6-45 Sectio N 613 – Ston E Fill and Riprap
613.0 1 DESCRIPTION . This work shall consist of furnishing and placing protective material s. 613.0 2 MATERIALS . Materials shall meet the requirements of the following subsection s: Sand Borrow and Cushion ................................ ................................ ......................... 703.03 Stone for Riprap, Heavy Type ................................ ................................ ................... 706.03(a) Stone for Riprap, Light Type ................................ ................................ ..................... 706.03(b) Stone Fill, Type I ................................ ................................ ................................ .......706.04(a) Stone Fill, Type II ................................ ................................ ................................ ......706.04(b) Stone Fill, Type III ................................ ................................ ................................ .....706.04(c) Stone Fill, Type IV ................................ ................................ ................................ ....706.04(d) E-Stone Fill, Type I ................................ ................................ ................................ ....706.05(a) E-Stone Fill, Type II ................................ ................................ ................................ ..706.05(b) E-Stone Fill, Type III ................................ ................................ ................................ .706.05(c) E-Stone Fill, Type IV ................................ ................................ ................................ .706.05(d) E-Stone fill shall be of the type specified on the Plans, supplemented with material excavated from the channel or the tailings of a topsoil screening operation. Bed material shall be approved by the Engineer and the Vermont Agency of Natural Resources prior to use . Similar sized river sediment is an acceptable alternative as is a mixture of angular material and river sediment. 613.0 3 PREPARATION . The areas to be protected shall be constructed and graded to the lines shown on the Plans or as directed by the Engineer and, if a fill area, shall be compacted . All slope s shall be maintained to the neat lines shown on the Plans prior to the placing of filter or bedding material , stone fill, or riprap. 613.0 4 PLACING .
6-46 Rearrangement of the stone fill by hand labor or mechanical equipment may be required to obtain
the specified results. When stone fill and gravel filter are to be placed as part of an embankment , the protective material s shall be placed concurrently with the construction of the embankment , unless otherwise directed by the Engineer. Where stone fill is to be placed under water, methods shall be used that will minimize segregation and ensure that the required thickness of p rotective material will be obtained. Once all material has been placed, the Contractor shall slowly wet the stream to minimize the effects of the initial sediment pulse . Every attempt shall be made to minimize the movement of sediment downstream of the sit e. Sand borrow shall be added to seal the bed and prevent subsurface flow as directed by the Engineer. There shall be no subsurface flow upon final inspection.
6-47 Payment wil l be made under:
Pay Item Pay Unit 613.0601 E -Stone Fill, Type I ................................ ................................ ................... Cubic Yard 613.0602 E -Stone Fill, Type II ................................ ................................ ................. Cubic Yard 613.0603 E -Stone Fill, Type III ................................ ................................ ................ Cubic Yard 613.0604 E -Stone Fill, Type IV ................................ ................................ ................ Cubic Yard 613.10 01 Stone Fill, Type I ................................ ................................ ...................... Cubic Yard 613.1 002 Stone Fill, Type II ................................ ................................ ..................... Cubic Yard 613.1 003 Stone Fill, Type III ................................ ................................ .................... Cubic Yard 613.1 004 Stone Fill, Type IV ................................ ................................ ................... Cubic Yard 613.15 10 Riprap, Light Type ................................ ................................ .................... Cubic Yard 613.1 520 Riprap, Heavy Type ................................ ................................ .................. Cubic Yard 6-48SECTIO N 614 – STREA M DIVERSIO N AND IN-WATE R SEDIMEN T ISOLATIO N MEASURES 614.0 1 DESCRIPTION . This work shall consist of implementing adequate control measures to protect the flow of water through the construction site using temporary stream relocation or in -water sediment isolation measures . This shall include designing, furnishing, installing, maintaining, and removing the control measures, as well as erosion prevention and sediment control, channel m aintenance, and debris removal in accordance with these specifications. 614.0 2 MATERIALS . Materials shall meet the requirements of the following subsections: Stone Fill ................................ ................................ ................................ .................... 706.04 Geotextile for Roadbed Separator ................................ ................................ .............. 720.02 Geotextile Under Stone Fill ................................ ................................ ....................... 720.04 Geotextile for Filter Curtain ................................ ................................ ....................... 720.06 Other materials which effectively separate sediment or pollutants from waters of the state, as defined in the Vermont Water Quality Standards , may be used. These shall be detailed on the EPSC plan and are subject to approv al. 614.0 3 TEMPORAR Y RELOCATIO N OF STREAM .