Effective with the December 2018 Letting 461 2019 Standard Spec ifications Section 649 Temporary Pavement Marking
649.1Description
649.2Materials
649.3Construction
General mar king ............................................... ..................................................................................... 646.3.1.1 Long line ..................................................... ........................................................................................... 646.3.1.2 Removing ma rking .............................................. ................................................................................... 646.3.1.4
LIQUID MARKING THICKNESS BEAD APPLICATION
Paint 12 4 - 5 Epoxy 16 12 - 15
markers, the contractor may ins tall used markers in like-new co ndition.
- On intermediate layers, includi ng milled surfaces, on the same day the pavement i s placed or milled. - On the upper layer, on the sa me day the pavement is placed un less the contractor a pplies permanent marking on the same day the pavement is placed. - If weather conditions preclude same-day application, delineat e the travel lanes and provide no-passing signing as the engineer directs . Apply centerlines and no-passi ng barrier lines as soon as conditions allow. The engineer may restrict operations until these markings are c ompleted.
existing no-passing barrier lines . Apply temporary no-passing b arrier lines at those existing locations. If the contract contains the Locating No-Passing Zones bid item , relocate permanent no-passing zones as specified in 648.
temporary marking, including ra ised markers, that deteriorates or fails to adhere to the extent that the roadway is not adequately delineated.
649.4Measurement
completed and the LF bid items under this section by the linear foot of line acceptably completed.
649.5Payment
items: ITEM NUMBER DESCRIPTION UNIT
649.0100 - 0299 Temporary Marking Line (material/type) (width) LF
649.0500 - 0599 Temporary Marking Arrow (material) EACH
649.0600 - 0699 Temporary Marking Word (material) EACH
649.0700 - 0799 Temporary Marki ng Raised Pavement Marker (type) EACH
649.0800 - 0899 Temporary Marki ng Stop Line (material) 18-Inch LF
649.0900 - 0959 Temporary Marking Diagonal (material) 12-Inch LF
60 - 0970 Temporary Marking Removable Mask Out Tape (widt h) LF
Revise 649.5(2) to restore language making temporary marking placed under the contractor's same day option incidental.
marker; for maintaining, and for removing the marking or marker . Placing and removing temporary markings applied under the 646 contractor option for same-day marking are incidental to the associated permanent pavement marking bid item.
Effective with the December 2018 Letting 462 2019 Standard Spec ifications Section 650 Construction Staking
650.1Description
bid items to establish the horizontal and vertical position for the following: Storm sewer Subgrade Base Curb, gutter, and curb & gutter Pipe culver ts Structure layout Concrete pavement Concrete ba rrier Resurfacing reference Electrical installations Supple mental Control Slope Stakes Curb Ramps 650.2 (Vacant)
650.3Construction
650.3.1 General
105.6 and the additional requirements specified here in 650.3 for th e individual contractor-staking bid items the contract includes.
The contract may require related work under the 621 bid items.
furnish data for the horizontal and vertical control points, co ntrol point ties, horizontal alignments, profiles, and elevations. Reestablish, set additional, and maintain the horizontal and vertical control points and control point ties, as needed for bid items. Furnish , set, reference, and maintain stakes and markings necessary to establish the alignment, location, benchmarks, elevations, and continuous profile-grades for road and stru cture work as needed for bid it ems. Supervise and coordinate construction staking.
and dimensions, that either the pl ans show or the engineer prov ides, for compatibility with existing field conditions. Conduct similar compat ibility checks and accuracy checks of horizontal and vertical positions either the department o r the contractor establishes in the field.
guidance. The contractor may employ global positioning technolo gy, robotic total station systems, laser systems, conventional met hods, or other engineer-approved methods the engineer deems capable of achieving the specif ied horizontal and vertical tole rances for the work in question. Establish additional benchmarks and contro l points as necessary to suppor t the method of operation.
the lines and grades. Make the su rvey notes and computations available to the engineer within 24 hours, upon request, as th e work progresses.
perform this work, subject to the engineer’s approval. 650.3.2 Storm Sewer
support the method of operations . Locate pipe, inlet, catch bas in, manhole, and endwall construction stakes to within 0.02 feet horiz ontally and establish the elevations to within 0.01 feet vertically. Determine that the final elevati ons of storm sewer pipe outfalls and inlets match the existing field elevations, and provide this information to the engineer at a mutually agreed upon date or least 14 calendar days before ordering in lets, catch basins, manholes, endwalls, and storm sewer pipe. 650.3.3 Subgrade 650.3.3.1 General
system (GPS) machine guidance fo r conventional subgrade staking on all or part of the work. The engineer may require the contra ctor to revert to conventionals ubgrade staking methods for all or part of the work at any point during construction if, in the enginee r's opinion, the GPS machine guidance is producing unacceptable results. 650.3.3.2 Subgrade Staking
intervals of 50 feet, or more frequently, for urban sections. Include additional stakes at each cross-