02737Pavement Soft Spot Repair

UT · 2026 Standard Specifications✓ Full text on BuildSpecRev. September 12, 2024Book pages 454–457 Save this section

Ask about Section 02737

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

PAVEMENT SOFT SPOT REPAIR

PART 1 GENERAL

1.1SECTION INCLUDES

A.Removal and replacement of soft spots in the existing asphalt pavement,

untreated base course, and borrow.

1.2RELATED SECTIONS

A.Section 02056: Embankment, Borrow, and Backfill
B.Section 02072: Geosynthetics
C.Section 02075: Geotextiles
D.Section 02721: Untreated Base Course (UTBC)
E.Section 02741: Asphalt Mix
F.Section 02744: Stone Matrix Asphalt (SMA)

1.3REFERENCES Not Used

1.4DEFINITIONS Not Used

1.5SUBMITTALS

A.Daily Quality Control Report showing maximum density was obtained in

each repair for information.

1.6ACCEPTANCE

A.Granular Borrow and Untreated Base Course
1.The Engineer takes random samples from the grade and tests for

moisture and laboratory density and performs in-place density determinations.

2.Meet a minimum density of 92 percent of the maximum

laboratory density.

Pavement Soft Spot Repair

B.Asphalt Mix and SMA
1.The Engineer will visually inspect placement.

1.7QUALITY CONTROL

A.Use a nuclear density gauge in each repair to verify that maximum

density has been obtained.

1.Compact and test until maximum density is obtained.
2.Make one additional pass over the entire surface and test

again to verify maximum density is obtained.

3.Do not crush aggregate.

PART 2 PRODUCTS

2.1GEOSYNTHETICS COMPOSITE SYSTEM

A.Refer to Section 02072.

2.2SEPARATION GEOTEXTILE

A.Refer to Section 02075.

2.3UNTREATED BASE COURSE (UTBC)

A.Refer to Section 02721.

2.4ASPHALT MIX

A.Refer to Section 02741.

2.5STONE MATRIX ASPHALT (SMA)

A.Refer to Section 02744.

2.6GRANULAR BORROW

A.Refer to Section 02056.

PART 3 EXECUTION

3.1ASPHALT PAVEMENT SOFT SPOT REPAIR

A.The Engineer will identify and mark repair areas.

Pavement Soft Spot Repair

B.Remove the deteriorated asphalt to a depth of at least 6 inch below final

roadway surface for non-interstate routes and at least 8 inch for interstate routes or as determined by the Engineer.

1.Non-deteriorated existing asphalt may be left in place if at least 2

inch thick.

2.Remove material by pavement sawcutting or rotomilling, leaving all

edges square and vertical.

a.Size the removal area to be at least 6 ft by 6 ft.
b.Locate cuts at least 6 inch beyond the visible limits of distress.
c.Locate longitudinal cuts on lane lines or at the center of the

lane.

3.Remove the deteriorated asphalt without damaging the surrounding

asphalt pavement.

4.Transport and dispose of excavated material.
C.Grade and compact the existing base course surface if existing asphalt is

removed full-depth.

1.Use the largest piece of vibratory or impact compaction equipment

practical.

2.Continue compaction until additional work does not improve the

measured density.

D.Remove loose material and clean vertical edges before applying tack coat

and paving.

E.Place and compact Asphalt Mix or SMA to within 1/8 inch of the

surrounding pavement surface.

1.Use the largest piece of vibratory or impact compaction

equipment practical.

2.Continue compaction until additional work does not improve the

measured density.

3.2UTBC SOFT SPOT REPAIR

A.The Engineer will identify and mark repair areas.
B.Excavate and remove 10 inches of existing base course or as determined

by the Engineer.

1.Transport and dispose of excavated material.
C.Grade and compact the existing base
1.Use the largest piece of vibratory or impact compaction equipment

practical.

2.Continue compaction until additional work does not improve the

measured density. Pavement Soft Spot Repair

D.Place Separation Geotextile to within 1 inch of the edge of excavation.
E.Place and Compact UTBC
1.Use the largest piece of vibratory or impact compaction equipment

practical.

3.3GRANULAR BORROW SOFT SPOT REPAIR

A.The Engineer will identify and mark repair areas.
B.Remove saturated or unsatisfactory material in the repair area to a depth

of at least 24 inch or as determined by the Engineer.

1.Transport and dispose of excavated material.
C.Place Geosynthetic Composite System.
1.When Geosynthetic Composite System is comprised of separate

layers of material:

a.Place Separation Geotextile to within 1 inch of the edge of

excavation.

b.Place Geogrid. Wrap one foot up the sides.
2.When Geosynthetic Composite System is a single layer, wrap one

foot up the sides of the excavation.

D.Place and compact Granular Borrow or material deemed satisfactory by

the Engineer.

1.Materials may include recycled Portland Cement Concrete or

rotomill tailings if generated during construction.

2.Selected material must be sufficient to bridge or stabilize the

subgrade.

3.Material consisting of large aggregate (1 ft minus) may be required

to stabilize a heavily saturated subgrade.

4.Continue compaction until additional work does not increase the

measured density if rotomill tailings are used.

5.Use the largest piece of vibratory or impact compaction equipment

practical.

END OF SECTION

Pavement Soft Spot Repair

Get an email when 02737 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 454–457 of 1,331. View official source ↗

Ask about this section

Scoped to Utah Standard Specifications, Section 02737 — Pavement Soft Spot Repair. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.