Contract Time

Defined in the standard specifications of 8 state transportation agencies. Each definition below is the agency’s own text, with the section it comes from — they do not all say the same thing, and on a contract the difference is the point.

Definitions are quoted from state-authored public specification books. This page carries no I-Code-derived terms.

Florida · FDOT

The number of calendar days allowed for completion of the Contract work, including authorized time extensions.

Section 1 — DEFINITIONS AND TERMS
Idaho · ITD

The time allowed by the contract for substantial completion of the work. Contractor (Prime Contractor). The individual, partnership, firm, corporation, or any acceptable combination thereof, contracting with the Department for performance of the work. Contractor -Obligated Defects (CODs). The loss of asphalt or chips, or action simulating the loss of asphalt or chips, due to poor Contractor quality of work and/or materials that diminish the chip seal coat ’s effectiveness and appearance. Some of the most common CODs are described in the Department’s Chip

Section 101 — GENERAL, ABBREVIATIONS, AND DEFINITIONS
Louisiana · LaDOTD

The number of working days or calendar days allowed for completion of the contract, including authorized time extensions. When a calendar date of completion is shown in the contract in lieu of a number of working or calendar days, work shall be completed by that date, including authorized time extensions.

Section 101 — General Information, Definitions, and Terms
Michigan · MDOT

Time specified in the contract to perform and complete all the work, including authorized extensions of time.

Section 101 — Terms, Format, and Definitions
New Hampshire · NHDOT

The Working Days (time) allowed for completion of the Work, or phase of work, or the Completion Date stated in the Contract including authorized time extensions. See 108.07.

Section 101 — DEFINITIONS AND TERMS
Nevada · NDOT

Specified time allowed for completion of the contract. In case a calendar date of completion is shown in the proposal in lieu of the number of working or calendar days, the contract shall be completed by that date.

Section 101 — Terms and Definitions
Tennessee · TDOT

The number of working days or calendar da ys allowed for completion of the Contract or an item(s) of work, or the number of calendar days between the time of starting as determined by the Work Order, and the

Section 101 — DEFINITIONS AND TERMS
Wyoming · WYDOT

Begins 14 Calendar Days after the Award Date and consists of the number of calendar days up to and including the Contract Completion Date. Contractor, a. Any person or business holding prequalification status and bidding or eligible to Bid on a department “Proposal” (Form E-91). Contractor, the. The person or business with whom the Commission or Department enters into agreement through a binding Contract for performance of the specified

Section 101 — Definitions and Terms