the
classification of rock excavation in accordance with 203.03, notification shall be made
in writing. Ample time shall be allowed to make such investigation and measurements
that are necessary to determine the class and volume of the material in question.
Exploratory cores shall be taken from the top of the rock to approximately
subgrade elevation as directed. The cores shall be cut with standard diamond core bits550
and series X double tube core barrels to obtain 2 1/8 in. diameter samples. All cores
shall be suitably marked and identified to show the location of the core by station,
offset from centerline, elevation of top of rock, depth below top of rock, and percent
recovery within each core. All cores shall be retained. The cores shall be placed in
suitable compartmented wooden boxes in the order in which removed from the boring,
with dividers between core runs. The top and bottom of each run shall be appropriately
marked. The cores shall be transported to a location as directed.
The top of rock elevations shall be determined prior to locating the top of soil cut
slopes where finished rock slopes are planned to be 1:1 or steeper.560
Final breakage of rock excavation shall be in accordance with, or closely to, the
slope lines as shown on the plans unless different slope lines are fixed, and the
Contractor so notified. The final slopes shall be left reasonably smooth and uniform,
and all loose and overhanging rock removed. Unless otherwise specified, no rock shall
finally project more than 1 ft beyond established slopes. If natural seams intersect an
established slope, the excavation may be carried, with permission, along the face of
such seams for the distance approved.
Rock shall be excavated to the required elevation for the full width of the roadbed570
as shown on the plans or as directed. Where rock is excavated below the required
elevation, the area shall be backfilled to the subgrade elevation with crushed stone,
spalls, subbase material, or other approved granular material, which shall be shaped
and compacted to the required elevation and cross-section.
Exploratory drilling, which shall consist of drilling holes for the purpose of
determining the existence of cavities affecting underground drainage and possible
sinkholes in cut sections, may be required at locations as directed. Unless otherwise
directed, the holes shall be drilled on the centerline of the proposed pavement at
approximately 100 ft intervals and shall extend for a depth of 7 ft below the proposed580
grade and have a minimum diameter of 1 1/2 in.
Where cavities are discovered on centerline, additional holes shall be drilled at
25 ft intervals along the edge of the proposed pavement, and unless otherwise directed,
extend for a depth of 7 ft below the proposed grade. Where any cavity is discovered
or exposed having a minimum cover of less than 5 ft, the cover shall be removed, and
the treatment of such areas shall be in accordance with details in the plans or as
otherwise directed.
203.15
165
The final surface of rock excavation under the roadbed area shall be left so that590
drainage between the rock surfaces and any material placed thereon will be
substantially complete. Where seams of clay or other soft material 1 ft or less in
thickness are encountered in rock excavation, the volume of such seams will be
considered as rock excavation and paid for as such.
Unless otherwise specified or directed, rock shall be pre-split by drilling and the
use of explosives in such a manner as results in minimum breakage outside neat lines
of the typical cross-section and slope stakes as established. Deposits of commercial
building stone outside the right-of-way shall not be damaged. Holes for pre-splitting
shall be drilled along the established slope stake lines. The holes shall be from 2 to600
4 in. in diameter and, unless otherwise directed, be spaced approximately 3 ft apart.
Holes shall be drilled approximately 2 ft below the established grade of the cut, or the
predetermined bench elevation, or as directed.
The maximum depth of any pre-split lift shall be 30 ft, unless otherwise directed.
If more than one lift is required, the first line of drill holes shall be set in such a manner
as to allow for a specified offset for each succeeding lift and an offset of 2 ft from the
back of the paved side ditch line. The explosives used and the method of loading
depends on the material to be blasted. These explosives may vary from a single strand
of detonating cord, for blasting unconsolidated formations, to a solid column of610
dynamite for massive formations. However, the explosive shall be of a type to
accomplish the pre-splitting with a minimum of breakage outside the excavated area.
After the charges are placed, the holes shall be filled with sand or other suitable
granular material.
Except as indicated below, all pre-splitting charges shall be detonated
simultaneously by the use of instantaneous electric blasting caps or by means of a
detonating cord trunkline. The line holes shall be fired before the main excavation is
blasted. Pre-splitting shall be kept well in advance of regular blasting operations.
Primary blasting holes shall be drilled no less than 6 ft from the pre-split face, unless620
otherwise directed. If additional charges are required, holes shall be placed at 1/2 the
distance of a full depth hole to a depth such that the bottom of the hole clears the pre-
split face approximately 2 ft. The pre-split face shall deviate no more than 6 in. from
the front line of drill holes or more than 12 in. from the back line of drill holes, except
where the character of the rock will unavoidably result in some irregularities.
The amount of explosives per shot for instantaneous firing or the amount of
explosives per delay for delay firing shall not be great enough to damage nearby
structures, rock formations, or other property. Where commercial building stone
formations are located in the effective vicinity, adequate seismograph readings shall630
be obtained, with no additional payment, as evidence that blasting operations have not
altered existing commercial building stone formations outside the right-of-way limits
of the project.
203.15
166
Permission may be granted to use machine methods to establish the finished
slopes in those cuts where machine methods are used to remove roadway excavation,
provided final machine finished slopes are equal or superior to that which would be
obtained by pre-splitting methods.
When or where any direct or indirect damage or injury is done to public or private640
property by or on account of any act, omission, neglect, or misconduct in the execution
of the work or in consequence of the non-execution thereof, such property shall be
restored, with no additional payment, to a condition similar or equal to that existing
before such damage or injury was done by repairing, rebuilding, or otherwise restoring
as directed, or such damage or injury shall be made good in an acceptable manner.
No direct payment will be made for pre-splitting, but the cost thereof shall be
included in the pay item of rock excavation or unclassified excavation.
203.16Peat Deposit Treatment650
If construction is specified at a location where a peat deposit is to be treated, the
deposit shall be treated ahead of paving operations to obtain maximum settlement. If
settlement has not been obtained when paving operations are at the limits of any peat
deposit treatment, a gap in the pavement shall be left as directed. Gaps not constructed
as part of the project will become an exception to the contract.
Treatment shall be by the following methods:
If the required alignment is on an existing fill over a peat deposit, treatment may660
be required by any one or any combination of the following methods:
underlying peat and of the material at the sides of the existing
fill;
directed, blasting the peat underneath;670
sides either by removing the peat at the sides and backfilling or
by displacement or both;
Determination of the method or methods to be used will be made based on
conclusions from test holes which may be required to be drilled at designated
locations.680
203.16
167
This method consists of completely removing the objectionable material either as
peat excavation or by machine operation and backfilling to the full toe-width of the
proposed embankment or to such other widths, if so directed depending on the
condition and depth of the material to be removed.
If water is not present, the space previously occupied by the removed material
shall be backfilled with common excavation, borrow, or both, and placed in
accordance with 203.690
If water is present, the backfill shall be with material in accordance with 211.02
with the exception that ACBF or GBF shall not be used. Placement of this material
shall follow as closely behind the removal of the peat as possible. It shall be carried
across the area from one end to the other by end-dumping and finally left at the
established grade. This grade shall be such that keeps end-dumping to a minimum,
which nominally shall be approximately 2 ft above free water level. That portion
between free water level and this established grade shall be thoroughly water soaked
to secure maximum compaction.
700
If additional fill is needed to bring the embankment to its final required grade, it
may be common excavation or borrow. Further placing of the granular material above
the end-dumped material may be authorized. This additional fill shall be placed and
compacted in accordance with 203 but shall not be placed for at least 14 days after the
end-dumped material is placed and compacted. This period may be shortened or
lengthened with written approval, depending on the settlement that has been obtained.
When this method is used, the peat at each end of the deposit shall be removed
completely by excavation to the full width shown on the plans, or to such other width710
as may be directed, until a point is reached where the depth of the peat being removed
is greater than 10 ft, or to a greater or lesser depth, as directed.
If conditions allow, the upper portions of the remaining peat shall be excavated
across the remainder of the deposit in the same manner as set out above for the ends.
Removal of this upper portion shall begin at one end and proceed to the other end at a
sufficient distance ahead of backfilling operations so displacement of the remaining
peat will not be retarded. If excavation to the required depth is not maintained for the
full width ahead of the backfill or surcharge, additional units shall be used or backfill
operations stopped until the two operations are in balance. If conditions allow,720
draglines shall be operated from mats in front of the advancing excavation. If blasting
is required to aid displacement, it shall be completed as extra work in accordance with
104.03
Backfilling shall be in accordance with 203.16(b) for end-dumped material
except, when required, a temporary surcharge shall be maintained at the head of the
backfilling. The top of the surcharge shall be constructed and maintained to a width
203.16
168
equal to the full shoulder width of the proposed embankment, or as approved or
directed. The height of the surcharge shall be the same as the depth of the peat being
treated, unless otherwise directed. The original ground shall be the reference elevation730
for measuring peat depths and surcharge heights. The top of the surcharge shall be
approximately level and the length on top shall be at least two times the depth of the
peat being treated. The surcharge shall be kept built up and pushed forward with a
bulldozer or other approved equipment as the displacement progresses. Machine
methods shall be used to relieve pressure at the advancing toe and sides of the
surcharge. Sufficient hauling units shall be used to maintain the surcharge at the
required height, width, and length. The machine operation to augment displacement
shall be coordinated with the rate of placing temporary surcharge.
After the granular backfill has been completed across the deposit, any remaining740
fill necessary to bring the embankment up to the required final grade shall be in
accordance with 203.16(b) for that portion above the end-dumped material.
203.17Cased Test Holes
As displacement progresses, cased test holes shall be placed at locations as
directed to determine the extent of peat displacement and for use in conjunction with
final measurement. These holes shall extend to the bottom of the deposit. The boring
shall be conducted in such a manner that accurate information may be obtained as to
the nature of the materials through which the test holes are placed. If these test holes
indicate that full displacement has not been obtained, the remaining peat shall be750
blasted or additional treatment shall be performed as required.
Unless otherwise specified in writing, cased test holes shall be placed by hydraulic
boring. The external casing shall be a minimum of 2 in. in diameter and of such
additional size as to perform the operation satisfactorily. A continuous supply of fresh
water shall be jetted through an internal pipe so that the wash water and loosened
material is carried to the surface between the jet rod and the external casing. Pumps
and other miscellaneous tools and equipment shall be used as required to perform a
satisfactory operation.
760
203.18Embankment Construction
Embankment construction shall consist of constructing roadway embankments,
including preparation of the areas upon which they are to be placed; the construction
of dikes within or outside the right-of-way; the placing and compacting of approved
material within roadway areas where unsuitable material has been removed; and the
placing and compacting of embankment material in holes, pits, and other depressions
within the roadway area. Only approved materials shall be used in the construction of
embankment backfill. Recycled concrete pavement shall be from past documented
Department projects. RAP shall be the product resulting from the cold milling or
crushing of an existing HMA pavement. Rocks, broken concrete, RAP, or other solid770
materials shall not be placed in embankment areas where piling is to be placed or
driven.
203.17
169
Recycled concrete pavement shall meet the gradation requirements of B borrow
in accordance with 904.06. Construction requirements shall be in accordance with
203.20(a) or 211.03
Only RAP particles measuring 2 in. or less in all directions shall be incorporated
into the top 5 ft of the embankment. RAP particles incorporated anywhere in the
embankment shall be 5 in. or less.780
When two sizes are used for one embankment, materials shall be separated with
a layer of geotextile in accordance with 918.02(c), Type 2A. Geotextile used between
recycled material lifts shall be included in the cost of the embankment pay item.
Recycled concrete pavement and RAP shall not be mixed together or with other
materials. When two or more approved materials are allowed for one embankment,
materials shall be separated with a layer of geotextile in accordance with 918.02(c),
Type 2A. Geotextile used between recycled material lifts shall be included in the cost
of the embankment pay item.790
Recycled concrete pavement or RAP shall only be used below the elevation of the
pavement underdrains. Compacted lift thickness for RAP shall not be greater than 6
in. within the top 5 ft of the embankment. Where the depth of the embankment exceeds
5 ft, the compacted lift thickness for RAP shall not be greater than 12 in. Recycled
concrete pavement and RAP shall not be used within 2 ft of the water table.
Recycled concrete pavement shall be constructed in accordance with 203.20. RAP
shall be constructed in accordance with 203.23 or 203.24. Proofrolling in accordance
with 203.26 shall be performed to cover the entire grade for every 5 ft of fill.800
A geotextile in accordance with 918.02(c), Type 2B shall be placed in accordance
with 214 prior to the placement of subgrade treatment Type IC, Type II, or Type IV in
accordance with 207 when recycled concrete pavement or RAP is used for
embankment construction. Recycled concrete pavement or RAP shall not be used for
embankment construction when subgrade Type I, Type IBC, or Type IBL is specified.
Geotextile shall be placed completely covering the top of the embankment. A
minimum 24 in. soil encasement shall be constructed concurrently with the recycled
concrete pavement or RAP lift. The soil encasement shall be suitable for vegetation
growth and shall be constructed in accordance with 203.09.810
203.19Embankment Over and Around Structures
Fill shall not be placed against any new masonry abutment, wingwall, retaining
wall, or culvert, or over any culvert, bridge, or arch until approved. Applicable
provisions of 702.23 shall be met.
Filling around culverts, bents, and piers, and fill below the natural ground surface
at abutments, wings, and retaining walls shall be deposited on both sides to
approximately the same elevation at the same time. Piers or bents shall not be displaced
203.19
170
and shall be checked for proper location as the work progresses. Corrective measures820
shall be made if necessary. Filling at arch structures shall be carried up in horizontal
layers, symmetrically from haunch to crown, and simultaneously over and against all
piers, abutments, and arch rings.
Wedging action of filling material against structures shall be prevented. If
directed, back slopes of excavation shall be destroyed by stepping or serrating.
The embankments around the end bents shall be constructed to approximate
subgrade elevation for a distance of no less than 75 ft. This work shall be done before
piling in the end bents are driven, and before the end bent or abutment is constructed.830
Compaction shall be in accordance with 203.23. After the embankments are
completed, the embankments shall be excavated to construct the end bents and berms.
Before driving piles, pilot holes to receive the piling shall be predrilled through the
embankment in accordance with 701.09(a). After the piles have been driven, the space
between the pile and the predrilled hole shall be backfilled with granular material as
directed. If the embankment in the area of the end bents is to consist of sand, gravel,
or other permeable material in which a predrilled hole would not remain open, the
piling shall be driven before the embankment is constructed. No direct payment will
be made for excavation of the embankment at the end bents or abutments, or for
predrilling, backfilling holes, or excavating fill; those costs shall be included in the840
cost of other pay items.
Rock and Shale Embankment
Utilization of these materials in embankment construction shall be in accordance
with the following.
Where rock is used for embankment, no large stones shall be allowed to nest but
shall be distributed over the area to avoid pockets. Voids shall be filled carefully with
small stones. The final 2 ft of the embankment just below the subgrade elevation shall850
be composed of suitable material placed in layers not exceeding 8 in. loose
measurement and compacted to the required density. Shale or shale-like materials shall
not be incorporated in the upper 2 ft of the embankment.
Where the depth of an embankment exceeds 5 ft and is to consist entirely of rock,
the rock shall be deposited in lifts not to exceed the top size of the material being
placed, but in no event exceeding 4 ft. The rock for any particular lift shall be deposited
on and pushed over the end of the lift being constructed by means of bulldozers or
other approved equipment. Depositing of rock over the end of any lift from hauling
equipment will not be allowed. If the voids of the last lift are not closed sufficiently,860
they shall be choked with small broken stone or other suitable material and compacted
as directed. A geotextile in accordance with 918.02(a), Type 2A shall be placed
between the rock and the soil.
203.20
171
Where the depth of embankment is 5 ft or less, or where the material being placed
does not consist entirely of rock, the material shall be placed in lifts not to exceed the
top size of the rock being placed but not exceeding 2 ft. Each layer shall be choked
thoroughly with broken stone or other suitable material and be compacted to the
required density or as directed. A geotextile in accordance with 918.02(a), Type 2A
shall be placed between the rock and the soil.870
Where a rock fill is to be placed over a structure, the structure shall first be covered
with 2 to 4 ft of earth or other approved material, and properly compacted before the
rock is placed. This covering shall be placed in accordance with 203.19.
Shale shall not be incorporated as rock embankment unless written permission is
obtained.
When these materials are encountered and are to be used for embankment880
construction, the compaction shall be accomplished with an approved vibratory
tamping-foot roller in conjunction with a static tamping-foot roller. The minimum
weight for the static tamping-foot roller shall be 30 t. The minimum total compactive
effort for the vibratory tamping-foot roller shall be 27.5 t. Total compactive effort is
defined as that portion of the static weight acting upon the unsprung compaction drum
added to the centrifugal force provided by that drum. If the manufacturer’s charts do
not list the static weight acting on the compaction drum, the roller shall be
satisfactorily weighed, the weight shall be added to the centrifugal force, and the roller
rated in accordance with the Construction Industry Manufacturers Association, CIMA.
Each tamping foot on the static roller shall project from the drum a minimum of 6 in.890
Each tamping-foot on the vibratory tamping-foot roller shall project from the drum a
minimum of 4 in. The surface area of the end of each foot on both tamping-foot rollers
shall be no less than 5 1/2 sq in.
Shale, shale and soft rock mixtures, or soft rock shall be placed in 8 in. maximum
loose lifts. Strength and moisture control for compacted soils shall be in accordance
with 203.23 or the density shall be at least 95% of maximum dry density with moisture
control in accordance with 203.23. Excavation and blasting procedures shall
accommodate the selective placement of these materials and avoid intermixing rock.
Rock shall be placed in accordance with 203.20(a).900
Water shall be applied to the shale in the cut to accelerate the slaking action and
again prior to disking and compaction to facilitate the compaction. The water shall be
distributed by an approved method which provides uniform application of the required
quantity of water. The water shall be uniformly incorporated throughout the entire lift
by a multiple gang disk with a minimum disk wheel diameter of 24 in.
Unless otherwise approved in writing, each embankment lift shall receive a
minimum of three passes with the static roller and a minimum of two passes with the
vibratory roller. The material shall be bladed before using the vibratory tamping-foot910
203.20
172
roller. A pass shall be in accordance with 402.15. The rollers shall not exceed 3 mph
during these passes. The number of passes will be adjusted upward if necessary to
meet the requirements of 203.23. No additional compensation will be allowed for
additional passes as specified herein, the cost of which shall be included in the cost of
the pay items.
Water required to facilitate the slaking and compaction of the shale or soft rock
will be measured in accordance with 203.27(h) and paid for in accordance with 203.28.
No payment will be allowed for any water required for compaction of material
furnished as borrow.920
In Dearborn, Decatur, Fayette, Franklin, Jefferson, Ohio, Ripley, Rush,
Switzerland, Union, and Wayne Counties specifically, or in other areas where
relatively thin layered shale and rock are encountered, their use will be allowed in the
construction of embankment, if the following provisions, in addition to those stated in
(b), are observed
relatively impervious, non-shale, non-erodible material.930
thickness and 1.5 ft in any other dimension.
vibratory tamping-foot roller shall be six static and two
vibratory.
If the material is found to be too intermixed with limestone fragments to enable
field density tests as required in this section, this requirement may be waived by940
written permission. As an alternate to this requirement, proofrolling shall be performed
after every four lifts, and the moisture content will be controlled on clayey soils in
accordance with 203.23.
203.21Embankment on Hillsides or Slopes
Before an embankment is placed on natural soil slopes or existing fill slopes of
4:1 or flatter, the existing ground surfaces shall be plowed or deeply scarified or, if the
nature of the ground indicates greater precautions should be taken for integrating the
proposed fill materials with the existing slopes, benches shall be cut into the existing
slopes before fill placement is started. All such precautionary work shall be done as950
directed. No direct payment will be made for plowing or scarifying, the cost thereof
shall be included in the various pay items of the contract. Before an embankment is
placed on natural soil slopes or existing fill slopes steeper than 4:1, benches a
minimum of 10 ft wide, unless otherwise specified, shall be cut into the slopes prior
to the placement of embankment fill. If benches are cut, the excavation involved will
203.21
173
be paid for at the contract unit price per cubic yard for the class or classes of excavation
encountered.
203.22Embankment Over Existing Roadbeds
If embankment for new pavement is to be placed over an area where a rigid960
pavement or any pavement having a concrete base is in place, or in other cases when
required, the upper surface of which is 1 ft or less below the subgrade elevation of the
proposed new pavement, the existing old pavement, including any concrete base, shall
be removed. The method of removal, disposal, and basis of payment shall be in
accordance with 202.05 and 202.14.
If embankment for new pavement is to be placed over an area where an existing
rigid pavement is in place, the upper surface of which is more than 1 ft but less than 3
ft below the subgrade elevation of the proposed new pavement, or in other cases when
required, the existing pavement shall be broken. Pavement shall be broken so the area970
of any individual unbroken slab does not exceed 1 sq yd.
If embankment for new pavement is to be placed over an area where an asphalt
filled brick-type or an asphalt-type surface on a concrete base is in place, and such
existing surface is more than 1 ft but less than 3 ft below the subgrade elevation of the
proposed new pavement, or in other cases when required, the brick and cushion
material, or the asphalt courses, shall be removed and the concrete base broken.
Removal of the surfacing material, breaking the base, disposal of removed material,
and basis of payment shall be in accordance with 202.05 and 202.14.
980
If embankment for new pavement is to be placed over an area where a
flexible-type pavement is in place, the top of which is at the approximate elevation of,
or is 1 ft or less below the required subgrade elevation of the proposed new pavement,
the existing pavement shall be loosened to the depth directed, but no less than 1 ft.
This loosened material shall be spread uniformly over the full width of the subgrade
plus 1 ft on each side and compacted. No direct payment will be made for this
loosening, spreading, and compacting, the cost thereof to be included in the various
pay items of the contract.
If embankment for new pavement is to be placed over an existing macadam, the990
surface of which is more than 1 ft but less than 3 ft below the subgrade elevation of
the proposed new pavement, the existing macadam shall be loosened to a depth
sufficient to prevent possible trapping of water above the existing surface. No direct
payment will be made for this loosening, the cost thereof to be included in the various
pay items of the contract.
Where the existing roadbed is too narrow, except as otherwise herein provided,
new pavement shall not be placed partly on old and partly on new embankment. If the
fill supporting an existing roadbed is 1 ft or more in depth, and is too narrow to carry
the entire width of the proposed new pavement, the existing width of roadbed shall be1000
taken down to include the new roadbed width and rebuilt from the lowest elevation of
203.22
174
the disturbed old roadbed to the required new width. This rebuilding shall be in
accordance with these specifications for constructing embankment and as directed. For
the necessary tearing down of the existing embankment, payment will be made at the
contract unit price per cubic yard for the class or classes of excavation encountered.
If an embankment is to be widened, due precautions shall be taken to ensure a
firm foundation. After all sod and other perishable material has been removed, the
existing shoulders shall be plowed down 2 ft out from the existing pavement. This
material shall be used for widening. Benches, a minimum of 4 ft wide, shall be cut into1010
the slope of the old embankment, unless otherwise directed. The materials from
plowing down the shoulders and benching the slopes shall be deposited, spread, and
compacted as set out herein for embankment, after which any remaining required
embankment shall be finished with additional material, deposited and compacted in
like manner. No direct payment will be made for benching, plowing, spreading, and
compacting, the cost thereof to be included in the various pay items of the contract.
Embankment other than Rock, with Strength or Density Control
The compaction will be determined by dynamic cone penetrometer, DCP, testing
in accordance with ITM 509 and the moisture content in accordance with ITM 506.1020
Soil classification will be performed in accordance with the ITM 512 and the following
DCP blow counts will be used for compaction control:
203.23
175
Textural
Classification
Maximum
Dry
Density
(pcf)
Optimum
Moisture
Content
Range (%)
Acceptable
Minimum
DCP value
for 6 in.
for 95%
compaction
Acceptable
Minimum
DCP value
for 12 in.
for 95%
compaction
Acceptable
Minimum
DCP value for
6 or 12 in.
for 100%
compaction
CLAY SOILS
Clay < 105 19 - 24 6 *
Clay 105 - 110 16 - 18 7 *
Clay 111 - 114 14 - 15 8 *
SILTY SOILS
Silty 115 - 116 13 - 14 9 *
Silty 117 - 120 11 *
SANDY SOILS
Sandy 121 - 125 8 - 12 12 *
Sandy > 125 15 *
GRANULAR SOILS - STRUCTURE BACKFILL and A-1, A-2, A-3 SOILS
No. 30 6 9
No. 4 7 10
1/2 in. 11 14
1 in. 16 19
* Test section required in accordance with ITM 513.
Unless otherwise specified, all material directed to be compacted in accordance
with 203.23 shall meet the acceptable minimum DCP value for 95% compaction.
Subgrade shall meet the acceptable minimum DCP value for 100% compaction when
required.
As an alternate, all embankments shall be compacted to at least 95% of their1030
maximum dry density and all subgrade shall be compacted to at least 100% of their
maximum dry density. In situ density will be determined in accordance with AASHTO
T 191 and the moisture content as specified.
For clay, silty, and sandy soils compacted to 100% of their maximum dry density,
a test section is required in accordance with ITM 513 for DCP testing.
Clay soils shall be constructed and tested with DCP in 6 in. lifts, whereas silty,
sandy, and granular soils shall be constructed in 6 in. lifts and tested with DCP for 12
in.1040
The moisture compaction range for all soil types shall be as follows:
203.23
176
Soil Type Moisture Compaction Range
Clay (< 105 lb/cu ft) -2 to +2% of optimum moisture content
Clay (105 - 114 lb/cu ft) -2 to +1% of optimum moisture content
Silty and Sandy (> 114 lb/cu ft) -3% to optimum moisture content
Granular 5 to 8%
DCP testing will be performed in accordance with the Frequency Manual at
random locations determined in accordance with ITM 802.
Moisture testing will be performed in accordance with the Frequency Manual.
If the embankment material is too wet or too dry, either the material shall be1050
aerated to remove excess moisture or watered and disked to increase the moisture
content, until in either case the moisture content is within the specified range.
Sufficient moisture tests will be made to ensure that this range is maintained
throughout the embankment.
The embankment material shall be placed in uniform level layers, left properly
shaped as set out above, and compacted with approved compacting equipment.
Compacting equipment shall include at least one 3-wheel roller or other approved
compacting equipment capable of providing a smooth and even surface on the
embankment as directed.1060
Each lift shall be disked or treated by some other mechanical means which shall
ensure the breaking up of any existing lumps and clods.
The loose depth of each lift shall be such that the required compaction can be
obtained, but in no case shall it exceed 8 in. Where a tamping roller is used, the loose
depth of lift shall not exceed the length of the tamper feet. The surface area of the end
of each foot of the tamping roller shall be no less than 5 1/2 sq in.
.1 Coal Ash Embankment1070
When used as borrow, coal ash shall be placed in the embankment, compacted,
and encased upon delivery to the project unless stockpiled at an approved location and
in an approved manner.
The Contractor shall include appropriate measures to prevent the movement of
coal ash from the embankment area. These measures include, but are not limited to
controlling stormwater runoff and fugitive dust. The top of coal ash embankments
shall be temporarily encased if embankment construction will be delayed for more
than seven days or if weather conditions warrant encasement. Control measures shall
be amended into the SWQCP in accordance with 205.1080
Coal ash shall not be mixed with other embankment materials within a given lift
of the embankment.
177
Coal ash shall not be placed in any of the following locations:
lake, reservoir, wetland, karst feature or any protected1090
environmental area.
pond or other ground source of water.
construction materials.
The loose depth of each lift of coal ash shall not exceed 8 in. Compaction of each
lift shall begin at the outer edge and progress towards the center of the embankment
using a maximum 10 t roller.
The moisture content shall be controlled within -2 and +2 percentage points of the
optimum moisture content determined in accordance with AASHTO T 99.1110
Compaction will be determined by DCP testing in accordance with ITM 509. The DCP
criteria for compaction acceptance will be as follows:
fly ash.
of bottom ash consisting of two compacted 6 in. lifts.
The Contractor shall coordinate with the Department’s Geotechnical Engineering1120
Division to determine the minimum blow count for a mixture of fly ash and bottom
ash.
Lateral underdrains shall be installed at the bottom of coal ash embankments.
Lateral underdrains shall be trenched into the embankment after it has reached an
elevation at least 2 ft above existing ground. The bottom of the trench shall be at the
top of existing ground with adjustment made for slope of the drain. The trench shall
be located within 2 ft of the toe of slope. The trench shall be backfilled with the coal
ash material used for the embankment, mechanically compacted to meet the
178
compaction requirements herein. Lateral underdrains shall be 6 in. diameter Type 41130
pipe in accordance with 715.02(d) and shall be enclosed in geotextile for underdrains
in accordance with 918.02. Lateral underdrains shall be spaced a maximum of 100 ft
longitudinally along the centerline of the embankment, shall outlet into the roadside
ditch on each side of the embankment, shall extend a minimum of 8 ft horizontally
into the embankment, and shall be sloped at a minimum of 0.2%.
Underdrain outlet protectors in accordance with 718.06 shall be installed at the
outlet end of each lateral underdrain.
Coal ash shall be encased on all sides with cohesive soil. The cohesive soil shall1140
be a silty loam, sandy clay, silty clay, sandy clay loam, clay, or a silty clay loam in
accordance with 903.02. All cohesive soils shall have a minimum clay content of 10%.
Encasement shall be as follows:
Total Finished
Embankment Height
Encasement
(measured horizontally)
Less than 10 ft 2 ft
10 ft to 20 ft 3 ft
Greater than 20 ft 4 ft
Encasement material shall be placed and compacted concurrently with the coal
ash lifts.
The top of the coal ash embankment shall be encased with a minimum of 1 ft of1150
cohesive soil beneath the bottom of subgrade.
203.24Method of Making Strength, Stiffness and Density Tests
The strength of chemically modified or compacted soils will be determined by
DCP in accordance with ITM 509.
The stiffness of chemically modified soils or aggregates will be determined by the
LWD in accordance with ITM 508.
The density of soils and aggregates, as a percent of compaction, will be based on1160
the maximum dry densities unless otherwise specified or directed.
DCP field compaction tests will be performed in accordance with 203.23. LWD
and density field compaction tests will be performed in accordance with this section.
The required compaction shall be obtained before additional material is placed.
The DCP criteria will be established on representative soils by performing ASTM
D1140, AASHTO T 88, AASHTO T 89, AASHTO T 90, and AASHTO T 99 using
203.24
179
Method A for soils and Method C for granular materials.1170
The optimum moisture content, maximum dry density, and gradation of
aggregates will be determined by performing AASHTO T 99 Method C, AASHTO T
11, and AASHTO T 27 on representative samples of the aggregates.
The soil strength of compacted soils or compacted chemically modified soils will
be determined by DCP in accordance with ITM 509 and the stiffness of chemically
modified soils or aggregates will be determined by LWD in accordance with ITM 508.
The moisture content will be determined in accordance with ITM 506 or AASHTO T1180
255.
As an alternative, in situ field density may be determined in accordance with
AASHTO T 191, except as listed below. The maximum dry density of the soil will be
determined by ITM 512.
silica sand in accordance with the gradation as follows:
Passing the No. 20 (850 μm) sieve - 98 to 100%1190
Passing the No. 40 (425 μm) sieve - 0 to 35%
Passing the No. 70 (212 μm) sieve - 0 to 2%
Sand such as Wedron Silica Sand No. 4075 or Ottawa 2.8
Blasting Sand has been found to be acceptable.
mm) sieve for soil and a 3/4 in. (19 mm) sieve for granular
material are encountered, corrections shall be made so that the
density obtained is for the minus No. 4 (4.75 mm) or 3/4 in. (191200
mm) only. After the densities are determined, the percent
compaction will be computed by the following formula:
Percent Compaction = In Place Density, pcf
Maximum Density, pcf x 100
control purposes after density values corresponding to those
obtained by either of the methods set out above have been
established.
1210
interpreted to mean either or both soil and granular materials.
203.24
180
Acceptance testing of chemically modified soils and coarse aggregates will be
determined by LWD testing in accordance with ITM 508. The allowable deflection
will be determined from a test section or will be specified. Test sections shall be
constructed in accordance with ITM 514 in the presence of a representative of the
Geotechnical Engineering Division for other materials not included in the Tables to
determine the maximum allowable deflection. The compaction procedures shall be in
accordance with 203.23, 215, 301, 302, and 303. Proofrolling of compacted aggregate1220
shall be performed in accordance with 203.26.
The allowable average deflection and maximum deflection for chemically
modified soils and aggregate over chemically modified and untreated soils shall be in
accordance with the following:
Table 1. Allowable Average Deflection and Maximum Deflection for Chemically
Modified Soils and Aggregate over Chemically Modified Soils
Material Type Allowable Average
Deflection (mm)
Maximum Deflection
at a Single Test
Location (mm)
Lime Modified Soil 0.35
Cement Modified Soil 0.31
Aggregate over Lime Modified Soil 0.35
Aggregate over Cement Modified Soil 0.31
1230
Table 2. Aggregate over Untreated Soils:
Where Proofrolling Can Be Performed
Material Thickness Allowable Average
Deflection (mm)
Maximum Deflection
at a Single Test
Location (mm)
6 in. Thick Coarse Aggregate No. 53 0.57*
12 in. Thick Coarse Aggregate No. 53 0.40**
18 in. Thick Coarse Aggregate No. 53 0.35**
* When deflection exceeds this value, the area shall be recompacted or undercut as
directed. The failed area will be delineated prior to excavation. Deflection will be
measured based on the top 6 in. thick coarse aggregate No. 53 material placed for
undercut.
** The Contractor shall recompact the coarse aggregate No. 53 in accordance with 301.06.
203.24
181
Table 3. Aggregate over Untreated Soils:
Where Proofrolling Cannot be Performed
Material Thickness Allowable Average
Deflection (mm)
Maximum Deflection
at a Single Test
Location (mm)
6 in. Thick Coarse Aggregate No. 53 0.65*
12 in. Thick Coarse Aggregate No. 53 0.52**
18 in. Thick Coarse Aggregate No. 53 0.49**
* When deflection exceeds this value, the area shall be recompacted or undercut as
directed. The failed area will be delineated prior to excavation. Deflection will be
measured based on the top 6 in. thick coarse aggregate No. 53 material placed for
undercut.
** The Contractor shall recompact the coarse aggregate No. 53 in accordance with 301.06.
Note:
The Engineer will perform the moisture test on in-situ soils prior to placement of coarse
aggregate. If the result of the moisture test is > 13%, the Engineer will contact the
Department’s Geotechnical Engineering Division.
Acceptance of the compaction of chemically modified soils or aggregate will be
determined by averaging three LWD tests obtained at a random station determined in
accordance with ITM 802, for each 1,400 cu yds of chemically modified soil or for1240
each 800 t of compacted aggregate. Where the construction area is 8 ft wide or more,
the location of the three tests will be at 2 ft from each edge of the construction area
and at 1/2 of the width of the construction area. Where the construction area is less
than 8 ft wide, the location of the three LWD tests will be spaced at 1/2 of the width
of the construction area and spaced 5 ft apart in the longitudinal direction. The average
deflection shall be equal to or less than the maximum deflection allowed in the tables
above or determined by the test section.
203.25Embankment Without Stiffness Control
When aggregate is used for embankment construction and it is not possible to1250
perform stiffness testing in accordance with ITM 508 or strength testing in accordance
with ITM 509, such material shall be compacted with several passes of crawler-tread
equipment or with approved vibratory equipment, or both. The equipment weight shall
be at least 10 t. The materials shall be placed in lifts not to exceed 9 in. loose
measurements, or as directed by the Engineer. Each lift shall be compacted with a
minimum of five passes. The tread areas shall overlap enough on each trip so that the
entire embankment is compacted uniformly. When the embankment reaches 24 in.
below the proposed subgrade elevation, proofrolling shall be performed in accordance
with 203.26. Proofrolling shall also be performed at every 5 ft of fill placed. Any defect
shall be corrected as directed. Upon acceptance, a layer of geotextile in accordance1260
with 918.02(a) Type 2B, shall be placed and the remaining embankment shall be
constructed with No. 53 aggregate in accordance with 301.
203.25
182
At locations inaccessible to the above compacting equipment, the required
compaction shall be obtained with approved mechanical tamps or vibrators, in which
case the depth of lifts, loose measurement, shall not exceed 4 in.
203.26Proofrolling
When proofrolling is specified, the work shall be performed with an on-highway
dump truck with a minimum tire pressure of 90 psi.1270
Proofrolling for original ground or embankment construction shall be performed
using a dump truck weighing at least 15 t. Proofrolling for subgrade preparation shall
be performed using a dump truck weighing at least 33 t. All proofrolled surfaces shall
be covered completely with a single pass. Operating speed of the proofrolling truck
shall not exceed 2 mph.
Deflections or rutting in excess of 1/2 in. shall require remediation of the surface
as directed. Deflection or rutting in excess of 3 in. shall require corrective remediation
measures and the Department’s Geotechnical Engineering Division will be contacted.1280
Proofrolling shall be performed after remediation measures on embankment or
subgrade prior to the placement of additional material. There shall be one or two
complete coverages as directed. Roller marks, irregularities, or failures shall be
corrected.
203.27Method of Measurement
The quantities of excavation for which payment will be made will be those shown
in the Schedule of Pay Items for the pay items, provided the project is constructed to1290
the lines and grades shown on the plans.
Unless otherwise specified, the project limits will be considered as one balance.
If earthwork balances are shown on the plans, they are for information only.
When the plans have been altered or when disagreement exists as to the accuracy
of the plan quantities in any balance, or the contract quantity, either party shall have
the right to request and cause the quantities involved to be measured in accordance
with measured quantities. When the quantities are measured for payment, the original
plan cross-sections plotted on the plans shall be used as original field cross-sections.1300
Additional original cross-sections may be interpolated at points where necessary to
determine the quantities more accurately. If the Contractor has acceptable engineered
data that indicates an excavation quantity that is in error by more than 2%, then
additional measurements will be performed on the areas in question and payment will
be made for actual quantities.
When payment is specified on a volume basis, all accepted excavation and borrow
will be measured in its original position by cross-sectioning the area excavated, which
203.26
183
measurements will include over-breakage or slides in common excavation and1310
unclassified excavation, not attributable to carelessness, and authorized excavation of
rock, shale, peat, or other unsuitable material. Volumes will be computed from cross-
section measurements by the average end area method.
Measurement for payment will not include material excavated beyond authorized
cross-sections. Where material is excavated beyond authorized cross-sections and
wasted without authority, the material so wasted will be measured and deducted from
the excavation quantities. Unless otherwise authorized, the amount of waste to be
deducted, when common excavation, rock excavation, unclassified excavation,
borrow, or other excavation has been wasted along embankments or elsewhere without1320
authority shall be that portion of the embankment or fill which is outside a 1/4 to 1
slope in excess of that shown on the plans, and all portions outside a line from the
shoulder point to a point 4 ft, measured horizontally, outside the theoretical toe of the
slope. In determining waste, no tolerance in widths of shoulders will be allowed unless
additional widths are authorized in writing before shoulders are finally constructed.
Measurements will be made for unsuitable materials actually excavated and
removed to obtain proper compaction in cut sections and in foundations for fill
sections.
1330
Where it is impracticable to measure material by the cross-section method due to
the erratic location of isolated deposits, acceptable methods involving three-
dimensional measurements may be used to measure the material in its original
position.
The cubic yards of peat excavated will be determined by cross-sections, as
described above, with the final cross-sections taken after complete excavation and
before placing granular backfill, if peat is removed by excavation. When removal by
displacement is necessary, final cross-sections will be derived from cased test holes
through the completed granular treatment in accordance with 203.17. Such test holes1340
shall be located at intervals which clearly define the bottom of the treatment between
lateral limits. Pay quantities of peat excavation will be limited to the volume of peat
lying between vertical lines as shown on the plans for lateral limits.
Cased test holes and exploratory drilling will be measured by the linear foot; B
borrow by the cubic yard, in accordance with 211.09. However, measurement to neat
lines will not apply unless specifically designated. Breaking pavement will be
measured by the square yard in place before breaking.
Linear grading will be measured by the linear foot. Measurement will be made
once along each survey centerline for all linear grading completed on the line.
Deductions will be made for bridges. Classes of excavation, except for required
borrow, involved in linear grading will not be measured.
203.27
184
A pay item for excavation may be specified to be measured and paid for on a
weight basis. When a weight basis is specified, the material will be weighed in
accordance with 109.01(b).
1360
When specified, embankments constructed will be measured in accordance with
the terms set forth.
When embankment is specified as a separate pay item, the volume as constructed
will be measured in place in accordance with 203.27(b). However, no measurement
will be made for excavation or borrow, except as noted herein. The volume shall be
computed in cubic yards from the dimensions of the embankment cross-sections and
to the depth below completed grade to which this method of construction applies. No
shrinkage factor shall be used in computing the embankment volume. Measurements1370
will be made for unsuitable materials actually excavated and removed to obtain proper
compaction in cut sections and in foundations of fill sections in accordance with
(b). B borrow from off the right-of-way placed within embankment areas will
be measured in accordance with 211.09.
Borrow will be measured by the cubic yard. Except as otherwise provided herein,
borrow will be cross-sectioned in its original position before excavation is started,
again after it is completed, and the volume computed by the average end area method.
No material shall be excavated as borrow until unsuitable material, vegetation, and1380
other perishable matter have been removed and cross-sections taken over the cleared
area. None of this removed unacceptable material shall be moved back into the pit
before final sections are taken.
If borrow is obtained from a source where it is impracticable to measure the
material in its original position, such material will be measured after being placed in
embankment with no allowance made for a compaction factor. The borrow may be
measured in truck beds in accordance with 211.09 for contracts having a proposal
quantity less than 500 cu yds. If such source is contemplated, approval shall be
obtained in writing before this part of the work is started. For quantities less than1390
5,000 cu yds, the material may be weighed in accordance with 109.01(b) and
converted from pounds shown on the weigh tickets to cubic yards using a factor of
3,000 lb/cu yd.
If borrow is specified outside the limits of B borrow and if the requirements of the
work do not otherwise prohibit, material in accordance with these specifications for B
borrow, may be furnished and placed at the contract unit price for borrow, in which
case measurement will be in accordance with 211.09. Measurement of borrow in
accordance with 211.09 will be limited to nominal quantities outside the limits of
structure backfill. The quantity of borrow measured for payment will not exceed the1400
theoretical quantity of B borrow furnished.
203.27
185
Mechanical treatment of embankment foundation soils will be measured by the
square yard. Chemical treatment of embankment foundation soils will be measured in
accordance with 217.
Soft Rock
When payment for water for shale is specified in the contract, the water for shale1410
used will be measured by the 1,000 gal. by means of calibrated tanks or distributors,
or by means of accurate water meters. When water for shale is not specified as a pay
item in the contract, the water for shale that is used will not be measured directly. Such
measurement will be included in that required for other pay items.
If the pay unit for a pay item for excavation is lump sum, no measurement will be
made.
Exploratory cores will be measured by the linear foot of rock core.
If coal ash is used as borrow, it will be measured in accordance with 203.27(f).
If coal ash is encountered during excavation, it will be measured as common
excavation in accordance with 203.27.
203.28Basis of Payment
The accepted quantities of excavation and embankment will be paid for at the1430
contract price per unit of measurement for each of the pay items listed below which is
included in the Schedule of Pay Items. Common excavation and unclassified
excavation will be paid for on the unit basis of contract quantities in accordance with
(a), without any quantity limit, unless otherwise shown in the Schedule of Pay
Items. Combined quantities of borrow, common and unclassified excavation not
exceeding 15,000 cu yds will be paid for on the basis of contract quantities in
accordance with 203.27(a) with no adjustment to plan shrinkage factor. Except as
noted above, borrow, as well as all other excavation, will be paid for on the basis of
measured quantities in accordance with 203.27(b), unless otherwise shown in the
Schedule of Pay Items. Linear grading will be paid for at the contract unit price per1440
linear foot.
If the class of excavation is linear grading, additional borrow and the excavation
of and disposal of unsuitable material not included as pay items will be paid for as
follows:
203.28
186
If the total quantity exceeds 5,000 cu yds at a given location, it will be paid for at
$8.00 per cu yd. If the total quantity exceeds 1,000 cu yds, but does not exceed 5,000
cu yds at a given location, it will be paid for at $12.00 per cu yd. If the total quantity
does not exceed 1,000 cu yds at a given location, it will be paid for at $15.00 per cu1450
yd.
Linear grading includes only such grading within the construction limits. All
grading the Contractor is directed to perform outside the construction limits, except
for the Contractor’s convenience, will be paid for in accordance with 104.03 or 109.03
unless such grading is shown on the plans or in the Contract Information book.
Existing concrete building foundations, concrete walls, concrete columns, or
concrete steps not visible and not shown on the plans within the limits of the planned
excavation will be paid for at 10 times the contract unit price per cubic yard for1460
common or unclassified excavation, whichever is set out as a pay item. Unless a waste
area is established within the contract limits, the minimum pay for this work will be
$80.00 per cu yd.
Excavation and disposal of unsuitable material will be paid for at the contract unit
price for the class of excavation involved. If no such pay item is included in the
contract and embankment is included as a pay item, the excavation and disposal will
be paid for at the contract unit price for embankment, unless otherwise directed.
If there is no pay item for rock excavation and such is encountered, it will be paid1470
for at $125.00 per cu yd for quantities less than or equal to 100 cu yds. For quantities
greater than 100 cu yds pay will be determined in accordance with 104.03.
If there is no pay item for common excavation and if such is encountered, it will
be paid for at the contract unit price per cubic yard for borrow.
If the contract includes a pay item for waterway excavation, and if class Y
excavation is encountered and there is no pay item for such, the class Y excavation
will be paid for at 10 times the contract unit price per cubic yard for waterway
excavation, or $100.00 per cu yd, whichever is greater.1480
If the contract does not include a pay item for waterway excavation and such is
encountered, pay will be determined in accordance with 104.03.
If excavation is necessary to investigate or to seal sinkholes, or to explore
underground drainage, the accepted quantity involved at each location will be paid for
as follows. The first 10 cu yds or fraction thereof will be paid for at 10 times the
contract unit price for the class of excavation encountered. The next 40 cu yds or
fraction thereof will be paid for at seven times the contract unit price for the class of
excavation involved. Additional quantities will be paid for at three times the contract1490
unit price per cubic yard for the class of excavation involved.
203.28
187
Material overlying the peat deposits which is excavated and used in embankment
will be considered as common excavation and will be paid for as such. Excavation for
standard side ditches or other side ditches which are constructed through peat areas at
locations shown on the plans, or where directed, will be paid for at the contract unit
price per cubic yard for common excavation.
Mechanical treatment of embankment foundation soils will be paid for by the
square yard as embankment foundation soils treatment.1500
Cased test holes and exploratory drilling will be paid for at the contract unit price
per linear foot.
If there is no pay item for borrow, the costs of identifying the borrow areas, the
archeological investigation, all required permits, and the opening and closing of the
borrow area will be included in a change order developed in accordance with 109.05
and paid for as borrow area.
If the contract documents do not identify excess excavation or require removal of1510
any items from the site, the cost of identifying a disposal area, archeological
investigation, all required permits, and the opening and closing of the disposal area
will be included in a change order developed in accordance with 109.05 and paid for
as disposal area.
If a type of excavation for which no pay item exists is required and the new type
of excavation requires the Contractor to use equipment not otherwise being used on
the contract, all cost involved in determining the type of equipment necessary to
complete the work and making this equipment available for the project will be
included in a change order developed in accordance with 109.05 and paid for as1520
additional mobilization and demobilization.
If a type of excavation for which no pay item exists is required and the new type
of excavation requires additional traffic control not shown on the plans or results in
traffic control being required for an additional period of time, all cost involved in
providing the additional traffic control will be included in a change order developed
in accordance with 109.05 and paid for as additional maintaining of traffic.
Coal ash used as borrow will be paid for at the contract unit price for borrow.
1530
Excavation of coal ash will be paid for at the contract unit price for common
excavation.
Payment will be made under:
Pay Item Pay Unit Symbol
Borrow ....................................................................................... CYS
203.28
188
Breaking Pavement.................................................................... SYS
Cased Test Holes ....................................................................... LFT1540
Embankment Foundation Soils Treatment ................................ SYS
Embankment.............................................................................. CYS
Excavation, Common ................................................................ CYS
Excavation, Peat ........................................................................ CYS
Excavation, Rock....................................................................... CYS
Excavation, Unclassified ........................................................... CYS
Excavation, Waterway............................................................... CYS
Excavation, Y ............................................................................ CYS
Exploratory Cores...................................................................... LFT
Exploratory Drilling .................................................................. LFT1550
Linear Grading .......................................................................... LFT
Water for Shale .......................................................................... kGAL.
If embankment is specified as a pay item, borrow and common excavation, unless
otherwise specified, will not be paid for directly. The costs thereof shall be included
in the cost of embankment. Such price shall be full compensation for preparation of
the natural ground on which the embankment is to be placed and excavating, hauling,
placing, spreading, and compaction of materials in accordance with 203.23. The costs
of labor, equipment, tools, and necessary incidentals shall be included in the cost of
embankment. The cubic yards of suitable material used in the embankment excavated1560
from the right-of-way and paid for under a specific pay item will not be deducted from
the embankment quantities. The quantity of material to be paid for as B borrow and
placed within the embankment area as specified will be deducted from the quantity of
embankment.
The costs of excavating, backfilling, disposal of surplus material, labor,
equipment, tools, and necessary incidentals necessary shall be included in the cost of
excavation required to seal sinkholes or explore underground damage.
The costs of all excavated or displaced peat, regardless of depth, peat disposal,1570
temporary surcharge, machine operation, and machine availability shall be included in
the cost of peat excavation. However, the Department may provide temporary right-
of-way for peat disposal when so specified.
Cost for providing additional lighting for grading operations shall be included in
the cost of other pay items in this section.
No payment will be made for the construction or restoration of borrow or disposal
sites.
1580
No payment will be made for the inspection of disposal and borrow areas for
wetland identification, obtaining of permits, the development and construction of all
mitigation measures, or the fulfillment of permit requirements.
203.28
189
The cost of boring the holes, casings and fittings, labor, equipment, tools, and all
necessary incidentals shall be included in the cost of cased test holes or exploratory
drilling.
The cost of reshaping scoured or eroded areas shall be included in the cost of other
pay items.1590
The cost of surface roughening shall be included in the cost of other pay items.
The cost of identification of borrow areas, archeological investigations, and
changes to construction operations caused by the identification of an archeological site
shall be included in the cost of borrow, unless otherwise agreed to in writing.
The cost of all classes of excavation, except required borrow, within the limits of
linear grading shall be included in the cost of linear grading.
1600
The cost of geotextiles shall be included in the cost of other pay items.
The costs for the use of coal ash in embankment construction, including, but not
limited to testing of the material, encasement, additional erosion and sediment control
measures, lateral underdrains and all incidentals shall be included in the cost of other
pay items in this section.