Electrical (16000-16999)

16526Electrical Conduit on Bridge

UT · 2026 Standard SpecificationsRev. February 15, 2024Book pages 13031305View official source ↗

Part 1 — General

1.1 Section Includes

A.Electrical conduits and junction boxes installed on and adjacent to bridge.

1.2 Related Sections

A.Section 13554: Underground Junction Box
B.Section 16530: Electrical Power

1.3 References

A.ASTM F 512: Smooth- Wall Poly(Vinyl Chloride) (PVC) Conduit and Fittings for Underground Installation
B.ASTM F 593: Stainless Steel Bolts, Hex Cap Screws, and Studs
C.Electronic Industries Association (EIA)
D.National Electrical Manufacturers Association (NEMA)
E.Underwriters Laboratory (UL)

1.4 DEFINITIONS Not Used

1.5 Submittals

A.Manufacturer’s product data and recommended installation instructions for conduit expansion coupler for information.

Part 2 — Products

2.1 Electrical Equipment

A.Use equipment conforming to the applicable standards:
1.National Electrical Manufacturer’s Association (NEMA)
2.Underwriters Laboratories, Inc. (UL)
3.Electronic Industries Association (EIA)

2.2 Conduit and Fittings

A.Schedule 40 PVC conduit and fittings when conduit is encased in concrete .
1.Type EPC -40, rated for use with 90 degrees C conductors.
a.Conduit. Comply with NEMA TC- 2.
b.Fittings. Comply with NEMA TC -3.
c.Conduit and Fittings. Comply with ASTM F 512, and UL 651 Listed.
B.Rigid metal conduit and fittings w hen the conduit is attached to the exterior surface of the structure . Refer to Section 16530.
C.Conduit Expansion Coupler
1.Compatible with attached conduit
2.For use in electrical applications
3.Two-piece expansion system
4.Provides at least 8 inches of total travel distance

2.3 Foam Tape Seal

A.Use foam tape 3/8 inch or 1/2 inch thick and at least 3/4 inch wide .

2.4 Mounted Junction Boxes

A.Use galvanized or stainless steel NEMA 3 or 4, screw -cover junction boxes .
1.Use junction box covers with at least four stainless steel screws.
B.Stainless Steel Hardware. Refer to ASTM F 593.

2.5 Underground Junction Boxes

A.Refer to Section 13554.

2.6 Pull Tape

A.Flat profile, low stretch polyester, 1,200 lb tensile strength pull tape.

Part 3 — Execution

3.1 Conduit Expansion Coupler

A.Conduit encased in concrete
1.Install conduit expansion coupler immediately before placing concrete.
2.Cut ends of conduit to position conduit expansion coupler so that the piston (smaller diameter length of coupler) is completely within the open expansion joint.
3.Place the extent of the female coupler end 1/2 inch inside the face of concrete on one side of the joint and the barrel 1/2 inch inside the opposite face of concrete.
4.Wrap piston in foam tape at least two complete revolutions to make certain concrete will not interfere with the expansion m echanism.
a.Apply tape in individual rounds beginning at the face of the barrel, do not spiral along the length of the piston.
b.Wrap tape gently so that it does not significantly compress with the second revolution.
B.Exter ior Conduit
1.Place conduit expansion coupler near the expansion joint.
a.Do not place a hanger or mount ing point between the coupler and the expansion joint.
2.Cut ends of conduit to set conduit expansion coupler in the half -way expanded position.

3.2 Junction Boxes

A.Install junction boxes as shown .
1.Underground junction boxes. Refer to Section 13554.

3.3 Pull Tape

A.Install pull tape in each conduit.
B.Provide 3 ft of pull tape slack coiled in the parapet junction box es and in junction boxes installed in the ground, measured from the top of the junction box going out.
Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 13031305 of 1,331.