02229Temporary Retaining Walls

UT · 2026 Standard Specifications✓ Full text on BuildSpecRev. December 8, 2022Book pages 268–271 Save this section

Ask about Section 02229

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

TEMPORARY RETAINING WALLS

PART 1 GENERAL

1.1SECTION INCLUDES

A.Temporary retaining walls designed by the Contractor and used by the

Contractor in the execution of the work.

1.2RELATED SECTIONS

A.Section 02075: Geotextiles
B.Section 02317: Structural Excavation and Backfill
C.Section 03055: Portland Cement Concrete
D.Section 03211: Reinforcing Steel and Welded Wire
E.Section 05120: Structural Steel

1.3REFERENCES

A.AASHTO LRFD Bridge Construction Specifications
B.UDOT Geotechnical Manual of Instruction (GMOI)

1.4DEFINITIONS Not Used

1.5SUBMITTALS

A.Temporary retaining wall working drawings for review
1.Include at least the following:
a.Type, location, size and other pertinent information about the

temporary retaining wall for each location

b.Plans, profiles, cross sections, and details (including grading

and tie-ins, if applicable) for each retaining wall

Temporary Retaining Walls

c.Measures to be taken to prevent impacts on or interference

with adjacent foundations, structures, utilities, and properties from temporary retaining walls; including but not limited to impacts or interference from structural elements, settlements, and vibrations 1) Provide upper threshold values for settlement for each protected element.

d.Specific details that reflect construction staging requirements

of the bridge or other work item in the vicinity of the temporary retaining wall

e.Surface and subsurface drainage details including

dewatering requirements, if applicable

f.Geotechnical design parameters necessary for the design of

the wall

g.Drivability analyses of piles or sheet piles, if used
h.Subgrade preparation and stabilization measures, if required
i.Details and measures for incorporating temporary retaining

walls (in whole or in part) into the backfill of permanent retaining walls or into permanent slopes, if applicable 1) Include a drawing showing the limits of the temporary wall which will be incorporated along with its placement relative to the permanent wall or slope to be constructed.

a.Provide the permanent wall structure number

for reference if applicable 2) Identify submittal requirements for Quality Control items that need to be submitted during temporary wall construction as appropriate for the permanent wall or slope. Including:

a.Material Sampling and Testing Requirements
b.Certificates of compliance for incorporated

materials with test results as applicable

c.Signed Mill Test Reports
d.Product data sheets
e.Grout mix designs
f.Field test results
g.Construction documentation and observation

reports

2.Include supporting calculations sufficient to demonstrate that the

retaining wall is designed according to the required criteria.

3.Provide the seal of a Professional Engineer (PE) or Professional

Structural Engineer (SE) licensed in the State of Utah on the drawings and calculations.

Temporary Retaining Walls

B.Submit as-built drawings for temporary walls to be incorporated into the

backfill of permanent walls or permanent slopes for information before constructing the permanent wall or slope.

1.Include sufficient survey to locate the temporary wall

PART 2 PRODUCTS

2.1TEMPORARY RETAINING WALL

A.Use the following retaining wall types as temporary retaining walls:
1.Mechanically Stabilized Earth (MSE) with geosynthetic or metallic

soil reinforcing

2.Sheet pile, with or without tiebacks
3.Soldier pile and lagging, with or without tiebacks
4.Soil nail
5.Cast-in-place concrete
6.Rock/soil anchor

2.2MATERIALS

A.Concrete
1.Class AA(AE).
2.Refer to Section 03055.
B.Reinforcing Steel and Welded Wire
1.Refer to Section 03211.
C.Structural Steel
1.Refer to Section 05120.
D.Geotextiles
1.Refer to Section 02075.

2.3DESIGN CRITERIA AND REQUIREMENTS

A.Design temporary retaining walls according to the UDOT GMOI and the

AASHTO LRFD Bridge Construction Specifications.

B.Design temporary retaining walls to support at least the following loads:
1.Earth pressure (including the effects of pore-water pressure)
2.Live load surcharge
3.Construction live loads
4.Embankment surcharge fills

Temporary Retaining Walls

C.Design temporary retaining walls that will remain in place and become

incorporated into permanent retaining walls or slopes (in whole or in part) to meet the requirements for the permanent and temporary conditions, such as materials, compaction, density, settlement, stability, and design life.

D.Consider vibration and settlement requirements when determining

temporary retaining wall design criteria.

E.Determine the drivability of proposed piles and sheet piles.

PART 3 EXECUTION

3.1GENERAL

A.Construct temporary retaining walls according to the authorized temporary

retaining wall working drawings.

B.Maintain stability of temporary slopes.
C.Provide adequate drainage measures for the protection of the temporary

works.

3.2INSTALLATION

A.Excavate for temporary retaining walls according to Section 02317.
B.Construct retaining walls on solid foundations that are safe from

undermining, protected from softening, and capable of supporting the intended imposed loads.

C.Meet materials sampling and testing requirements shown in the authorized

Working Drawings.

3.3REMOVAL

A.Remove temporary retaining walls that are not part of the permanent work

at least 2 ft below the finished grade.

B.Remove temporary grading and tie-ins.

END OF SECTION

Temporary Retaining Walls

Get an email when 02229 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 268–271 of 1,331. View official source ↗

Ask about this section

Scoped to Utah Standard Specifications, Section 02229 — Temporary Retaining Walls. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.