722.01Description
This work shall consist of the surface preparation and construction of a bridge deck overlay consisting of latex modified portland cement concrete, LMC, latex modified concrete very early strength, LMC-VE, or silica fume modified concrete, SFMC, on an existing or new bridge deck, or it shall consist of patching an existing concrete overlay on a bridge deck in accordance with 105.03.
722.02Quality Control 10
LMC-VE overlays shall be placed in acco rdance with the QCP, which shall be prepared and submitted in accordance with ITM 803. The QCP shall include the Contractor’s experience placing LMC-VE over lays within the last three years. The QCP shall be submitted to the Engineer at least 14 days prior to commencing the overlay operation. Work shall not begin until written notice has been received that the QCP was accepted by the Department’s Division of Materials and Tests.
MATERIALS
722.03Materials 20
Materials shall be in acco rdance with the following:
Admixtures .................................................................. 912.03 Coarse Aggregate, Class A or Higher, Size No. 11* ... 904.03 Epoxy Resin Adhesive ................................................ 909.11 Fly Ash ........................................................................ 901.02 Latex Modifier ............................................................. 912.04 PCC Sealer/Healers ..................................................... 901.06 Portland Ceme nt .......................................................... 901.01(b) 30 Rapid Hardening Hydraulic Cement ........................... 901.01(d) Silica Fume .................................................................. 901.04 Water ........................................................................... 913.01 * Crushed stone only.
Evaporation retardant shall be a product that produces a monomolecular film. A Type D certification in accordance with 916 shall be provided for the evaporation retardant.
Citric acid shall be marked “food grade” on the packaging. 40
722.04Storage and Handling of Materials
Fine and coarse aggregates shall be stored and handled avoiding contamination and maintaining uniform moisture content. Fine and coarse aggregates which are stored in piles or bins shall remain separated and shall be covered with a moisture proof material which prevents variations in moisture content of the aggregates. The maximum variation of moisture content in successive concrete batches shall be 0.5%. 722.01
Cement shall be shipped and stored in accordance with 702.04 and 901.01.
The latex modifier, liquid silica fume sl urry, and dry condensed silica fume shall be stored in accordance with the manuf acturer’s recommendations. Latex modifier shall be strained to remove solid particles during transfer of the material from storage drums to the mobile mixer tank.
722.05Proportioning
A mix design shall be submitted a minimum of 14 days prior to use and calibration of the mobile mixer in accordance with 72 2.09. The proportioning of the ingredients 60 for the LMC shall be in accordance with 702.05 except as modified herein.
The amount of fine aggregate shall be 60% ±5% by dry weight of the total aggregate and shall be considered as the amount of aggregate blend passing the No. 4 (4.75 mm) sieve. The coarse aggregate sh all be No. 11, class A crushed stone. The cement content shall be a minimum of 658 lb/cu yd of concrete. The same brand of cement shall be used throughout a bridge structure. The amount of latex modifier shall be 3.5 gal. per 94 lb of cement. The net water added shall produce a slump of 5 in. ±1 in. at 4 to 5 minutes after discharge from the mixer. The moisture content of the aggregates shall be controlled such that the slump is within the specified limits. The 70 maximum water/cement ratio shall be 0.400 including the water in the latex. The air content shall be a maximum of 6%, by volume, of the plastic mix.
The yield will be checked using the 1/4 cu yd box method as follows. The chute shall be cleaned and the box shall be posi tioned to receive the discharged concrete. The mixer shall be operated until the cement counter indicates that 1/4 cu yd of concrete has been produced. The contents of the box shall be consolidated and struck off. Where the box is not essentially full, the gates shall be adjusted and the procedure shall be repeated until the actual and calculated volumes of concrete agree. Yield tests shall be run on the first load of each truck and every third load per truck thereafter. 80 The air content shall be tested on the first load of each truck prior to placing concrete onto the deck. Additional tests will be required after making any adjustments.
Slump and air content tests will be perf ormed after each acceptable yield test. The slump test shall be in accordance with AASHTO T 119 and will be performed 4 to 5 minutes after the concrete is discharged from the mixer. The water flow meter reading will be recorded at the time the slump test is taken. The concrete shall not be disturbed during the waiting period for the slump test. The air content test shall be in accordance with 505. Any concrete mixture which is not properly proportioned or does not conform to the specified slump will be rejected. 90
Class F or class C fly ash may be used in the latex modified portland cement concrete. The maximum cement reduction shall be 15% and the minimum replacement 722.05
ratio by weight of fly ash to cement shall be 1.25:1. Where portland pozzolan cement, Type IP is to be used in the concrete mix design, the cement content shall be increased by a multiplier of 1.06 times the specified cement content.
Proportioning of ingredients for LMC-VE shall be in accordance with 722.05(a) except as follows. 100
Cement shall be a rapid hardening hydraulic cement. Fly ash or other pozzolanic materials shall not be used. Citric acid ma y be used as a retardant. The maximum content of citric acid shall be 1% of the cement weight. The minimum compressive strength shall be 2,500 psi at 3 h and 3,500 psi at 24 h. The net water added shall produce a minimum slump of 7 in. and maximum slump of 10 in. at 4 to 5 minutes after discharge from the mixer. The maximum water-cement ratio shall be 0.440 including the water in the latex.
A trial batch shall be produced to verify that the mix design complies with the physical properties specified, as well as, simulating the placement properties unique to the conditions of the contract such as profile grade, cross slope, delivery time, discharge rate, slump loss with time, air content and target compressive strength. All testing of the trial batch concrete shall be performed by an ACI certified concrete field testing technician, grade I.
The trial batch demonstration shall include a meeting between the Contractor, material suppliers, and Department to discuss LMC-VE, mixing, delivery, placement, finishing, curing, and compressive testing. Representatives from the rapid hardening 120 cement manufacturer shall be present for tr ial batch demonstrations and the start-up for initial bridge deck placement. The Department’s Division of Materials and Tests may waive the required atte ndance for these representatives where the Contractor provides sufficient evidence of adequate experience with producing and placing LMC- VE. The trial batch demonstration may be conducted in conjunction with calibration of the mobile mixer in accordance with 722.13.
A CMDS shall be submitted a minimum of 14 days prior to the trial batch utilizing the Department provided spreadsheet. The proportioning of ingredients for each batch of SFMC shall be in accordance with 702.05 except as modified below and shall meet the mix design, trial batch demonstration, and job-use requirements as specified.
The portland cement content shall be 658 lb/cu yd. Silica fume shall be added at 50 lb/cu yd.
722.05
The SFMC shall utilize a Type F or G admixture to be combined with an air- entraining admixture, AEA, a HRWR admixture system or a HRWRR admixture 140 system and shall be selected from the QPL of PCC Admixtures and Admixture Systems.
The water/cement ratio shall be no less than 0.370 and shall not exceed 0.400. Portland cement and silica fume shall be included in the total amount of cementitious material.
The same brand of cement and silica fume shall be used throughout the structure. The HRWR or HRWRR admixture system shall not be changed during any individual contiguous pour. 150
The Contractor shall obtain a written st atement from each admixture manufacturer stating the compatibility of the HRWR admixture system and satisfactory performance in SFMC.
The SFMC shall have a relative yield and air content in accordance with 702.05. The slump will be tested in accordance with AASHTO T 119 at the time of placement and shall be at least 4 1/2 in. but shall not exceed 7 1/2 in. The SFMC shall have a minimum compressive strength of 4,500 psi at 7 days and 5,500 psi at 28 days. The compressive strength shall be in accordance with 702.24. 160
A trial batch shall be produced to verify that the mix design complies with the physical properties specified, as well as simulating the placement properties unique to the conditions of the contract such as profile grade, cross slope, delivery time, discharge rate, slump loss with time, air co ntent, and target compressive strength. All testing of the trial batch concrete shall be performed by an ACI certified concrete field- testing technician, grade I.
The trial batch demonstration shall include a meeting between the Contractor, 170 material suppliers, and Department to discuss SFMC, batching, mixing, delivery, placement, finishing, curing, and compressive testing. Representatives from the silica fume and chemical admixture manufacturer shall be present for trial batch demonstrations and the start-up for initial bridge deck placement. The Department’s Division of Materials and Tests may waive the required attendance for these representatives where the Contractor pr ovides sufficient evidence of adequate experience with producing and placing SFMC.
Batching shall be in accordance with 702.06 except the minimum batch shall be 180 4 cu yds and the maximum shall not exceed 80% of the truck rated capacity. Dry condensed silica fume shall be either sacked or bulk and it shall be batched in accordance with the requiremen ts for cement as specified in 702.06. No partial sack of dry condensed silica fume shall be used in a batch of SFMC. Dry condensed silica 722.05
fume shall be typically added after the initial water and aggregates, with premixing prior to the addition of cement and fly ash, to facilitate dispersion. An alternate batching sequence will be allowed as recommended by the manufacturer of the silica fume and as approved by the Engineer. Liquid silica fume slurry shall be batched as required by the manufacturer and as approved by the Engineer. The AEA shall be added initially with either the first portion of mix water or the fine aggregate. Where 190 a Type A or Type D chemical admixture is used as part of the HRWR admixture system, it shall be added separately with a portion of the mix water, after the AEA is premixed in the concrete. A Type F or Type G chemical admixture shall be added separately at the end of the batching sequence with some mix water held in reserve to aid dispersion.
.
A change in the sequence of batching may be approved if it is in accordance with
the chemical admixture and silica fume manufacturer’s recommendations and is
agreed to in writing prior to any trial batch demonstration.
200
722.06Preparation of the Bridge Floor
When an existing deck overlay is to be removed, the removal shall be performed
with a milling machine. The milling shall include the depth of the existing deck overlay
and an additional depth as shown on the plans. If no additional depth is shown on the
plans, the additional depth shall be 1/2 in. Removal in areas that are inaccessible to the
milling machine, shall be performed by chipping hammers or handchipping in
accordance with 722.06(b)3.
210
When an existing concrete deck without an overlay surface is to be removed, the
removal shall be performed with a milling machine. The milling shall be to a depth
shown on the plans. If no depth is shown on the plans, the milling shall be 1/2 in.
depth. The surface removal operation shall be limited to that portion of the bridge deck
that is closed to traffic at any one time. After this initial surface removal, additional
milling may be required as directed.
220
The milling machine shall uniformly remove the required depth of concrete
surface in a satisfactory manner. Surface removal in areas adjacent to the curb that are
inaccessible to milling, shall be done by handchipping in accordance with 722.06(b)3.
All surface removal residue, including water, dust, and concrete, shall be immediately
removed.
Where the milling operation results in the snagging of the top mat of steel
reinforcing bars, the milling operation shall cease and the depth of removal adjusted.
Damaged reinforcing bars shall be repaired as directed with no additional payment.
230
722.06
777
When shown on the plans, removal of unsound concrete shall be performed by
hydrodemolition. Following the cleanup from the surface removal operation, areas of
unsound concrete to be removed will be marked. The hydrodemolition equipment shall
consist of a self-propelled computerized machine that utilizes a high pressure water jet
stream capable of removing concrete as specified, as well as removing rust and
concrete particles from exposed reinforcing bars.
Prior to hydrodemolition, the equipment shall be calibrated on an area of sound
original deck concrete as designated by the Engineer. Calibration shall be performed240
at the bottom depth of the overlay shown on the plans.
The initial settings shall be verified on an area of unsound concrete. This area
shall not contain existing patches. The initial settings shall be adjusted to achieve total
removal of unsound concrete within the verification area. Equipment shall be
calibrated at each project bridge deck prior to operation. Where directed, equipment
shall be recalibrated to ensure removal of known areas of unsound concrete and to
guard against removal of sound concrete. The Engineer shall be notified of the final
equipment settings resulting from the calibration process.
250
After calibration of the equipment, concrete removal by hydrodemolition shall be
performed on the bridge deck. The removal will be verified as necessary, every 30 ft
along the cutting path. Handchipping shall be used in areas that are inaccessible to the
hydrodemolition equipment. Handchipping tools may be handheld or mechanically
driven. The removal operation shall cease where it is determined that sound concrete
is being removed. Equipment shall be recalibrated, or approved changes to equipment
and methods shall be performed, prior to resuming the removal operation.
The Contractor shall submit a wastewater control and disposal plan for approval
seven days prior to commencing hydrodemolition activities. The wastewater control260
and disposal plan shall detail how all wastewater generated by the hydrodemolition
activities shall be contained, tested for pH, stored, and transported to a disposal facility
in accordance with 202.
The Contractor shall provide sufficient shielding to ensure containment of all
dislodged concrete during hydrodemolition operations and to prevent damage to
surrounding property from flying debris, both on and under the work site.
Cleaning of the hydrodemolition debris and slurry shall be performed with a
vacuum system equipped with fugitive dust control devices and be capable of270
removing wet debris and water in the same pass. The vacuum equipment shall be
capable of washing the deck with pressurized water during the vacuum operation to
dislodge all debris and slurry from the bridge deck surface. Debris and slurry shall not
be allowed to dry prior to vacuuming.
After hydrodemolition has been completed, the deck will undergo sounding to
722.06
778
identify remaining areas of unsound concrete. Ponded or standing water shall be
removed from the deck prior to sounding.
Additional concrete removal of remaining unsound concrete shall be as directed280
by the Engineer and shall be performed by handchipping or hydrodemolition.
When hydrodemolition is not shown on the plans, all removal of unsound concrete
shall be performed by handchipping. Following the cleanup from the surface removal
operation, areas of unsound concrete to be removed will be marked. Handchipping
tools may be hand or mechanically driven. Jackhammers shall not be heavier than
nominal 45 lb class and chipping hammers shall not be heavier than nominal 15 lb
class. Only chipping hammers shall be used when removing concrete within 1 in. of
reinforcing bars. Mechanically driven tools shall be operated at a maximum angle of290
45° from the bridge floor surface.
Regardless of the method of removal, the removal operation shall cease where it
is determined that sound concrete is being removed. Agreed upon changes in
equipment and methods shall be performed prior to resuming the removal operation.
Where reinforcing bars have been exposed for a length greater than 2.0 ft and the
bond between the existing concrete and reinforcing bars has been destroyed, the
concrete adjacent to the bars shall be removed to a minimum clearance of 1 in. around300
the entire periphery of the exposed bars.
Regardless of the method used for unsound concrete removal, where the deck is
unsound for more than 1/2 of its original depth, the concrete shall be removed full
depth, except for limited areas as determined by the Engineer. Forms for areas of up
to 4 sq ft may be suspended from wires attached to the reinforcing bars. For areas
greater than 4 sq ft, the forms shall be supported from the structural members of the
superstructure or by shoring from below.
310
Prepared cavities which are deeper than the level of the adjacent prepared deck
surface, but are not full depth, shall require partial depth patching in accordance with
722.07(b). Prepared partial depth cavities shall be made full depth when directed
Exposed reinforcing bars shall not be damaged by the removal operation. Any
damaged reinforcing bars shall be repaired as directed with no additional payment.
The removal areas shall be thoroughly cleaned of all dirt, foreign materials, and
loose concrete to the extent necessary to produce a firm solid surface for adherence of
the new concrete. A minimum 1 in. vertical surface shall remain, or be cut, 1 in. outside
and around the entire periphery of each removal area after removal of all loose and320
unsound concrete. The 1 in. vertical cut may be waived where it is determined that a
722.06
779
cut will damage the reinforcing bars. Where hydrodemolition is utilized on the
adjacent surface, the 1 in. vertical surface will not be required.
After the concrete removal operation is completed and just prior to placing the
patches or the overlay, the entire deck shall be heavily sandblasted to expose fine and
coarse aggregates and to remove unsound concrete or laitance layers from the surface.
Exposed reinforcing bars and the concrete under and around the exposed bars shall be
thoroughly cleaned by sandblasting. The surface shall be then cleaned free of all dust,330
chips, water, and foreign material to the extent necessary to produce a firm, solid
surface for adherence of the new concrete.
The air lines for sandblasting and air cleaning shall be equipped with oil traps.
When hydrodemolition is utilized, water blasting may be used in lieu of
sandblasting. The sandblasting or water blasting shall be performed using two passes
with the second pass being at a right angle to the first pass or a cross-blasting
technique. The minimum pressure of the water blast shall be 6,000 psi.
340
Patching of the Bridge Floor
A vacuum device shall be used to remove all water from the prepared cavities.
The material used for full depth patching shall be either bridge deck patching
concrete, overlay concrete, or concrete patching material from the QPL of Rapid
Setting Patch Materials.
Full depth patching shall be performed prior to the overlay operation. The
patching material shall be consolidated by internal vibration at the time of placement.350
Equipment shall not be operated on the repaired deck areas until the test beams indicate
a minimum modulus of rupture of 550 psi.
Epoxy resin adhesive shall be used to coat the surfaces of the prepared cavities
and all the exposed reinforcing bars within the cavities. The epoxy coating shall be
tacky at the time that the patching concrete is placed. Where the epoxy coating has
cured beyond the obvious tacky condition, it shall be re-applied prior to patching. The
coated cavities shall then be filled with the patching concrete to the level of the
adjacent deck surface. Curing of the patching concrete shall be as directed.360
Bridge deck patching concrete shall be composed of the following:
aggregate used.
722.07
780
III or Type IIIA, or 846 lb/cu yd of portland cement Type I
or Type IA.
370
8% entrained air.
6 in. and a maximum water/cement ratio of 0.450.
The surfaces of the prepared cavities shall be coated with a bond coat in
accordance with 722.10. The cavities shall then be filled with the overlay concrete to
the level of the adjacent deck surface.380
Concrete patching materials shall be as approved by the overlay supplier for
compatibility with the overlay material. Concrete patching materials shall be placed
and cured in accordance with the manufacturer’s recommendations.
The material used for partial depth patching shall be either bridge deck patching
concrete, overlay concrete, or concrete patching material from the QPL of Rapid
Setting Patch Materials. The patching material shall be consolidated by internal390
vibration at the time of placement.
Partial depth patching with bridge deck patching concrete shall be in accordance
with 722.07(a) and 722.07(a)1. Curing of the patching concrete shall be as directed.
The surfaces of the prepared cavities shall be coated with a bond coat in
accordance with 722.10, except where hydrodemolition is utilized. The cavities shall
be filled with the overlay concrete at the time that the overlay is placed. Concrete400
overlay material used for patching shall be cured in accordance with 722.12.
Concrete patching materials shall be as approved by the overlay supplier for
compatibility with the overlay material. Concrete patching materials shall be placed
and cured in accordance with the manufacturer’s recommendations.
722.08Overlay Dam
An overlay dam shall consist of the removal of existing concrete from the bridge
floor and replacing it with new concrete as shown on the plans or as otherwise directed.410
Overlay dam material shall be in accordance with 722.05.
722.08
781
The existing concrete shall be removed as required in accordance with 722.06(b).
Exposed reinforcing bars shall not be cut or otherwise damaged.
Power driven hand tools for removal by handchipping will be allowed. Pneumatic
hammers with a maximum weight of 69 lb may be used for the tops of mudwalls.
Where, during the removal process, the tools or methods being used appear to cause
damage such as cracks or spalling on the concrete which is to remain, the work shall
cease immediately and agreed upon changes in equipment and methods shall be420
performed prior to resuming the removal operation.
The surface to be repaired, the reinforcing bars, and the concrete under and around
the bars shall be cleaned in accordance with 722.06(c). The cavity shall be coated with
an epoxy resin adhesive in accordance with 722.07(a)1, then filled with class C
concrete in accordance with 702.
722.09Mixing
Very Early Strength
Proportioning and mixing of the latex modified concrete shall be performed in a
self-contained, self-propelled continuous mixer. The mixer shall be calibrated to
accurately proportion the specified mix prior to starting the work. The calibration shall
be in accordance with 722.13. Sufficient mixing capacity or mixers shall be provided
to enable the intended pour to be placed without interruption. The mixer shall carry
sufficient quantities of unmixed ingredients to produce at least 6 cu yds of latex
modified concrete at the site.
The mixer shall measure and control the flow of ingredients being introduced into440
the mix and shall record these quantities on an approved visible recording meter
equipped with a ticket printer. Water flow shall be readily adjustable to compensate
for minor variations in aggregate moisture content and shall be displayed by an
approved flow meter. The flow of the latex modifier shall also be displayed by an
approved flow meter. The manufacturer’s inspection plate shall clearly show the serial
number, proper operating revolutions per minute, and the approximate number of
counts on the cement meter to deliver 94 lb of cement.
The mixer shall automatically proportion and blend simultaneously all the
ingredients of the specified mix on a continuous or intermittent basis as required by450
the finishing operation. The latex modified concrete shall be discharged through a
conventional chute directly in front of the finishing machine. The surface ahead of the
deposited mixture shall be kept damp by spraying it with water. Where the water is
applied by the mixer, it shall be dispensed ahead of the water flow meter.
Mixing shall be in accordance with 702.09(a), 702.09(b), and 702.09(c), except
mixing time shall be a minimum of 84 s. Retempering SFMC by adding water or by
722.09
782
other means will not be allowed after 30 minutes from initial batching and mixing.
When concrete is delivered in transit mixers, additional water may be allowed to460
increase a marginally low slump. Water shall not be added once 10% of the load has
been discharged. Additional mixing shall be performed as directed and all operations
completed within the time limits in accordance with 702.09(c). The amount of water
shall be determined accurately and noted on the batch ticket. Such addition of water
will not be allowed as a continuing operation. The total of all water included in the
mix shall not exceed the maximum allowable water/cement ratio.
722.10Placing and Finishing
Existing expansion joints shall be maintained throughout the overlayment unless
otherwise shown on the plans. A construction dam or bulkhead, equal in thickness to470
the joint width, shall be installed to the required grade and profile prior to placing the
overlay. Screed rails for the finishing machine shall be placed to the required profile,
and anchored for stability both vertically and horizontally. Screed rails shall not be
treated with a bond breaking compound.
The overlay shall be placed only when the ambient temperature is 45°F and rising,
unless otherwise approved by the Department in writing. The maximum allowable
ambient temperature during placement is 85°F. The overlay shall not be placed if rain
is expected within 4 h. Adequate precautions shall be taken to protect freshly placed
overlay material from sudden or unexpected rain. Damaged material shall be removed480
and replaced with no additional payment. A construction dam or bulkhead shall be
installed in case of a delay in placement of 1 h or more. During delays of less than 1 h,
the end of the placed overlay material shall be protected from drying with layers of
wet burlap.
After the surface has been cleaned, and immediately before placing the overlay
material, the surface shall be thoroughly soaked and covered with plastic sheeting for
a period of 1 h. The surface shall not be allowed to dry before placing the overlay
material and there shall be no standing water at the time of placement. The surface
shall then be thoroughly and evenly coated with a brush applied bond coat of overlay490
concrete, except a bond coat shall not be applied to surfaces where the removal was
performed by hydrodemolition. The progress of the bond coat application shall be
controlled to ensure that the bond coat does not dry before the overlay is placed to the
required grade. Aggregate segregated in the brush application of the bond coat shall
be removed before the overlay is placed. Surface irregularities shall be filled to
approximately three-quarters of their depth sufficiently ahead of the overlay operation
to allow the material to stiffen and resist rolling back during the finishing.
Following the bond coat application and partial filling of any surface
irregularities, the concrete overlay shall be placed to an elevation approximately 1/2500
in. above final grade. The mix shall then be consolidated and machine finished to the
required grade. The machine finishing shall be to within 12 in. of the curb line or
coping line unless otherwise directed. Supplemental hand finishing with a wood float
shall be performed as needed to produce the required tight and uniform surface.
722.10
783
The finishing machine shall be self-propelled and capable of positively controlled
forward and reverse motion. The machine shall be equipped with at least two finishing
devices. The first finishing device shall be a vibrating mechanism, such as a vibrating
pan, for consolidating the deposited mix. The vibrating pan shall be metal and of
sufficient dimensions to ensure proper consolidation. The second finishing device510
shall be either a rotating cylindrical drum, at least 45 in. in length, or a vibrating
oscillating metal faced screed of 4 in. minimum in width. The vertical position of the
finishing devices shall be positively controlled and the devices shall be raised clear of
the finished surface when the machine is operated in the reverse direction. The
vibration frequency of any vibrating finishing device shall be variable, with positive
control between 3,000 and 6,000 vibrations per minute. Alternate finishing machines
may be considered for approval subject to a written request.
Screed rails and construction dams shall be separated from the newly finished
overlay by passing a pointing trowel along the rail-to-overlay and dam-to-overlay520
interfaces after the overlay has sufficiently set such that it does not flow back. This
trowel cut shall be made for the entire length and depth of the rail or dam. The rails
may be removed any time after the overlay has initially set. Adequate precautions shall
be taken during and after the rail removal to protect the edge of the new overlay from
damage.
Protection shall be provided to prevent rapid drying of concrete. The rate of water
evaporation shall be determined both prior to placement based on forecasted
conditions and during placement based on actual conditions in accordance with ACI
308, section 5.2.1 or the following equation:530
E = (T c 2.5 - rT a 2.5 )(1 + 0.4V) x 10 -6
where:
E = Evaporation rate, lb/sq ft/h
T c = Concrete mix temperature, °F
T a = Ambient temperature, °F
r = (Percent of Relative Humidity)/100
V = Wind velocity, mph.
Measurement of T a , r, and V shall be obtained from readings made by the local
weather bureau or the Contractor's measurements made on site. Measurement of T c
shall be determined from the concrete on site at the point of placement. Fog misting
shall be performed after the finishing operation and prior to the wet cure, where the
evaporation rate exceeds or is expected to exceed 0.05 lb/sq ft/h. Fog misting shall540
keep the environment above the concrete surface at high humidity to protect against
plastic shrinkage cracks and shall not be used to apply water directly to the surface to
facilitate finishing. Evaporation retardants shall not be substituted for fog misting
where the evaporation rate exceeds 0.05 lb/sq ft/h.
722.10
784
An evaporation retardant shall be applied in a fine mist immediately after the
finishing is complete to ensure that the surface remains wet until covered. The
evaporation retardant shall be used as such and not as a finishing aid. These products
consist primarily of water and excessive amounts of evaporation retardant shall not be
applied and the product shall not be worked into the overlay surface. Evaporation550
retardant shall only be used on SFMC overlays. Evaporation retardant shall not be
used in any other applications.
722.11Texturing
The overlay surface shall be textured with a double thickness burlap drag or a
minimum 4 ft wide turf drag immediately following the placement of the overlay
material. Areas where the texture is disturbed by other finishing operations shall be
immediately restored to a burlap drag finish.
Grooving or tining in the plastic concrete of the concrete overlay will not be560
allowed. Longitudinal grooving shall not commence until the curing requirements
have been met in accordance with 722.12. Grooves shall be cut into the hardened
concrete surfaces parallel to the centerline using a mechanical cutting device. For
curved bridges, grooves shall be cut along the curve chord within the spans. Grooving
shall be done before traffic is allowed on the surface except as follows.
The Contractor shall have the option of cutting the longitudinal grooves at the end
of each phase of construction or waiting until all phases have been completed. If the
Contractor elects to delay the grooving process until completion of all phases, the
concrete overlay surface for any phase opened to traffic shall receive an interim coarse570
broom finish during placement.
The completion of the grooving process shall be within 30 days of completion of
the last phase of construction. Any additional maintenance of traffic operations
required for the grooving process shall be included in the cost of Maintaining Traffic.
The interim broom finish shall not be allowed as a surface texture when opened to
traffic over a winter season. If the coarse broom texture is present and the Contractor
is not in a position to finish all phases of the project, longitudinal grooving shall be
placed into the hardened concrete in order to establish an acceptable driving surface
texture for the winter season.580
Each groove shall be 1/8 in. ±1/64 in. in width, 3/16 in. ±1/16 in. in depth. The
grooves shall be uniformly spaced at 3/4 in. intervals measured from the center of
groove to center of groove. Grooving shall not be within the area approximately 2 ft
adjacent to the curbs or railings. The grooving shall not be cut closer than 3 in. nor
further than 6 in. from any construction joint running parallel to the grooving. The
grooving shall not be cut within 6 in. of deck drains, curbs, or expansion joints. If the
bridge has a variable width traffic lane, the grooving shall remain parallel to the
centerline of the main roadway. Any staggering of the groove terminations to
accommodate the variable width shall be within the shoulders. Stair stepped ends in590
grooving will be allowed for skewed bridge decks. When a new reinforced concrete
722.11
785
approach slab is placed adjacent to the overlay, the grooving shall extend across the
reinforced concrete approach slab. Grooving shall terminate approximately 6 in. from
the interface with the roadway pavement.
The grooving machine shall contain diamond blades mounted on a multi-blade
arbor on a self-propelled machine built for grooving hardened concrete surfaces. The
grooving machine shall have a depth control device that detects variations in the deck
surface and adjusts the cutting head height to maintain a specified depth of the grooves.
The grooving machine shall have a guide device to control multi-pass alignment.600
The Contractor shall submit a wastewater control and disposal plan for approval
seven days prior to commencing grooving activities. The wastewater control and
disposal plan shall detail how all wastewater generated by the grooving activities shall
be contained, tested for pH, stored and transported to a disposal facility in accordance
with 202.
Cleaning of the grooving debris and slurry shall be performed with a vacuum
system equipped with fugitive dust control devices and be capable of removing wet
debris and water in the same pass. The vacuum equipment shall be capable of washing610
the deck with pressurized water during the vacuum operation to dislodge all debris and
slurry from the bridge deck surface. Debris and slurry shall not be allowed to dry prior
to vacuuming.
722.12Curing
When fly ash is used, the requirement for additional wet or dry curing time shall
be determined based on the relative initial, and final time of set and a comparison of
strength versus age using control concrete strengths at conventional cure period ages
as the reference. The additional curing requirements shall be as approved by the
Engineer.620
For LMC overlays the minimum curing period shall be 48 h of wet cure followed
by 48 h of dry cure. An LMC overlaid bridge deck may be opened to traffic during the
dry curing duration when the compressive strength of cylinders is 4,000 psi or greater.
For SFMC overlays the minimum curing period shall be seven calendar days
consisting of 120 h of wet cure followed by 48 h dry cure. The deck shall remain
completely covered during the dry cure period. An SFMC overlaid bridge deck may
be opened to traffic after the dry cure period when the compressive strength of
cylinders is 4,500 psi or greater.630
For LMC-VE concrete overlays the minimum curing period shall be 3 h of wet
cure. An LMC-VE overlaid bridge deck may be opened to traffic after the wet curing
period when the compressive strength of cylinders is a minimum of 2,500 psi.
The wet cure period for all overlay types is not controlled by strength and shall
not be reduced. Membrane forming curing compound shall not be used to cure the
722.12
786
bridge deck overlay. All cylinders shall be 6 in. by 12 in. and compressive strength
shall be determined from the average of a minimum of two cylinders. For LMC and
SFMC, cylinders shall be cast and cured in accordance with 702.24. For LMC-VE640
cylinders shall be cast and field cured at the jobsite under the same conditions as the
LMC-VE overlay.
The plastic film which forms on the surface of the overlay shall be protected from
shrinkage cracking with a single layer of well drained wet burlap. This layer of wet
burlap shall be placed as soon as the overlay surface will support it without
deformation. The entire surface shall be covered with plastic sheeting and maintained
in a saturated wet condition during the wet cure period. A network of soaker hoses
shall be used under the plastic sheeting during the wet cure period for LMC and silica
fume overlays.650
When the ambient temperature falls below 50°F during either the wet or dry
curing periods, the time that the temperature is below 50°F shall not be considered as
part of the total curing period. When there is sufficient rain to wet the surface of the
overlay for 1 h or more during the dry cure period, this number of hours shall not be
considered as part of the dry cure period.
Immediately upon the start of the dry cure period or opening to traffic, the surface
shall be checked for cracks. Upon request, the Contractor shall flood the deck with
water to facilitate inspection for cracks and distress. Where cracks exist, a thorough660
investigation will be conducted prior to sealing cracks. Cores may be required to
determine the actual crack depth. Surface cracks not exceeding 3/8 in. in depth shall
be sealed with a PCC Sealer/Healer followed by an application of an approved sand.
Cracks exceeding 3/8 in. in depth shall not be sealed at this time. Corrective procedures
for repairing cracks exceeding 3/8 in. in depth will be determined after further
investigation which may include additional cores. The Department’s Division of
Materials and Tests will be contacted and the Engineer will determine the method of
repair including possible removal.
Where the area of shallow cracking exceeds 5% of the deck area, then the method670
of repair shall be the same as for cracks exceeding 3/8 in. The shallow crack area will
be calculated by multiplying the total combined linear feet of all cracks less than 3/8
in. deep by a tributary width of 1 lft. The percentage of deck area will be the shallow
crack area divided by the total deck area and multiplied by 100.
Where it is determined by sounding or coring that adequate bonding between the
overlay and the bridge deck has not been attained, the deficient areas shall be removed
and replaced as directed.
722.13Calibration of Continuous Mixers680
A complete calibration shall be performed for each mixer prior to each pour unless
722.13
787
the initial calibration was made within the previous 10 calendar days. A mixer that has
been calibrated within the previous 10 calendar days may be approved for use
providing that the mixer operator is in possession of the completed, signed, certified,
and dated Department calibration form for that mixer. A complete calibration of a
mixer may be required at any time as directed. All mixers which are calibrated within
the 10-day limit but are changing aggregate sources shall have an aggregate blend test
performed.690
All special equipment required for calibration shall be furnished. It shall include
but not be limited to suitable material containers, buckets, stop watches, and a scale
accurate to within 0.1 lb or 0.3% of the test load, whichever is greater, at any point
within the range of use. The minimum capacity of the scale shall be 150 lb. The scale
shall be verified annually per ITM 910. The Contractor shall provide paperwork that
shows the date the scale was verified by a company with NIST traceable class F
weights. Samples shall be obtained and handled by the Contractor. Normal testing
equipment such as aggregate sieves and containers shall also be furnished.700
The aggregate bin shall be clean and the bin vibrators shall be in good working
order. The mixer shall be equipped with a grounding strap. The cement meter feeder,
the fins, and all pockets shall be clean and free of any accumulated cement. The
aeration system shall be equipped with a gauge or indicator to verify that the system
is operating. The main belts and the latex strainer shall be clean and free of any
accumulated material.
The mixer manufacturer’s mix setting chart shall determine the specified
operating revolutions per minute and the approximate number of counts required on
the cement meter to deliver 94 lb of cement. At least 3,760 lb of cement shall be placed
in the cement bin.
The mixing unit shall rest on a level surface. The engine throttle shall be adjusted
to obtain the required revolutions per minute. The unit discharging the cement shall be
operated until the belt has made one complete revolution. The unit shall then be720
stopped and the cement meter shall be reset to zero.
A suitable container shall be positioned to catch the cement and at least 90 lb of
cement shall be discharged. The time required to discharge the cement shall be
measured with a stopwatch, the number of counts on the cement meter shall be
recorded, and the weight of the discharged cement shall be determined. This process
shall be repeated a total of three times. The cement counter shall be reset to zero before
each repetition.
722.13
788
The following formulas shall be used to calculate the number of counts per 94 lb730
of cement and the time required to discharge 94 lb of cement.
Counts per 94 lb of cement = 94 ÷ A
B
Time in seconds per 94 lb of cement = 94 ÷ A
C
where:
A = Total weight of cement in pounds for three trials
B = Total number of counts on the cement meter for three trials
C = Total time in seconds for three trials.
740
The accuracy of the water flow meter shall be verified by adjusting the flow to
2 gal. per minute. With the equipment operating at the required revolutions per minute,
the water discharged during a 1-minute interval shall be collected and weighed. The
weight in pounds of the discharged water shall be divided by 8.33 to determine the
number of gallons. This procedure shall be repeated with the flow meter adjusted to 3
gal. per minute.
The aggregate gate openings shall be adjusted to provide the required amount of750
aggregate to produce a cubic yard of the designated mix. The gate settings for the fine
aggregate and coarse aggregate shall be determined separately. Each aggregate shall
be verified by stopping the cement discharge and collecting the aggregate discharged
in a container.
Calculations for all aggregates shall be based on SSD weights taken from the mix
design. The calculations shall be adjusted for the tested moisture content. The final
gate setting for each aggregate shall dispense material within a tolerance of ±2% of
the target weights after adjustment for measured moisture content.
760
The latex strainer shall be unobstructed. The latex throttling valve shall be
adjusted to deliver the required amount of latex emulsion admixture for each 94 lb of
cement. With the unit operating at the required revolutions per minute for the
calculated time in seconds per 94 lb of cement, the latex shall be discharged into a
container. The weight of the latex shall be determined and, when necessary, the valve
shall be adjusted such that the amount of latex discharged is within 1/2 lb of the amount
required for each 94 lb of cement. One verification shall be performed to check the
accuracy of the valve setting.
770
This equipment shall be calibrated in accordance with the manufacturer’s
instructions for the specific materials and quantities involved.
722.13
789
722.14Patching an Existing Bridge Deck Overlay
Materials shall be in accordance with 722.03.
Storage and handling of materials shall be in accordance with 722.04.
Proportioning shall be in accordance with 722.05.
Preparation of the bridge floor shall be in accordance with the applicable
provisions of 722.06.
Patching shall be in accordance with 722.07 except as modified herein. Areas
repaired by full depth patching shall not be open to traffic until the test beams indicate
a minimum modulus of rupture of 550 psi.
Mixing shall be in accordance with the applicable provisions of 722.09.
Placing and finishing shall be in accordance with the applicable provisions of
. Machine finishing shall be required when directed.800
The surface texturing shall match the pattern of the adjacent overlay and shall be
in accordance with the following:
Immediately after the finishing is complete and before the surface film has
formed, the surface of the overlay patch shall be textured by grooving in the same
direction as the existing overlay. The grooves may be formed by mechanized
equipment using a vibrating beam roller, a series of discs, or other approved device.
Manual tools such as fluted floats, spring steel tined rakes, or finned floats with a810
single row of fins may be used. The grooves shall be relatively uniform, smooth, and
shall be formed without tearing the surface or bringing coarse aggregate to the top.
The grooves shall be in accordance with 504.03. The grooves shall be terminated the
same distance from the vertical faces of railings as the existing grooves in the adjacent
existing overlay surface.
All areas of hardened grooved overlay patching which do not conform to these
requirements, due to either a deficiency in the grooving or a rough open textured
surface, shall be corrected with no additional payment. Corrections shall be made by
cutting grooves in the hardened overlay with an approved cutting machine or by820
722.14
790
sealing with an approved mixture and retexturing to a satisfactory finish as directed.
Curing shall be in accordance with 722.12 when patching has been performed
using overlay concrete. Patches that have been constructed using bridge deck patching
concrete shall be wet cured until test beams indicate a minimum modulus of rupture
of 550 psi. Patches that have been constructed using rapid setting patch materials shall
be cured in accordance with the manufacturer’s recommendations.
Calibration shall be in accordance with 722.13.
722.15Method of Measurement
Removal of the existing overlay and the additional depth into the existing deck
surface will be measured by the square yard of deck area regardless of the number of
passes with the milling machine.
Removal of the existing concrete deck surface will be measured by the square
yard for the initial depth shown on the plans. Additional surface removal required
below the initial depth will be measured by the square yard for each required 1/4 in.840
depth. The areas of the bridge floor which are shown on the plans to be removed,
except for undefined full depth patching areas, will not be measured for payment.
Hydrodemolition of the bridge deck will be measured by the square yard.
Additional surface preparation around reinforcing bars will be measured by the linear
foot of exposed reinforcing bar. Reinforcing bar repair will not be measured for
payment.
When hydrodemolition is not shown on the plans, partial depth patching will be
measured by the square foot.850
The measurement of bridge deck patching concrete for partial depth cavities
created by handchipping or hydrodemolition will be based on a theoretical quantity
determined by multiplying the area of the appropriate partial depth cavities by an
assumed average depth of 2 in. and converting the resulting volume into cubic yards.
Overlay material used in a partial depth cavity will be measured by the cubic yard. The
quantities of patching material used in a partial depth cavity will be included in the
measurement of additional bridge deck overlay.
The overlay and bridge deck patching concrete used to fill cavities as part of860
patching an existing bridge deck overlay will not be measured for payment.
Overlay material used to fill surface irregularities and partial depth cavities will
be calculated by the cubic yard and will be included for payment for Bridge Deck
Overlay Budget.
722.15
791
Full depth patching will be measured by the square foot. The patching material
used in full depth patching will not be measured for payment.
Bridge deck overlay will be measured by the square yard for the specified870
thickness. Where there is no specified thickness shown on the plans, the specified
thickness shall be 2 in.
Overlay dams and patching an existing overlay will be measured by the square
foot.
Longitudinal grooving will be measured by the square yard. No deduction in
measurement will be made for areas where grooving is terminated or not required.
Epoxy resin adhesive and bond coat will not be measured for payment. Blasting,880
cleaning, finishing, texturing other than the longitudinal grooving, and curing will not
be measured for payment.
722.16Basis of Payment
Removal of the existing overlay and the additional depth into the existing deck
surface will be paid for at the contract unit price per square yard of bridge deck, remove
existing concrete overlay.
Milling of the initial depth of surface will be paid for at the contract unit price per
square yard of bridge deck, remove existing concrete surface. Additional surface890
removal below the initial depth will be paid for at the contract unit price per square
yard for bridge deck, remove existing concrete surface for each required 1/4 in. depth.
Hydrodemolition of the bridge deck will be paid for at the contract unit price per
square yard. When hydrodemolition is shown on the plans, additional surface
preparation will be paid for at the established price shown per linear foot for bridge
deck overlay, additional surface prep.
When hydrodemolition is not shown on the plans, partial depth patching will be
paid for at the contract unit price per square foot for bridge deck patching, partial900
depth.
When partial depth cavities are subsequently directed to be made full depth,
additional payment will be made at 80% of the contract unit price per square foot for
bridge deck patching, full depth.
Full depth patching will be paid for at the contract unit price per square foot for
bridge deck patching, full depth.
Bridge deck overlay will be paid for at the contract unit price per square yard, for910
the type of overlay material specified.
722.16
792
Patching an existing bridge deck overlay will be paid for at the contract unit price
per square foot for bridge deck overlay patching.
Overlay dam will be paid for at the contract unit price per square foot, complete
in place.
Longitudinal grooving will be paid for at the contract unit price per square yard.
920
The Department will include the pay item Bridge Deck Overlay Budget, with an
established dollar amount in the proposal to pay for additional surface preparation
completed after hydrodemolition and bridge deck overlay additional quantity used to
fill irregularities and partial depth cavities. The Bridge Deck Overlay Budget amount
shown in the proposal is included in the total bid amount. The Department will pay for
the additional quantity installed to fill irregularities and partial depth cavities as
directed by the Engineer. Where the material exceeds the planned overlay quantity,
payment will be at the invoice cost of the additional bridge deck overlay quantity
installed. An amount equal to 10% of the invoice cost will also be paid for additional
disposal and all other related costs in connection with the additional quantity installed.930
No additional markup shall be applied for additional bridge deck overlay quantity
installed. This amount will be paid using the Bridge Deck Overlay Budget pay item.
Payment will be made under:
Pay Item Pay Unit Symbol
Bridge Deck Overlay Budget .................................................... DOL
Bridge Deck Overlay, Latex Modified ...................................... SYS
Bridge Deck Overlay, LMC-VE ................................................ SYS940
Bridge Deck Overlay, Patching ................................................. SFT
Bridge Deck Overlay, Silica Fume Modified ............................ SYS
Bridge Deck, Remove Existing Concrete Overlay .................... SYS
Bridge Deck, Remove Existing Concrete Surface ..................... SYS
Bridge Deck Patching, Full Depth ............................................. SFT
Bridge Deck Patching, Partial Depth ......................................... SFT
Hydrodemolition ....................................................................... SYS
Longitudinal Grooving .............................................................. SYS
Overlay Dam ............................................................................. SFT
950
Item shown with an established price will be paid at the price shown.
Pay Item Pay Unit Established
Symbol Price
Bridge Deck Overlay, Additional Surface Prep......LFT ............... $20
The cost of overlay removal by handchipping in areas adjacent to the curb or
722.16
793
otherwise inaccessible to the power-operated mechanical milling machine shall be
included in the cost of bridge deck overlay, remove existing overlay. The cost of960
disposing of overlay removal residue, including water, dust, concrete and incidentals
shall be included in the cost of bridge deck, remove existing overlay.
The cost of deck surface preparation by handchipping in areas adjacent to the curb
or otherwise inaccessible to the power-operated mechanical milling machine shall be
included in the cost of bridge deck, remove existing concrete surface or bridge deck,
remove existing overlay. The removal of surface milling residue, including water,
dust, concrete, and incidentals shall be included in the cost of bridge deck, remove
existing concrete surface or bridge deck, remove existing overlay.
970
The cost of the wastewater control and disposal plan, wastewater containment,
testing, storing, transporting and disposal, and any incidentals related to the carrying
out of the plan shall be included in the cost of hydrodemolition. If the wastewater is
found to have a pH of 12.5 or higher and thereby classified as hazardous, the additional
costs associated with this classification will be paid for in accordance with 109.05.
The initial equipment calibration, any re-calibration, equipment shielding,
handchipping curb areas, handchipping unsound concrete, cleaning of debris and
slurry, compressed air cleaning, water blasting, and sandblasting shall be included in
the cost of hydrodemolition.980
When hydrodemolition is shown on the plans, the cost of removal of unsound
concrete shall be included in the cost of hydrodemolition. Preparation of cavity
surfaces, furnishing and applying bond coat or epoxy resin adhesive as required in
handchipped locations, furnishing and placing patching material, and necessary
incidentals shall be included in the cost of bridge deck overlay for the type of overlay
material specified. Additional concrete removal required around exposed bars shall be
included in the cost of additional surface preparation.
When hydrodemolition is not shown on the plans, the cost of removal of unsound990
concrete, preparation of cavity surfaces, furnishing and applying bond coat or epoxy
resin adhesive as required, furnishing and placing patching material, and necessary
incidentals shall be included in the cost of bridge deck patching, full depth, or bridge
deck patching, partial depth.
The cost of patching material used for full depth patching shall be included in the
cost of bridge deck patching, full depth. The cost of texturing patched areas will not
be paid for separately but shall be included in the cost of the patch.
The cost of furnishing and placing patching material in partial depth cavities and1000
necessary incidentals shall be included in the cost of bridge deck overlay, additional.
When the project does not include the installation of a new bridge deck overlay,
the cost of partial depth patching below the bottom of the overlay shall be included in
722.16
794
the cost of bridge deck overlay, patching. The cost of patching and overlay materials
used to fill the cavities shall be included in the cost of bridge deck overlay, patching.
The cost of removing existing concrete, furnishing, hauling, and placing all
materials including the epoxy, preparing the surface, and all necessary incidentals shall
be included in the cost of overlay dam.1010
The cost of deck cleaning shall be included in the cost of other pay items.
The cost of removing and disposing of the slurry created during the longitudinal
grooving shall be included in the cost of longitudinal grooving.
Coring of the bridge deck, patching core holes, and all corrective measures
required in accordance with 722.12 shall be performed at no additional cost to the
Department.