302.01 210 SECTION 302 – SUBGRADE TREATMENT (LIME)
302.01 De scription ................................ ................................ ................... 210
302.02 Reserved ................................ ................................ ....................... 210
302.03 Material s ................................ ................................ ...................... 210
302.04 Equipment ................................ ................................ .................... 211
302.05 Limitations ................................ ................................ ................... 212
302.06 Preparing the Existing Subgrade ................................ .................. 212
302.07 Extra Depth Stabilization ................................ ............................. 213
302.08 Applying Lime ................................ ................................ ............. 213
302.09 Initial Mixing and Mellowing ................................ ...................... 214
302.10 Final Mixing ................................ ................................ ................. 214
302.11 Compaction and Finishing ................................ ........................... 215
302.12 Curing ................................ ................................ .......................... 216
302.13 Tolerances and Reconstruction ................................ .................... 216
302.14 Method of Measurement ................................ .............................. 217
302.15 Basis of Payment ................................ ................................ .......... 219
DESCRIPTION
302.01 Description
This work consists of treating in -place subgrade material with lime, and includes preparing the existing subgrade, distributing the specified percentage of lime, initial mixing, mellowing, final mixing, compacting, finishing, and curing.
302.02 Reserved
MATERIALS
302.03 Materials
302.04 Equipment
302.05 Limitations
Handle and store lime in completely enclosed, moisture resistant containers until immediately before use. Store bagged lime in weatherproof buildings with adequate protection from ground dampness. Do not stabilize areas that will not be covered with the succeeding stage of sub-base or base construction during the same construction season. Do not apply lime:
302.06 Preparing the Existing Subgrade
Grade and shape the existing roadway in reasonably close conformity with the lines, grades, and cross -sections shown on the Plans or as directed by the Engineer. Remove all grass turfs and other deleterious substances from the subgrade and prepare the subgrade as specified in 207.03. Correct wet or unstable underlying foundation material, if encountered, as directed by the Engineer. 302.07 213 302.07 Extra Depth Stabilization If directed by the Engineer, perform extra depth lime stabilization as follows:
302.08 Applying Lime
After preparing the subgrade as specified in 302.06, apply lime using the dry or slurry application metho d for either hydrated lime or quicklime. Use the slurry application method unless otherwise shown on the Plans.
302.09 Initial Mixing and Mellowing
In dry applications, immediately after applying the hydrated li me, scarify the course, if necessary, and mix to the required depth, width, and cross -sections. In slurry applications, before applying the lime slurry, scarify or partially pulverize with approved mixing equipment the full width of the course to be treated, as directed by the Engineer, to the depth required for stabilization. Perform successive passes over a measured section until the specified percentage of lime has been distributed. After each successive pass, incorporate the slurry into the soil with approved mixing equipment. Incorporate lime into the soil to the depth needed to provide a finished course of lime-treated material conforming to the specified thickness and surface requirements. Continue mixing, and applying water as necessary, until a ho mogeneous mixture of soil, lime, and water is obtained. During this initial mixing operation, add the quantity of water needed for the moisture content of the mixture to reach 5% above its optimum moisture content, plus or minus 3%, unless otherwise direc ted by the Engineer. If applying the lime as a slurry, ensure that the water added with the slurry does not cause the moisture content of the lime -soil mixture to exceed the above tolerance. After completing mixing operations, reshape the treated course to the approximate lines, grades, and cross -sections, and seal with a pneumatic -tire roller, and other approved equipment as necessary, and allow the treated course to mellow for 2 to 7 days as directed by the Engineer. During the mellowing period, maintain the entire surface of the treated course in a moist condition.
302.10 Final Mixing
After the required mellowing period, reshape and grade the initially mixed material to the required lines, grades, and cross -sections. 302.11 215 Thoroughly mix the previously mixed material with approved mixers while adding water as necessary. Continue mixing until 100% of the material, except for gravel and stone, will pass a 1-inch sieve, and 60% by dry weight will pass the No. 4 sieve. The quantity of water added shall be such that at the end of the final mixing and during compaction and finishing operations the percentage of moisture in the mixture and the unpulverized soil lumps will not vary more than plus or minus 3% from the specified opti mum moisture of the lime -soil mixture.
302.11 Compaction and Finishing
Immediately after completing the final mixing, blade the material to uniform thickness and shape, and start compaction operations. Us e sheepsfoot rollers to compact the material in a continuous operation until the entire depth of the lime-soil mixture is uniformly compacted to the required density. The Contractor may remove the sheepsfoot rollers when a surface mulch not exceeding 1 in ch remains. Lightly scarify the resulting surface and shape to the required lines, grades, and cross -sections within the tolerances specified in 302.13. Perform final rolling with the roller specified by the Engineer. The completed lime stabilized subgrade shall be smooth, dense, well bonded, unyielding, and free of cracks or loose material. Compact the lime -soil mixture in layers as shown on the Plans. The Department will determine the maximum density and optimum moi sture content of the lime -soil mixture according to AASHTO T 99. The sample used to determine the maximum density and optimum moisture content will be representative field samples of the lime -soil mixture that have undergone the same treatment as the lime treated subgrade being tested. For density testing purposes, the Department will divide the completed subgrade treatment into lots of approximately 10,000 square yards, and will perform five density tests on each lot. The average dry density of each lot shall not be less than 95% of maximum density, and no individual test shall be less than 92% of maximum density. Immediately scarify, moisten (if required), rework, and compact to the required density all areas that do not meet density requirements at no additional cost to the Department. 302.12 216 302.12 Curing After finishing the lime -treated subgrade as specified in 302.11, seal the surface by applying one of the bituminous materials specified in 302.03.D using a pressure distributor at the rate of 0.10 to 0.25 gallons per square yard, as directed by the Engineer or as shown on the Plans. Heat or otherwise prepare the bituminous material to ensure uniform distribution and a pply as soon as possible.
302.13 Tolerances and Reconstruction
The Department will determine the thickness of the completed lime -treated subgrade by measuring test holes at random locations as specified in Departmental procedures . The measured thickness at the locations shall not deviate from that shown on the Plans by more than pl us 1-1/2 inches or minus 1 inch. Immediately reconstruct areas of lime -treated subgrade that do not meet thickness requirements. For areas having a thickness greater than that allowed, add sufficient lime to correct the deficiency in lime content. Perform reconstruction, including adding lime, to correct the thickness deviation at no cost to the Department. As directed by the Engineer, repair areas of lime -treated subgrade that become unstable or that lose the required density or surface finish. Use additional lime and water if and as directed. Limit hauling over the treated subgrade to the minimum amount necessary to construct the overlying base or sub -base. When at least one course of base or sub -base has been constructed upon the treated subgrade, the Contractor may resume hauling, provided the layer or layers of base or sub -base are constructed and maintained as specified in
303.10 and 303.11.
302.14 217 COMPENSATION
302.14 Method of Measurement
302.14 B.
302.06 as provided for under 207.
302.15 219 302.15 Basis of Payment The Department will pay for accepted quantities at the contract prices as follows: Item Pay Unit Hydrated Lime Ton Bituminous Material Ton Soil-Lime Processing Square Yard Drilling for Subgrade Treatment Linear Feet Water M.G. Such payment is full compensation for providing all materials, equipment, labor, and incidentals to complete the work as specified. The Department will pay for moving, furnishing, or disposing of material under 207 if the Contract is for any of the following:
303.01 Description ................................ ................................ ................... 220
303.02 Aggregate ................................ ................................ ..................... 220
303.03 Calcium Chloride ................................ ................................ ......... 221
303.04 Reserved ................................ ................................ ....................... 221
303.05 Emulsified Asphalt ................................ ................................ ....... 221
303.06 Equipment ................................ ................................ .................... 221
303.07 General ................................ ................................ ......................... 222
303.08 Mixing ................................ ................................ .......................... 223
303.09 Spreading ................................ ................................ ..................... 224
303.10 Shaping and Compaction ................................ ............................. 225
303.11 Maintenance ................................ ................................ ................. 227
303.12 Thickness Requirements ................................ .............................. 227
303.13 Surface Requirements ................................ ................................ .. 227
303.14 Method of Measurement ................................ .............................. 228
303.15 Basis of Payment ................................ ................................ .......... 229
DESCRIPTION
303.01 Description
This work consists of furnishing and placing one or more courses of aggregates, and additives if required, on a prepared subgrade. Mineral aggregates base shall be Type A or Type B, whichever is shown on the Plans and called for in the bid schedule. Recycled Concrete Aggregate (RCA) may be used as an alternate for Type A or Type B base material. MATERIALS
303.02 Aggregate
Depending upon whether the Plans require Type A or Type B base, provide mineral aggregate meeting 903.05. For Type A base, use aggregate of Grading D. For Type B base, the Contractor may use aggregate of Grading C or D. For RCA, use grading specified in 903.05.C.