02755Concrete Slab Jacking

UT · 2026 Standard Specifications✓ Full text on BuildSpecRev. September 14, 2023Book pages 572–574 Save this section

Ask about Section 02755

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

CONCRETE SLAB JACKING

PART 1 GENERAL

1.1SECTION INCLUDES

A.Injection of a product to raise and support a failed section of concrete

pavement back to grade for a suitable ride.

1.2RELATED SECTIONS

A.Section 02705: Concrete and Asphalt Cutting

1.3REFERENCES

A.ASTM C 1107: Packaged Dry, Hydraulic-Cement Grout (Nonshrink)
B.ASTM D 790: Flexural Properties of Unreinforced and Reinforced Plastics

and Electrical Insulating Materials

C.ASTM D 1621: Compressive Properties of Rigid Cellular Plastics
D.ASTM D 1622: Apparent Density of Rigid Cellular Plastics

1.4DEFINITIONS Not Used

1.5SUBMITTALS

A.Copies of invoices from mix suppliers for information.
B.Manufacturer’s product data sheet and recommended installation

instructions.

C.A warranty letter guaranteeing all materials and workmanship for a period

of one year.

1.The guarantee period starts on the date of Substantial Completion.
2.Include in the letter:
a.State Project Designation
b.State Project Name
c.Contractor and Installer Name

Concrete Slab Jacking

3.Defects (performance failures) include:
a.Re-settling of treated areas beyond ⅛ inch of finished grade

profile

4.The guarantee covers 100 percent of the concrete slab jacking

costs.

5.Replace by re-injection or slab replacement any material that fails

during the warranty period.

1.8PAYMENT PROCEDURES

A.Liquid quantities of non-shrink grout measured using a calibrated meter

paid for at the contract unit price per cubic yard.

B.Liquid quantities of High-Density Polyurethane measured using methods

approved by Engineer paid for at the contract unit price per pound.

PART 2 PRODUCTS

2.1HIGH DENSITY POLYURETHANE

A.Use water based formulation of expanding high-density polyurethane that

sets to full compressive strength within 15 minutes after injection to raise slabs.

Table 1 High-Density Polyurethane PROPERTY ASTM LIMITS Density D 1622 Min 3.8 lb/ft3 - Max 4.3 lb/ft3 Tensile Strength D 790* Min. 80 psi Elongation N/A Max. 5.1% Compressive Strength at Yield D 1621 Min. 60 psi Point *Use the value of flexural strength or flexural yield as tensile strength.

2.2NON-SHRINK GROUT

A.Use packaged dry, hydraulic-cement grout (non-shrink) according to

ASTM C 1107.

2.3EQUIPMENT

A.Equipment capable of supplying a homogenous product at the appropriate

rate.

Concrete Slab Jacking

B.Certified scales or measuring devices to measure delivered product and to

proportion product components.

C.Concrete drill or saw capable of producing circular holes of adequate size

for the application type.

D.Elevation measuring devices with an accuracy of ⅛ inch.
E.Concrete saw capable of cutting joints between failed and non-failed

slabs.

PART 3 EXECUTION

3.1PREPARATION

A.Establish a finish target profile of pavement using elevation measuring

device or string lines.

B.Saw cut joints between failed and non-failed slabs as necessary to

prevent damage to non-failed slabs. Refer to Section 02705.

3.2INSTALLATION

A.Drill holes as necessary in roadway slab.
B.Inject product to evenly raise slab to finished grade profile.
C.Fill injection holes with at least 4 inches of non-shrink grout.
D.Final grade after jacking must be within ± ⅛ inch of finished grade profile.

END OF SECTION

Concrete Slab Jacking

Get an email when 02755 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 572–574 of 1,331. View official source ↗

Ask about this section

Scoped to Utah Standard Specifications, Section 02755 — Concrete Slab Jacking. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.