402.03 Procedures
a.Timber Sheet Piles: The Contractor shall furnish piles that are sawed with square corners and provided with tongues and grooves of ample proportions, either cut from the solid material or made with three planks securely fastened together. Piles shall be drift sharpened at the lower ends to wedge the adjacent piles tightly together. The top of piles shall be cut off to a straight line. Piles shall be braced with waling strips that are lapped and joined at splices and corners. Wales shall be in one length between corners and bolted near the top of the piles.
b.Concrete Sheet Piles: Concrete sheet piles shall be manufactured in accordance with Section 403, 404, or 405, as applicable. The Contractor shall install concrete sheet piles in accordance with Section 403. c.Steel Sheet Piles: When assembled in place, pile sections shall be practically watertight at the joints. Painting of steel sheet piles shall be performed in accordance with Section 403. Piles shall be provided with tongues and grooves of ample proportions for securely fastening together. Wales and structural supports shall be provided as necessary to ensure structural integrity. d.Temporary Sheet Piling: When shown on the plans or directed by the Engineer, temporary sheet piling will be measured in square feet. The Engineer will measure the horizontal dimensions contin- uously along the outer face of the sheet piling. The bottom limit will be the bottom of the excavation shown on the plans or authorized by the Engineer. The top limit will be the original ground line or, in areas adjacent to traffic, 3 feet above the original ground line, or as otherwise shown on the plans.
Source: Road and Bridge Specifications, 2020 Edition. Pages 465–465 of 1,065.
View official source ↗