02231Site Clearing And Grubbing

UT · 2026 Standard Specifications✓ Full text on BuildSpecRev. September 14, 2023Book pages 272–273 Save this section

Ask about Section 02231

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

SITE CLEARING AND GRUBBING

PART 1 GENERAL

1.1SECTION INCLUDES

A.Removal and disposal of vegetation, stumps, debris, and other materials

within the designated areas shown.

1.2RELATED SECTIONS Not Used

1.3REFERENCES Not Used

1.4DEFINITIONS

A.Clear – Removal and disposal of trees 20 inch or less in circumference

(measured at a point 2 ft above existing ground), stumps, logs, limbs, sticks, vegetation, debris, and other material on the natural ground surface.

B.Grub – Removal and disposal of roots, buried logs, debris, and organic

matter to 2 ft below natural ground surface.

1.5SUBMITTALS

A.Copies of disposal permits, agreements, or both, for information.
B.Request to dispose of material resulting from clearing and grubbing

operations inside the Right-of-Way, for review.

PART 2 PRODUCTS Not Used

PART 3 EXECUTION

3.1PREPARATION

A.Verify with the Engineer the vegetation or objects to be removed.
B.Before clearing and grubbing, verify the appropriate temporary

environmental controls have been installed.

Site Clearing and Grubbing

3.2VEGETATION AND DEBRIS REMOVAL

A.Clear and grub areas as shown or necessary to complete project work,

including the following:

1.Areas where fill material will be placed
2.Areas to be regraded
B.Roots, and non-perishable solid objects may remain in cleared areas

where the top of embankment is:

1.2 ft or more above the cleared ground.
C.Completely remove stumps and roots where a structure is to be

constructed, piles are to be driven, or unsuitable material is to be removed.

3.3DISPOSAL

A.Outside of the Right-of-Way
1.According to prevailing laws including environmental laws,

ordinances, regulations, and rules.

B.Inside the Right-of-Way
1.Use material to widen embankments and flatten embankment side

slopes as authorized by the Engineer or bury material at locations specified by or authorized by the Engineer.

a.Cover disposed material with at least 2 ft of earth and grade

to drain properly.

2.Reduce wood to chips a maximum of ½ inch thick for mulching cut

and fill slopes.

a.Bury or uniformly distribute chips on the ground surface or

mix with the underlying earth so the mixtures will not sustain burning.

3.4PROTECTION

A.Land monuments, property markers, or official datum points
1.Protect until their removal is necessary.
2.Reference for re-establishment before removing.
B.Protect trees from damage to roots and branches if they are designated to

remain.

C.Protect other vegetation and objects designated to remain.

END OF SECTION Site Clearing and Grubbing

Get an email when 02231 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 272–273 of 1,331. View official source ↗

Ask about this section

Scoped to Utah Standard Specifications, Section 02231 — Site Clearing And Grubbing. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.