315Individual anodes shall provide a current density output equal to or greater than 0.05 µA/cm2 (0.32 µA/ in2) at 10 years, based upon manufacturer’ s recommended steel surface area for placement. The anodes shall be designed and installed such that the anode has the same embedment depth as the reinforcing steel to which it is attached. Anodes shall be delivered, stored, handled, and installed according to the manufacturer’ s instructions. SECTION 252 - GRA VITY -FILL POL YMER CRACK SEALERS
252.01 Description
These specifications cover polymers used for gravity-filling sealing cracks in hydraulic cement concrete surfaces.
252.02 Materials
Gravity-fill polymer crack sealers shall be a high molecular weight methacrylate, epoxy, or urethane conforming to the following: Properties of Gravity-filled Polymers Property @ 75 ± 5 °F Test Method Requirement Gel Time, 50 ml sample ASTM C881 6 hrs. max. Tensile Strength ASTM D638 1,500 psi min. Sand Penetration, MX-45 sand VTM 101 80% min.252.02 317DIVISION III ROADW AY CONSTRUCTION 319SECTION 301—CLEARING AND GRUBBING
301.01 Description
This work shall consist of clearing, grubbing, and activities to remove and dispose of vegetation, debris, fences and other objects unsuitable for construction located within the construction limits except for vegetation and objects that are designated to be preserved, protected, or removed in accordance with the Contract or other provisions of these Specifications.
301.02 Procedures
If approved by the Engineer, the Contractor may clear and grub to accommodate construction equipment within the right of way up to 5 feet beyond the construction limits at his own expense. The Contractor shall install erosion and siltation control devices prior to beginning clearing or grubbing operations. Such devices shall be functional before upland land-disturbing activities take place. The surface area of earthen material exposed by grubbing, stripping topsoil, or excavation shall be limited to that necessary to perform the next operation within a given area. The Contractor shall confine the grubbing of root mat and stumps to that area of land on which the Contractor shall perform excavation or other land disturbance activities within 14 days following grubbing operations. The Contractor shall remove stumps, roots, other perishable material, and nonperishable objects that will be less than 5 feet below the top of earthwork within the area directly beneath the roadway pavement and shoulders. Material and objects that will be 5 feet or more below the top of earthwork within the area directly beneath the roadway pavement and shoulders and all such material and objects beneath slopes of embankments shall be left in place unless removal is necessary for installation of a structure. The top of stumps left in place shall not be more than 6 inches above the surface of existing ground or low water level. Branches of trees that overhang the roadway, reduce sight distance, or are less than 20 feet above the elevation of the finished grade shall be trimmed using approved tree surgery practices in accordance with Section 601.03(b). Vegetation, structures, or other items located outside the construction limits shall not be damaged. Trees and shrubs in ungraded areas shall not be cut or trimmed without the approval of the Engineer. The Contractor shall dispose of combustible cleared and grubbed material in accordance with the following: