731MECHANICALLY STABILIZED EARTH RETAINING WALLS

IN · 2024 Standard Specifications✓ Full text on BuildSpecBook pages 844–0 Save this section

Ask about Section 731

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

WALLS

731.01Description

This work shall consist of the design, furnishing materials, and placement of MSE retaining walls in accordance with 105.03.

731.02General Desi gn Requirements

An MSE retaining wall shall consist of a non-structural concrete leveling pad, concrete face panels, precast or cast-in-place concrete coping, ground reinforcement 10 elements mechanically connected to each panel, and accommodations for appurtenances behind, in front of, under, mounted upon, or passing through the wall. Ground reinforcement shall have sufficient strength, frictional resistance, and quantity as required by design. If a drainage system is shown on the plans, the wall design shall accommodate the drainage system.

The MSE retaining wall system shall be selected from the QPL of Retaining Wall Systems. A retaining wall system manufacturer will be considered for inclusion on the QPL by following ITM 806, Procedure J. The quantities shown in the Schedule of Pay Items will be the same for each MSE retaining wall system. The MSE retaining wall 20 panels shall be constructed as shown on the panels’ working drawings, based on the requirements herein.

If the wall manufacturer needs additional information to complete the design, the Contractor shall be responsible for obtaining such information.

All appurtenances behind, in front of, under, mounted upon, or passing through the wall such as drainage structures, utilities, or other appurtenances shown on the plans, shall be accounted for in the design of the wall.

The Contractor shall determine the final leveling-pad layout and step elevations that provide the wall envelope shown on the plans. The Contractor shall use this information to provide a final horizontal plan and vertical elevation profile along the front face of the wall to acco unt for the wall envelope shown on the plans. The final coping or top-of-wall elevations shall be at or above those shown on control line 1 on the plans. The final top-of-leveling-pad elevations shall be at or below those shown on control line 3 on the plans. Leveling-pad steps shall be in 2.5 ft increments. The top of the leveling pad elevation shall be a minimum of 1.0 ft above the ordinary high water mark, OHWM, or the groundwater table elevation, whichever is higher. The leveling pad dimensions shall typically be 12 in. wide and 6 in. thick and as shown on the 40 working drawings.

Where a coping is utilized, the wall face panel shall extend up into the coping as shown on the plans. The top of the face panels may be level or sloped to meet the top 731.01

of the face panel line shown. Cast-in-place concrete will not be an acceptable replacement for panel areas indicated by the wall envelope.

Where walls or wall sections intersect with an included angle of 130° or less, a single vertical corner element separate from the standard panel face shall abut and interact with the opposing panels. The corner element shall have ground reinforcement 50 connected specifically to that panel. All turn-point locations where the wall forms an angle that are shown on the working drawings shall correspond to those shown on the plans unless otherwise approved in writing by the Engineer.

Face panels shall be designed to accommodate a differential settlement of 1 linear unit in 100. Face panels of an area greater than 32 sq ft through 64 sq ft shall be designed to accommodate differential settlement of 1 linear unit in 200. Where shown on the plans, slip joints to accommodate excessive or differential settlement shall be included.

Only one typical face panel shape and ar chitectural finish shall be used per contract.

731.03Design Criteria

The internal, external, and compound stab ility shall be the re sponsibility of the Contractor. The global stability of the wall mass will be the responsibility of the Engineer.

The Contractor shall use the information supplied in the contract documents including but not limited to the plans and the geotechnical report when designing the 70 wall. The design of the wall including the internal, external, and compound stability shall be in accordance with the AASHTO LRFD Bridge Design Specifications and the requirements specified herein.

The splay angle of soil reinforcement m easured from a line pe rpendicular to the wall face, to avoid an obstruction, shall not be more than 15°. The tensile capacity of the splayed reinforcement shall be reduced by the cosine of the splay angle.

The design for internal stability shall include connection st rength design. Each design case shall present maximum tension capacity, soil overburden pressure, and 80 horizontal pressure at each reinforcement level, pullout capacity at each reinforcement level, the length of embedment in the resisting zone, and the total length of reinforcement at each level.

The design for the external stability shall include applied bearing pressure, overturning, sliding, and stability of temporary construction slopes.

The design for the compound stability shall include the slope present on top of and at the toe of the MSE wall.

731.03

The value of the pullout resistance factor, F*, used in design calculations shall be obtained from AASHTO LRFD Bridge Design Specifications figure 11.10.6.3.2-2.

The minimum embedment at the front face of the wall shall be in accordance with the AASHTO LRFD Bridge Design Specifications, section 11.10.2.2. However, the minimum embedment depth to the top of the leveling pad shall never be less than 3 ft unless founded on rock. A 4 ft horizontal bench in front of the wall shall be provided for slopes steeper than 4.0H:1.0V.

The embedment and bench material, at th e front face of the wall, shall match the 100 structural backfill material used for the wall and shall be encased in accordance with

203.09. Geotextiles, Type 2B, in accordance with 918.02(a), shall be installed over the

bench material in accordance with 616. 11. The embedment and bench shall be daylighted at the bottom of the slope with uniform riprap placed at a minimum 12 in. depth for erosion control.

An MSE wall shall be designed fo r a service life of 75 years.

(a)Geotechnical Considerations

The theoretical failure plane within the soil mass shall be analyzed so that the soil-110 stabilizing component extends sufficiently beyond the failure plane to stabilize the material. External loads which affect the internal stability, such as those applied through piling, bridge footings, traffic, crashwall, or slope surcharge, shall be accounted for in the design. The sizes of all structural elements shall be determined such that the design load stresses do not exceed the factored stresses shown in the AASHTO LRFD Bridge Design Specifications.

The material used as backfill in the reinforced backfill zone shall be assumed to have a unit weight of at least 120 lb/cu ft unless lightweight fill has been specified. 7KHijDQJOHIRUWKHLQWHUQDOGHVLJQRIWKHUHLQIRUFHGEDFNILOOVKDOOEHƒ7KHijDQJOH120 of the retained backfill zone shall be 30° for design. For the external design parameters, such as but not limited to, bearing capac ity, sliding, overturning, eccentricity, and global stability, the actual soil strength parameters and the expected settlement of the existing soil under the reinforced backfill zone shall be obtained from the geotechnical report.

(b)Height of Wall

The wall limits shall be defined by the wall envelope shown on the plans. For internal stability design purposes, the design height, H D, of wall shall be as follows:

1.For a wall with a level surcharge, the design height of the wall,

HD, shall be measured from the theoretical top of the leveling pad to the top of the coping or to the gutter line of the traffic barrier. The top of the wall shall be the theoretical top of the face panels only where a coping or barrier is not used.

731.03

2.For a wall with a sloping surcharge, the design height of the

wall, H D, shall be measured from the theoretical top of the leveling pad to a point above the top of the wall as calculated from the formula as follows: 140

HD = H + 0.3H tanȕ

1-0.3tanȕ

where: ȕ VXUFKDUJHVORSHDQJOHDVPHDVXUHGIURPWKHWRSRIWKH coping, and H = height of the wall from the theoretical top of the leveling pad to the top of the coping.

3.For an abutment face, the design height of the wall, H

D, shall be measured from the theoretical top of the leveling pad to the top 150 of the roadway surface.

(c)Ground Rei nforcement

The ground reinforcement length shall be the controlling length resulting from the internal or external design. The minimum ground reinforcement length for an MSE wall shall be the greater of 0.7H D or 8 ft, where HD is the design height of the wall.

The ground reinforcement shall be the same length from the bottom to the top of each wall section regardless of the type of ground reinforcement used. Differing ground reinforcement elements shall be marked for ease of construction. This element 160 may be used individually or in a prefabricated grouping.

The ground reinforcement for the MSE volume shall be sized using the lesser of the factored loads for each specific connection and each specific reinforcing element. The connection’s applied factored load and effective pullout length shall be determined in accordance with the AASHTO LRFD Bridge Design Specifications.

For mats, grids, or strip steel, the minimum zinc coating thickness shall be 2 oz/sq ft. Such thickness shall be assumed to be 4 mils for purpose of calculation of reduced structural section. 170

The factored applied bearing pressu res under the stabilized mass for each reinforcement unit’s length shall be shown on the working drawings. It shall not exceed the maximum factored soil bearing resistance shown on the plans. Passive pressure in front of the wall mass shall be assumed to be zero for design purposes.

(d)Other Criteria
1.Traffic Load Considerations

Traffic load shall be considered as live lo ad surcharge. The load factor of traffic 180 load shall be 1.75 in accordance with AASHTO LRFD Bridge Design Specifications table 3.4.1-1. 731.03

2.Traffic Impact Considerations

Where traffic barriers are constructed above an MSE wall or reinforced backfill zone, the MSE wall supporting traffic shall include computations showing that the Extreme Event II limit state due to traffic impact has been met.

Loadings for MSE wall design for the Extreme Event II limit state shall be in accordance with the following table: 190

Maximum Nominal Tension Rupture and Pullout Impact Loads Layer Tension Impact Load Pullout Impact Load First Top Layer 2,300 lb/ft 1,300 lb/ft Second Top Layer 600 lb/ft 600 lb/ft

The Extreme Event II design for the top two layers shall be separately prepared and compared with the routine internal stability design.

3.Tributary Area – Design Basis

For internal stability analysis of MSE walls, each layer of reinforcement is assigned a tributary area, A trib in accordance with FH WA publication No. FHWA- NHI-10-025, Design and Construction of Mechanically Stabilized Earth Walls and Reinforced Soil Slopes Volume II and as follows: 200

Atrib = (wp) (Svt)

where:

w p = the wall system concrete panel width of the precast facing element, and Svt = the vertical tributary spacing of the reinforcement based on the location of the reinforcement above and below the level of the reinforcement under consideration.

For a wall system with steel reinforcemen t, within each tributary area, the factored reinforcement tensile resistance, T r, and the factored pullout resistance, Prr, shall be no less than the maximum factored tension load, Tmax. If the calculated minimum number

of strips is a decimal number, the minimum number required shall be rounded up to210

the next whole number.

731.04Submittals

The Contractor shall submit working drawings in accordance with 105.02. The

Contractor shall submit design calculations in accordance with 105.02 and the

following additional requirements. In case of discrepancy, the requirements listed

below supersede those listed in 105.02. Design calculations shall include each design

case of the MSE wall analyzed. Calculations may be in either longhand or computer-

731.04

833

printout format and shall follow a systematic and logical methodology. A summary

sheet that shows design assumptions and their source, controlling parameters and load220

cases, and other pertinent input and output information shall be included with the

calculations package. Wall construction operations shall not begin until the Contractor

receives written notice that the working drawings are approved.

(a)The working drawings shall include all details, dimensions,

quantities, and cross-sections necessary to construct the wall. They

shall include, but shall not be limited to, the following:

1.Plan and elevation views along the front face of wall alignment,

which shall include the following:230

a.A final profile along the front face of the wall.
b.A plan layout of the front face of the wall showing all

alignment points with stations and offsets.

2.A plan view of the wall that indicates the offsets from the

construction centerline to the face of the wall at all changes in

horizontal alignment. A plan view and elevation view which

detail the placing position and connection of all ground

reinforcement units in areas where piling, utility, or other240

structures are near the wall.

3.An elevation view along the front face of the wall with respect

to the wall alignment, which shall include the following:

a.The elevation at the top of the wall at all horizontal and

vertical break points at least every 50 ft along the face

of the wall.

b.All steps in the leveling pad.
c.The designation as to the type of wall unit.250
d.The length of ground reinforcement units.
e.A wall-elevation envelope that encompasses such

envelope shown on the plans.

4.All general notes required for constructing the wall.
(b)Panel details shall show all dimensions necessary to construct the

element, all reinforcement in the element, and the location of ground

reinforcement connection devices embedded in the panels.

260

(c)Details for construction of the wall around drainage facilities

including outletting of internal drainage from the MSE volume.

(d)Details of the architectural treatment.

731.04

834

(e)Details for diverting ground reinforcement around obstructions such

as piles, catch basins, or utilities.

(f)Details for the connections between the concrete panel and the

ground reinforcement.270

(g)'HWHUPLQDWLRQ RI ij DQJOH IRU UHLQIRUFHG PDWHULDOV DQG UHWDLQHG

materials.

(h)Detailed differential settlement calculations.
(i)Detail standard summary sheet of the input values in the following

format:

280

MATERIALS

731.05Materials

Materials shall be in accordance with the following:

Admixtures for Concrete ............................................. 912.03

Wall Detail Design Value

Design Life

Reinforcement

Type

Configuration (strip or grid)

Width, in.

E c (Corroded Thickness), in.

Reinforcement Strength (Fy ), ksi

Coverage Ratio (Rc )

Reinforced Fill

Type

Unit Weight, pcf

Friction Angle, degrees

Reinforcement Pullout

Resistance

F*

Į

Retained Fill

Type

Unit Weight, pcf

Friction Angle, degrees

Foundation Soil

Type

Unit Weight, pcf

Friction Angle or cohesion A ,

degrees or lb/sq ft

A Use only one value, whichever is applicable.

731.05

835

Air Cooled Blast Furnace Slag .................................... 901.09

Alignment Pins ............................................................ 910.07(d)

B Borrow ..................................................................... 211.02

Coarse Aggregate, Class A or Higher,290

Size No. 8, No. 91................................................. 904.03

Coarse Aggregate, Class F or Higher,

Size No. 93PG ...................................................... 904.03

Components of MSE Retaining Walls......................... 901.10

Deformed and Smooth Steel WWR............................. 910.01(b)5

Fly Ash ........................................................................ 901.02

Geotextile for Use Under Riprap ................................. 918.02

Ground Reinforcement ................................................ 910.07(b)300

Joint Spacers and Joint Covering................................. 901.10(b)

Portland Cement .......................................................... 901.01(b)

Preformed Expansion Joint Filler ................................ 906.03

Rapid Setting Patch Materials ..................................... 901.07

Reinforcing Bars.......................................................... 910.01

Steel Components of MSE Retaining Walls ................ 910.07

Structure Backfill, Type 3 ........................................... 211.03.1, 904.05

Underdrains for MSE Walls ........................................ 718.03

Water ........................................................................... 913.01310

Concrete for the leveling pad and coping shall be class A. Concrete used in

openings to accommodate appurtenances behind, in front of, under, mounted upon, or

passing through the wall shall be class C.

The Contractor shall supply all materials listed in 901.10, 910.07, and tie strips,

bearing pads, and all necessary incidentals through a manufacturer listed on the QPL

of Retaining Wall Systems.

(a)Backfill320
1.Reinforced Backfill Zone

Structure backfill Type 3 in accordance with 211 shall be used in the MSE wall

reinforced backfill zone and the horizontal bench in front of the wall. Structure backfill

nominal size aggregates No. 4 and No. 30 shall not be used.

2.Retained Backfill Zone

Structure backfill in the retained backfill zone shall be Type 3 or B borrow as

shown on the plans.

330

(b)Geotextile Requirements in Backfill Zones

If the Contractor elects to use a different size aggregate in the retained backfill

zone from that used in the reinforced backfill zone, geotextiles Type 2B in accordance

731.05

836

with 918.02(a) shall be installed at the interface between the reinforced and retained

backfill zones.

If the Contractor elects to use the same size coarse aggregate in both the reinforced

and retained backfill zones, geotextiles Type 2B in accordance with 918.02(a) shall be

installed along the interface between the retained backfill zone and the adjacent soil.

In addition, geotextiles Type 2B in accordance with 918.02(a) shall be installed at all340

interfaces of coarse aggregate and finer soils when used in the foundation.

CONSTRUCTION REQUIREMENTS

731.06General Requirements

The wall manufacturer’s representative shall provide technical instruction,

guidance in pre-construction activities including the pre-construction conference, and

on-site technical assistance to the Contractor during construction.

731.07Foundation Preparation350

Prior to wall construction, the foundation for the structure shall be graded for a

width equal to or exceeding the length of the ground reinforcement or as shown on the

plans. The foundation, if not in rock, shall then be compacted in accordance with 203.

After the foundation has been compacted, the resulting grade of the foundation shall

be 1 in. per foot sloped from the back of the leveling pad downward toward the back

of the reinforced zone. The portion of the foundation beneath the leveling pad shall

not be sloped. The foundation shall be proofrolled in accordance with 203.26. If

unsuitable foundation material is encountered, it shall be removed and replaced with

B borrow in accordance with 211.02 and compacted in accordance with 211.04.

360

After proofrolling has been completed and all unsuitable foundation material has

been removed and replaced, compaction of the portion of the foundation beneath the

reinforced backfill zone will be verified by dynamic cone penetrometer, DCP, testing

in accordance with ITM 509.

One DCP measurement for every 500 sq ft within the reinforced backfill zone and

five DCP measurements per end bent will be performed.

A DCP measurement is defined as the number of blows per 6 in. increment for a

total penetration of 30 in., based on five sets of DCP readings at each location. A370

minimum of five blows of the DCP for each 6 in. increment is considered acceptable.

Unsuitable areas shall be removed, replaced, and compacted in accordance with

203 and 211. DCP verification of compaction beneath the reinforced backfill zone will

not be required if the foundation is in an embankment section that is constructed in

accordance with 203.

731.06

837

An unreinforced concrete leveling pad shall be provided at each foundation level

as shown on the plans. The leveling pad shall be cured in accordance with 702.22 for

a minimum of 12 h before placement of concrete face panels.380

731.08Retaining Wall Excavation

The Contractor shall notify the Engineer a minimum of 7 calendar days or other

time as mutually agreed upon before beginning the excavation so that measurements

can be taken of the undisturbed ground.

Prior to starting excavation operations at the wall site, the area shall be cleared

and grubbed to the excavation with the limits shown on the plans and in accordance

with 201.03. All timber, stumps, or debris shall be disposed of in accordance with

201.03. Excavation shall include the construction and subsequent removal of all390

necessary bracing, shoring, sheeting, and cribbing. Excavation shall also include all

pumping, bailing, and draining.

The excavation shall be shored or braced in accordance with State and local safety

requirements. Excavation and related work shall be performed such that no portion of

the wall is endangered by subsequent operations.

Where excavation for the wall requires shoring, sheeting, or bracing, the method

shall be shown on the working drawings. Excavation operations shall not begin until

the Contractor receives notice that the working drawings are approved.400

After the excavation for the wall has been performed, the Contractor shall notify

the Engineer. The material beneath the leveling pad shall be compacted in accordance

with 203. Concrete for the leveling pad shall not be placed until the Engineer has

approved the depth of the excavation and the foundation material. The leveling pad

shall be in accordance with 731.07.

When an internal drainage system is shown on the plans, the drain pipe shall be 6

in. underdrain pipe in accordance with 715.02(d). The remainder of the internal

drainage system shall be in accordance with 718, longitudinal underdrains. Video410

inspection will not be required.

731.09Wall Erection

Concrete face panels shall be handled by means of a lifting device set into the

upper edge of each panel. Panels shall be placed in successive horizontal lifts in the

sequence shown on the plans as backfill placement proceeds. As backfill material is

placed behind the panels, the panels shall be maintained in vertical position by means

of temporary wooden wedges placed in the joint at the junction of the two adjacent

panels on the external side of the wall. External bracing will be required for the initial

lift.420

731.09

838

Panels shall be stored on blocking to minimize contact with the ground or being

covered by standing water. Panels placed in contact with the ground or covered by

standing water shall have face discoloration removed by means of a chemical wash.

Plumb, vertical tolerances, and horizontal alignment tolerances shall not exceed

3/4 in. as measured with a 10 ft straightedge. The maximum allowable offset in panel

joints shall be 3/4 in. For a wall of over 10 ft height, the overall plumb from top to

bottom of the wall shall not exceed 0.05 in./ft of wall height.

430

For aesthetic considerations and to make differential settlement unnoticeable, the

panels shall be erected such that the horizontal site line is discontinuous at every other

panel. This shall be accomplished by starting erection with the lower panel level of

each wall by alternating full-height and half-height panels. Panels above the lowest

level shall be of a uniform size, except as required to top out the wall, to be in

accordance with the plan elevations.

The Contractor shall perform the necessary work to verify that the foundation is

at the correct elevation, that the wall is constructed to the correct alignment, and that

the work is in accordance with the specified tolerances. The checking of alignments440

and tolerances shall include verifying that the plumb of the face panels is in accordance

with 731.10 over the entire height of the wall. Alignment shall be checked at each

layer of panels after the backfill behind the panels has been compacted, and the results

shall be recorded.

The connections of the ground reinforcement to the panels shall be in two

elevations for full height panels. The connections shall not be more than 30 in.

vertically apart. To prevent out-of-plane rotation, full height face panels shall be

connected to the ground reinforcement on at least three different points in two different

planes. However, a preapproved system utilizing a horizontal stabilizing leg to prevent450

rotation shall require only ground reinforcement attachments in one plane. Partial size

panels shall have three different connection points, but only one plane shall be attached

to the ground reinforcement. Panels located at the top of the wall shall not be attached

to the coping or traffic barrier.

Ground reinforcement shall be placed normal to the face of the wall, unless

otherwise shown on the plans or as directed. Prior to placement of the ground

reinforcement, backfill shall be compacted in accordance with 731.11.

731.10Joint Spacers and Joint Covering for Wall Panels460

Horizontal and vertical joint spacers shall be provided between adjacent face

panels to prevent concrete-to-concrete contact and chipping if differential settlement

occurs. Panels without an uninterrupted vertical joint shall have a minimum joint

thickness of 3/4 in. Joint covering shall be provided and attached to the rear face of

the panels. Geotextiles used to cover the joint behind the MSE wall facing panels shall

be in accordance with 918.02(a), Type 2B.

731.10

839

731.11Backfill Placement

Backfill placement shall follow erection of each course of panels and ground

reinforcement. All sheeting and bracing shall be removed as the backfilling progresses.470

Backfill shall be placed to avoid damage or disturbance to the wall materials or

misalignment of the concrete face panels. All material for backfill shall be subject to

approval and shall be free from lumps, wood, or other undesirable material. Wall

materials that become damaged or disturbed during backfill placement shall be

removed and replaced or corrected as directed. All misalignment or distortion of the

concrete face panels due to placement of backfill outside the limits described herein

shall be corrected as directed.

B borrow shall be compacted in accordance with 203.23 or 203.24. For structure

backfill Type 3, compaction shall consist of five passes with a vibratory roller and one480

pass with the same roller in static mode. Compaction equipment shall be in accordance

with 409.03(d). All displacement or rutting of the aggregate shall be repaired prior to

placing subsequent material.

The maximum loose lift thickness shall not exceed 9 in. However, lifts within 3

ft of the wall shall not exceed 5 in. in loose thickness. This lift thickness shall be

decreased, if necessary, to obtain the specified density.

Compaction within 3 ft of the back face of the concrete face panels shall be

achieved by means of a minimum of five passes with a lightweight mechanical tamper,490

roller, or an alternative vibratory system.

At the end of each day's operation, the last level of backfill shall be sloped away

from the wall units. Surface runoff from adjacent areas shall not enter the wall

construction site.

Subsurface drainage for the pavement section shall be underdrains for MSE walls

and shall be as shown on the plans.

Cutting or altering of ground reinforcement in the field shall not be performed500

unless one of the alternatives in Article 11.10.10.4 of the AASHTO LRFD Bridge

Design Specifications is followed and a compensating adjustment is made in the wall

design. All adjustments shall be shown on revised working drawings, signed by, and

shall bear the seal of a professional engineer, and submitted to the Engineer for

approval. Cutting shall be considered only if adequate additional ground reinforcement

is provided to produce the required strength shown in the approved calculations. If the

ground reinforcement is shortened in the field, the cut ends shall be covered with a

galvanized paint or coal tar to prevent corrosion of the metal.

731.12Method of Measurement510

The measurement of concrete face panels and wall erection will be based on the

square foot of area contained within the neat line limits of the wall envelope shown on

the plans and not that of the wall system supplier.

731.12

840

Concrete leveling pad will be measured by the linear foot. Common excavation

will be measured by the cubic yard in accordance with 203.27(a) to the neat lines

shown on the plans. Structure backfill and B borrow will be measured in accordance

with 211.09. Unsuitable foundation materials, if found, will be measured in

accordance with 211.09. Geotextile used in conjunction with MSE wall construction

will not be measured for payment. Underdrains for MSE walls and components of the520

internal drainage system will be measured in accordance with 718.09. If unsuitable

foundation material is encountered in the portion of the foundation beneath the

leveling pad in a section constructed on original ground or in a cut section, the removal,

replacement, and compaction of the new material will be measured in accordance with

203 and 211.

Precast or cast-in-place concrete coping will not be measured.

731.13Basis of Payment

The accepted quantities of concrete face panels will be paid for at the contract unit530

price per square foot. Wall erection will be paid for at the contract unit price per square

foot. Concrete leveling pad, complete and in place, will be paid for at the contract unit

price per linear foot for leveling pad. Common excavation will be paid for in

accordance with 203.28. Structure backfill and B borrow will be paid for in accordance

with 211.10, except that structure backfill used in the retained backfill zone will be

paid for as B borrow. Unsuitable foundation materials, if found, will be paid for in

accordance with 211.10. Underdrains for MSE walls and components of an internal

drainage system will be paid for in accordance with 718.10.

Payment will be made under:540

Pay Item Pay Unit Symbol

Face Panels, Concrete ................................................................ SFT

Leveling Pad, Concrete ............................................................. LFT

Wall Erection ............................................................................. SFT

The cost of designing the wall system, services including the testing laboratory,

certified testing personnel, and the testing and inspection of the concrete panels shall

be included in the cost of face panels, concrete.550

The cost of all wall materials including concrete face panels, ground

reinforcement, tie strips, fasteners, joint materials, joint covering, precast or cast-in-

place concrete coping, repair or replacement of face panels damaged or removed due

to backfill placement, and incidentals shall be included in the cost of face panels,

concrete.

731.13

841

The cost of all labor and materials required to prepare the wall foundation, place

the ground reinforcement, and erect the concrete face panels shall be included in the

cost of wall erection.560

If unsuitable foundation material is encountered in the portion of the foundation

beneath the reinforced backfill zone in a section constructed on original ground or in

a cut section, the cost of removal, replacement, and compaction of new material will

be paid for in accordance with 203 and 211.

If unsuitable foundation material is encountered in the portion of the foundation

beneath the reinforced backfill zone that is constructed on an embankment section that

is constructed under the same contract, the cost of removal, replacement, and

compaction of new material will not be considered for payment.570

The cost for geotextile used in MSE wall construction shall be included in the cost

of the pay items in this section.

The cost of refilling and refinishing of the core holes from verification coring shall

be included in the cost of face panels, concrete.

The cost of performing the laboratory tests by a qualified geotechnical consultant

for structure backfill or ACBF slag shall be included in the cost of the pay items in

this section.580

The cost of cutting, altering, or recoating the ground reinforcement at the site shall

be included in the cost of wall erection.

Get an email when 731 changes

Indiana revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Indiana Standard Specifications, 2024 Edition. Pages 844–0 of 1,248. View official source ↗

Ask about this section

Scoped to Indiana 2024 INDOT Standard Specifications, Section 731 — MECHANICALLY STABILIZED EARTH RETAINING WALLS. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.