SUBMITTALS

PART 1 GENERAL

1.1SECTION INCLUDES

A.Administrative and general requirements for project submittals.
1.The technical specifications specify the required submittals for each

item.

1.2RELATED SECTIONS Not Used

1.3REFERENCES

A.AASHTO LRFD Bridge Construction Specifications
B.UDOT Structures Quality Control/Quality Assurance (QC/QA) Procedures

1.4DEFINITIONS Not Used

1.5SUBMITTALS Not Used

1.6ADMINISTRATIVE REQUIREMENTS

A.Transmit each submittal with a transmittal form.
1.Sequentially number each submittal on the transmittal form.
a.Number resubmittals with the original number and a

sequential alphabetic suffix.

2.Identify:
a.Project number, Project name, Structure number as

applicable, Date, and Revision number.

b.Contractor, subcontractor and supplier, as applicable.
c.Pertinent drawing and detail number, and Specification

Section and Title, as applicable.

d.Variations from Contract Documents and product

requirements.

e.Changes made since previous submissions when revised for

resubmission.

3.Include a signature line for Contractor’s signature indicating the

submittal meets requirements.

Submittals

B.Schedule submittals to expedite the project and to coordinate submission

of related items.

C.Provide space for Contractor and Engineer stamps when submittals are

for approval or review.

1.Allow 4 inch by 4 inch space for Engineer stamp.
D.Document format
1.Submit electronically in PDF format.
2.Drawings
a.Use 11 x 17 inch sheets.
b.Locate the title block in the lower right corner of each sheet.
3.Engineering calculations
a.Use 8½ x 11 inch or 11 x 17 inch sheets.
b.Locate the title block at the top of 8½ x 11 inch sheets and at

the lower right corner of 11 x 17 inch sheets.

4.Other submittals
a.Use 8½ x 11 inch or 11 x 17 inch sheets.
E.Place the following information in the title block of working drawings and

supporting engineering calculations as applicable:

1.State Project Number
2.State Project Name
3.State Structure Number
4.Contractor, Fabricator, or Erector Name
5.Contractor, Fabricator, or Erector Drawing Number
6.Contractor, Fabricator, or Erector Sheet Number
F.Provide the seal of a Professional Engineer (PE) or Professional Structural

Engineer (SE) licensed in the State of Utah when specified.

1.Drawings – Place the seal in the lower right corner of each sheet

when engineering calculations are required to complete the design.

2.Engineering Calculations – Place the seal on the calculation cover

sheet.

3.Other Submittals – Place the seal on the submittal cover sheet.
G.Certify that engineering calculations for structure submittals have been

checked according to the UDOT Structures QC/QA Procedures.

H.Sign transmittal form certifying information is according to the

requirements.

I.Unsolicited submittals not required by the contract or requested by the

Engineer may not be recognized or processed, and may be returned to the Contractor without review. Submittals

1.7SUBMITTAL PROCEDURES

A.Submittals for approval
1.Allow the Department 14 calendar days for review each time the

information is submitted.

2.The Department will return the submittal with one of the following

dispositions:

a.Approved – Submittal is approved.
b.Approved as Noted – Submittal is approved provided listed

conditions are met. Resubmit if conditions cannot be met.

c.Revise and Resubmit – Revise the submittal according to

the markups and resubmit.

d.Rejected –The submittal is not approved.
e.Submit Specified Items – Submittal is incomplete. Resubmit

with the specified items.

3.Receive approval before proceeding with work related to the

submittal and perform work according to approved submittal.

a.The Department may reject work performed before submittal

approval.

4.Resubmit for approval deviations from a previously approved

submittal.

5.The Department may rescind approval at any time.
a.Stop related work if approval is rescinded and revise

submittal to achieve approval.

B.Submittals for review
1.Allow the Department 14 calendar days for review each time the

information is submitted.

2.The Department will return the submittal with one of the following

dispositions:

a.No Exceptions Taken – Submittal is authorized for use.
b.Make Corrections As Noted – Submittal is authorized for use

provided listed conditions are met. Resubmit if conditions cannot be met.

c.Revise and Resubmit – Revise the submittal according to

the markups and resubmit.

d.Rejected –The submittal is not authorized for use.
e.Submit Specified Items – Submittal is incomplete. Resubmit

with the specified items.

3.Receive authorization before proceeding with work related to the

submittal and perform work according to authorized submittal.

a.The Department may reject work performed before submittal

authorization.

4.Resubmit for review deviations from a previously authorized

submittal. Submittals

5.The Department may rescind authorization at any time if it is

discovered that the submittal does not meet contract requirements.

a.Stop related work if authorization is rescinded and revise

submittal to achieve authorization.

C.Submittals for information
1.Provide information related to conformance with requirements

before incorporating related work into the project.

2.The Engineer will verify compliance with the contract requirements.
D.Samples for selection
1.Deliver samples with transmittal form to location determined by the

Engineer.

2.Allow 7 calendar days for the Department to make a selection.
E.Samples for verification
1.Deliver samples with transmittal form to location determined by the

Engineer.

2.Allow 7 calendar days for the Department to test the samples

provided.

1.8DRAWING & PLAN SUBMITTALS

A.Working Drawings
1.Shop drawings
a.Submit for review.
b.Provide sufficient detail to fabricate the member and to

demonstrate contract compliance.

c.Provide the seal of a PE or SE licensed in the State of Utah

when the Contractor designs the item or the Contractor completes the design for the item. 1) Include supporting engineering calculations for items designed by the Contractor.

d.The seal of a PE or SE is not required when the complete

details for the item are provided in the contract.

2.Erection Drawings
a.Submit for review.
b.Include supporting engineering calculations.
c.Provide the seal of a PE or SE licensed in the State of Utah

on drawings and calculations.

3.Shipping Drawings
a.Submit for review.
b.Required for structural elements when specified, shown, or

requested by the Engineer.

Submittals

1) Structural steel plate girder shipped on its side, for example.

c.Include the following:

1) Details and methods used to protect products from damage (overstress)

d.Include supporting engineering calculations.
e.Provide the seal of a PE or SE licensed in the State of Utah

on drawings and calculations.

4.Drawings for Temporary Works.
a.Submit for review according to the following:

1) When specified, shown, or requested by the Engineer. 2) The height of falsework exceeds 14 ft or whenever traffic, other than workers involved in constructing the bridge, will travel under the bridge. 3) Temporary bridges or bridge widenings that carry or span the travelled way. 4) Temporary retaining walls that support or protect the travelled way.

b.Include detailed plans for items such as falsework, concrete

forms, cofferdams, shoring, and temporary bridges.

c.Include design calculations and supporting data.
d.Design temporary works according to the current edition of

the AASHTO LRFD Bridge Construction Specifications, Section 3 (Temporary Works).

e.Provide the seal of a PE or SE licensed in the State of Utah

on drawings and calculations.

5.Demolition Plans
a.Submit for review when specified, shown, or requested by

the Engineer.

b.Provide detailed plans depicting the proposed methods of

removal of existing structures and structural elements.

c.Include supporting engineering calculations.
d.Provide the seal of a PE or SE licensed in the State of Utah

on drawings and calculations.

PART 2 PRODUCTS NOT USED

PART 3 EXECUTION NOT USED

END OF SECTION Submittals

Submittals in other states

Get an email when 01450 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 149–153 of 1,331. View official source ↗

Ask about this section

Scoped to Utah Standard Specifications, Section 01450 — Submittals. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.