MATERIAL QUALITY ASSURANCE
PART 1 GENERAL
1.1SECTION INCLUDES
1.2RELATED SECTIONS- Not Used
1.3REFERENCES
1.4DEFINITIONS
have been verified as meeting the requirements in the standard specifications.
1.5SUBMITTALS
federal-aid projects demonstrating compliance with Buy America requirements for approval before delivery to project site.
that has handled the steel or iron product affirming that every process, including the application of a coating, performed on the steel or iron product has been carried out in the United States.
Material Quality Assurance
identification such as heat numbers, lot numbers, and other industry identification markings for each process the material underwent so the final product can be tracked through a step process from smelting to final product.
mill certifications.
for approval before payment and incorporation into the project, when applicable.
steel incorporated into the project.
Contractor from the supplier as delivered to the site, not the Contractor’s bid price.
the cost of the foreign steel and iron does not exceed Buy America requirements
1.6MATERIALS QUALITY ASSURANCE
Management Plans (QMP) listed for the following materials:
qualification during the project will be rejected.
Material Quality Assurance
Information.
incorporated in the work when authorized before use based upon manufacturer information. a The manufacturer information required for authorization is specified in the technical specifications as submittals.
1) Manufactured materials can be incorporated in the work only if listed on the APL when the APL Compliance Form is listed as a submittal in the technical specifications. The APL Compliance Form and application to submit products for placement on the APL can be found on the UDOT website. 2) Materials not listed on the APL when the technical specifications list the APL Compliance Form as a submittal will not be authorized for use.
1) Manufactured materials and assemblies can be incorporated in the work if accompanied by a manufacturer’s Certificate of Compliance when a Certificate of Compliance is listed as a submittal in the technical specifications. Includes the following:
Contractors’ name;
source location and point of manufacture or assembly;
or supplied to;
identification of the certified materials or assemblies delivered to the project;
requirement of the contract specifications fulfilled through certification along with test reports, when applicable; and
comply with the particular requirements of the contract cited above and signed by a manufacturer’s representative in a position to legally bind the manufacturer.
Material Quality Assurance
2) The Department may sample and test materials or assemblies used on the basis of Certificates of Compliance and reject if determined not to meet contract requirements.
instructions 1). Materials may be incorporated into the project based on information provided through manufacturer’s product data sheets and installation instructions when listed as a submittal in the technical specifications. 2). Provide sufficient information to demonstrate conformance with product requirements before incorporating the product into the work. 3). Installation instructions supplement Part 3 Execution requirements of technical Sections; in case of conflict, the more stringent requirements apply. 4). APL Compliance Form may be submitted in lieu of product data sheets and installation instructions if the product is listed in the Department’s APL.
their incorporation into the project as required in the technical specifications.
acceptance using sampling and testing.
considered accepted by that test.
Requirements and the UDOT Materials Manual of Instruction define procedures for anyone performing tests for verification.
extension for or as a result of testing.
costs for retesting of materials made necessary by the Contractor’s activities.
according to the requirements of the UDOT Materials Manual of Instruction to perform materials sampling and testing.
Material Quality Assurance
verification is not defined in the technical specification may be verified for conformance by any of the methods listed in this Article as determined by the Engineer.
1.7SUPPLY SOURCE AND QUALITY REQUIREMENTS
their delivery.
contract requirements.
byproducts do not meet contract requirements.
testing occurred within a year of submittal.
1.8PLANT INSPECTION
manufacturing, or supplying source for compliance with specified manufacturing methods.
manufacture or produce materials.
semiautomatic mechanical sampling devices.
1.9MATERIAL STORAGE AND HANDLING
loading and measuring.
Material Quality Assurance
add loads to bridge elements.
1.10DEPARTMENT FURNISHED MATERIALS
the specified site.
specified.
deducts from money due the Contractor for the following:
after physical transference from the Department.
at the designated time and point of delivery.
are used interchangeably throughout the contract documents to mean components for specific use in the project that are provided by an entity other than the Contractor.
1.11BUY AMERICA
America requirements.
manufactured in the United States to be considered domestic.
a product such as melting, rolling, extruding, machining, bending, grinding, drilling, and coating must occur within the United States.
value of the material to which the coating is applied. The material applied as a coating is not subject to Buy America requirements.
steel or iron, provided the cost of the steel or iron used does not exceed one tenth of one percent (0.1 percent) of the total contract amount or $2,500, whichever is greater.
the project.
could be removed without damaging the completed work. Material Quality Assurance
spacers, mailboxes, and other steel or iron parts that may be considered miniscule or non-structural to the whole of the project.
components.
weight steel or iron content when they are delivered to the job site for installation. 1) Precast items such as pipe, manholes, and drainage boxes must meet the Buy America requirements.
other similar assemblies must meet the Buy America requirements: 1) Guardrail, guardrail posts, end sections, terminals, cable barrier, steel or iron pipe, conduit, grates, manhole covers and risers, mast arms, poles, standards, trusses, supporting structural members for signs, luminaires, and traffic control systems.
1.12CONVICT PRODUCED MATERIALS
CFR Part 635.417, Convict Produced Materials.
incorporated in a Federal-aid highway construction project if such materials have been:
release, or probation from a prison.
annual production amount of such materials for use in Federal-aid highway construction does not exceed the amount of such materials produced in such facilities for use in Federal-aid highway construction during the 12-month period ending July 1, 1987.
PART 2 PRODUCTS Not Used
PART 3 EXECUTION Not Used
END OF SECTION
Material Quality Assurance