Broward County, Florida Building Permit Cost Calculator
Estimates permit cost in Broward County from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.
217 jurisdictions with fee schedules on file
Total cost of work, labor and materials
Used by cities that price per square foot
Fences and retaining walls
Electrical permits priced by the ampere
Building Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Minimum base permit fee Flat fee $125.00 | $125.00 |
Permit fee rate on job value, $1 to $9,999,999.99 3.0% | see rule |
Permit fee rate on job value over $10,000,000.00 2.5% | see rule |
○Permit application processing fee, nonrefundable, paid at application in addition to permit fees Flat fee $125.00 | $125.00 |
○Reinspection for the same violation (1st) Flat fee $100.00 | $100.00 |
Reinspection for the same violation (2nd / 3rd / 4th) $200.00 / $300.00 / $400.00 | see rule |
○Training and continuing education surcharge, per $1.00 of permit and plan review fee Flat fee $0.02 | $0.02 |
○Public awareness surcharge, per $1.00 of permit and plan review fee Flat fee $0.01 | $0.01 |
Florida Department of Commerce surcharge, s. 553.721 F.S. (min $2.00) 1% | see rule |
Building Code Administrators and Inspectors surcharge, s. 468.631(1) F.S. (min $2.00) 1.5% | see rule |
Work without a permit Double Fee | see rule |
○Minimum base roofing permit fee Flat fee $250.00 | $250.00 |
○Certificate of Occupancy / Certificate of Completion / Temporary or Partial CO, per discipline for inspection Flat fee $50.00 | $50.00 |
○Permit extension Flat fee $50.00 | $50.00 |
○Expired permit (minimum) Flat fee $125.00 | $125.00 |
○Change of contractor Flat fee $75.00 | $75.00 |
How this jurisdiction calculates the fee
Fees are set by the Broward County Administrative Code, Chapter 40, Part VI (Building Code Division), sections 40.27 through 40.32, read in the Administrative Code as codified through Supplement 28 (banner: codified through Resolution No. 2026-283, adopted June 9, 2026). Sections 40.29 through 40.32 were last amended by Resolution 2025-038, adopted 2-25-25, effective 5-1-25; section 40.28 by Resolution 2026-27, 2-3-26. Permit fees are the greater of the $125.00 minimum base permit fee ($250.00 minimum base roofing permit fee) or 3.0% of job value for job values of $1 to $9,999,999.99, and 2.5% for job values over $10,000,000.00. Job value is the greater of the RS MEANS Manual (latest edition) figure or the applicant's estimated job value. Permit fees include standard inspections but do not include plan review or reinspections. A nonrefundable $125.00 permit application processing fee is charged at application in addition to applicable permit fees. Reinspection for the same violation is $100.00 and subsequent reinspections are charged in multiples of $100.00 ($200.00, $300.00, $400.00). Surcharges stack on top: training and continuing education at $0.02 per $1.00 of permit and plan review fee, public awareness at $0.005 per $1.00, a Florida Department of Commerce surcharge of 1% under s. 553.721 F.S. (minimum $2.00), and a Building Code Administrators and Inspectors surcharge of 1.5% under s. 468.631(1) F.S. (minimum $2.00). A Board of Rules and Appeals surcharge also applies under section 43.1. Work started without a permit is charged double fee. SUPERSESSION NOTE (2026-09-10): the previously cited PDF at broward.org/Building/Forms/Documents/40.27.___General_Fees_Schedule.pdf now returns HTTP 404 - broward.org has migrated to a new CMS and no longer publishes this schedule as a standalone PDF. The stored figures had been the pre-2025 ones: a 1.85% rate, reinspections at $66/$132/$198/$264, a 1.5% Florida DCA surcharge and no application processing fee. All of those are superseded.
Source: published fee schedule · Verified 9/15/2026
Deck Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Minimum base permit fee Flat fee $125.00 | $125.00 |
Permit fee rate on job value, $1 to $9,999,999.99 3.0% | see rule |
Permit fee rate on job value over $10,000,000.00 2.5% | see rule |
○Permit application processing fee, nonrefundable, paid at application in addition to permit fees Flat fee $125.00 | $125.00 |
○Reinspection for the same violation (1st) Flat fee $100.00 | $100.00 |
Reinspection for the same violation (2nd / 3rd / 4th) $200.00 / $300.00 / $400.00 | see rule |
○Training and continuing education surcharge, per $1.00 of permit and plan review fee Flat fee $0.02 | $0.02 |
○Public awareness surcharge, per $1.00 of permit and plan review fee Flat fee $0.01 | $0.01 |
Florida Department of Commerce surcharge, s. 553.721 F.S. (min $2.00) 1% | see rule |
Building Code Administrators and Inspectors surcharge, s. 468.631(1) F.S. (min $2.00) 1.5% | see rule |
Work without a permit Double Fee | see rule |
How this jurisdiction calculates the fee
Fees are set by the Broward County Administrative Code, Chapter 40, Part VI (Building Code Division), sections 40.27 through 40.32, read in the Administrative Code as codified through Supplement 28 (banner: codified through Resolution No. 2026-283, adopted June 9, 2026). Sections 40.29 through 40.32 were last amended by Resolution 2025-038, adopted 2-25-25, effective 5-1-25; section 40.28 by Resolution 2026-27, 2-3-26. Permit fees are the greater of the $125.00 minimum base permit fee ($250.00 minimum base roofing permit fee) or 3.0% of job value for job values of $1 to $9,999,999.99, and 2.5% for job values over $10,000,000.00. Job value is the greater of the RS MEANS Manual (latest edition) figure or the applicant's estimated job value. Permit fees include standard inspections but do not include plan review or reinspections. A nonrefundable $125.00 permit application processing fee is charged at application in addition to applicable permit fees. Reinspection for the same violation is $100.00 and subsequent reinspections are charged in multiples of $100.00 ($200.00, $300.00, $400.00). Surcharges stack on top: training and continuing education at $0.02 per $1.00 of permit and plan review fee, public awareness at $0.005 per $1.00, a Florida Department of Commerce surcharge of 1% under s. 553.721 F.S. (minimum $2.00), and a Building Code Administrators and Inspectors surcharge of 1.5% under s. 468.631(1) F.S. (minimum $2.00). A Board of Rules and Appeals surcharge also applies under section 43.1. Work started without a permit is charged double fee. SUPERSESSION NOTE (2026-09-10): the previously cited PDF at broward.org/Building/Forms/Documents/40.27.___General_Fees_Schedule.pdf now returns HTTP 404 - broward.org has migrated to a new CMS and no longer publishes this schedule as a standalone PDF. The stored figures had been the pre-2025 ones: a 1.85% rate, reinspections at $66/$132/$198/$264, a 1.5% Florida DCA surcharge and no application processing fee. All of those are superseded.
Source: published fee schedule · Verified 9/15/2026
Electrical Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Minimum base permit fee Flat fee $125.00 | $125.00 |
Permit fee rate on job value, $1 to $9,999,999.99 3.0% | see rule |
Permit fee rate on job value over $10,000,000.00 2.5% | see rule |
○Permit application processing fee, nonrefundable, paid at application in addition to permit fees Flat fee $125.00 | $125.00 |
○Reinspection for the same violation (1st) Flat fee $100.00 | $100.00 |
Reinspection for the same violation (2nd / 3rd / 4th) $200.00 / $300.00 / $400.00 | see rule |
○Training and continuing education surcharge, per $1.00 of permit and plan review fee Flat fee $0.02 | $0.02 |
○Public awareness surcharge, per $1.00 of permit and plan review fee Flat fee $0.01 | $0.01 |
Florida Department of Commerce surcharge, s. 553.721 F.S. (min $2.00) 1% | see rule |
Building Code Administrators and Inspectors surcharge, s. 468.631(1) F.S. (min $2.00) 1.5% | see rule |
Work without a permit Double Fee | see rule |
How this jurisdiction calculates the fee
Fees are set by the Broward County Administrative Code, Chapter 40, Part VI (Building Code Division), sections 40.27 through 40.32, read in the Administrative Code as codified through Supplement 28 (banner: codified through Resolution No. 2026-283, adopted June 9, 2026). Sections 40.29 through 40.32 were last amended by Resolution 2025-038, adopted 2-25-25, effective 5-1-25; section 40.28 by Resolution 2026-27, 2-3-26. Permit fees are the greater of the $125.00 minimum base permit fee ($250.00 minimum base roofing permit fee) or 3.0% of job value for job values of $1 to $9,999,999.99, and 2.5% for job values over $10,000,000.00. Job value is the greater of the RS MEANS Manual (latest edition) figure or the applicant's estimated job value. Permit fees include standard inspections but do not include plan review or reinspections. A nonrefundable $125.00 permit application processing fee is charged at application in addition to applicable permit fees. Reinspection for the same violation is $100.00 and subsequent reinspections are charged in multiples of $100.00 ($200.00, $300.00, $400.00). Surcharges stack on top: training and continuing education at $0.02 per $1.00 of permit and plan review fee, public awareness at $0.005 per $1.00, a Florida Department of Commerce surcharge of 1% under s. 553.721 F.S. (minimum $2.00), and a Building Code Administrators and Inspectors surcharge of 1.5% under s. 468.631(1) F.S. (minimum $2.00). A Board of Rules and Appeals surcharge also applies under section 43.1. Work started without a permit is charged double fee. SUPERSESSION NOTE (2026-09-10): the previously cited PDF at broward.org/Building/Forms/Documents/40.27.___General_Fees_Schedule.pdf now returns HTTP 404 - broward.org has migrated to a new CMS and no longer publishes this schedule as a standalone PDF. The stored figures had been the pre-2025 ones: a 1.85% rate, reinspections at $66/$132/$198/$264, a 1.5% Florida DCA surcharge and no application processing fee. All of those are superseded. 2026-09-17 (lane B run 1390, pipeline run 94): all eleven stored figures re-verified verbatim. library.municode.com serves an Angular shell to curl and was rendered with headless Chromium (4,060 lines), returning full section text. Broward County Administrative Code s. 40.27 General Fees Schedule carries the amendment history "(2004-490, 5-25-04; ... 2024-062, 2-20-24; 2025-038, 2-25-25, eff. 5-1-25; 2026-27, 2-3-26)" - the current edition, last amended 2-3-26, no successor. Confirmed present: minimum permit fee $125.00, permit application processing fee $125.00, reinspection $100.00 with 2nd/3rd/4th at $200.00/$300.00/$400.00, training and continuing education $0.02 per $1.00 of permit and plan review fee, public awareness $0.005, and the s.553.721 (1%) and s.468.631(1) (1.5%) Florida surcharges with their $2.00 minimums. FLORIDA HB 803 CHECK, NEGATIVE FOR THIS ROW: s.40.27(d)(12) DOES price private providers (inspections-only reduces the permit fee by $100.00 per inspection; plan-review-and-inspections is billed hourly at $37.70 clerical / $99.80 Building Official), but NONE of those lines is among our stored examples, so HB 803's invalidation of private-provider fees does not touch any stored Broward figure.
Source: published fee schedule · Verified 9/17/2026
Fence Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Minimum base permit fee Flat fee $125.00 | $125.00 |
Permit fee rate on job value, $1 to $9,999,999.99 3.0% | see rule |
Permit fee rate on job value over $10,000,000.00 2.5% | see rule |
○Permit application processing fee, nonrefundable, paid at application in addition to permit fees Flat fee $125.00 | $125.00 |
○Reinspection for the same violation (1st) Flat fee $100.00 | $100.00 |
Reinspection for the same violation (2nd / 3rd / 4th) $200.00 / $300.00 / $400.00 | see rule |
○Training and continuing education surcharge, per $1.00 of permit and plan review fee Flat fee $0.02 | $0.02 |
○Public awareness surcharge, per $1.00 of permit and plan review fee Flat fee $0.01 | $0.01 |
Florida Department of Commerce surcharge, s. 553.721 F.S. (min $2.00) 1% | see rule |
Building Code Administrators and Inspectors surcharge, s. 468.631(1) F.S. (min $2.00) 1.5% | see rule |
Work without a permit Double Fee | see rule |
How this jurisdiction calculates the fee
Fees are set by the Broward County Administrative Code, Chapter 40, Part VI (Building Code Division), sections 40.27 through 40.32, read in the Administrative Code as codified through Supplement 28 (banner: codified through Resolution No. 2026-283, adopted June 9, 2026). Sections 40.29 through 40.32 were last amended by Resolution 2025-038, adopted 2-25-25, effective 5-1-25; section 40.28 by Resolution 2026-27, 2-3-26. Permit fees are the greater of the $125.00 minimum base permit fee ($250.00 minimum base roofing permit fee) or 3.0% of job value for job values of $1 to $9,999,999.99, and 2.5% for job values over $10,000,000.00. Job value is the greater of the RS MEANS Manual (latest edition) figure or the applicant's estimated job value. Permit fees include standard inspections but do not include plan review or reinspections. A nonrefundable $125.00 permit application processing fee is charged at application in addition to applicable permit fees. Reinspection for the same violation is $100.00 and subsequent reinspections are charged in multiples of $100.00 ($200.00, $300.00, $400.00). Surcharges stack on top: training and continuing education at $0.02 per $1.00 of permit and plan review fee, public awareness at $0.005 per $1.00, a Florida Department of Commerce surcharge of 1% under s. 553.721 F.S. (minimum $2.00), and a Building Code Administrators and Inspectors surcharge of 1.5% under s. 468.631(1) F.S. (minimum $2.00). A Board of Rules and Appeals surcharge also applies under section 43.1. Work started without a permit is charged double fee. SUPERSESSION NOTE (2026-09-10): the previously cited PDF at broward.org/Building/Forms/Documents/40.27.___General_Fees_Schedule.pdf now returns HTTP 404 - broward.org has migrated to a new CMS and no longer publishes this schedule as a standalone PDF. The stored figures had been the pre-2025 ones: a 1.85% rate, reinspections at $66/$132/$198/$264, a 1.5% Florida DCA surcharge and no application processing fee. All of those are superseded. 2026-09-17 (lane B run 1390, pipeline run 94): all eleven stored figures re-verified verbatim. library.municode.com serves an Angular shell to curl and was rendered with headless Chromium (4,060 lines), returning full section text. Broward County Administrative Code s. 40.27 General Fees Schedule carries the amendment history "(2004-490, 5-25-04; ... 2024-062, 2-20-24; 2025-038, 2-25-25, eff. 5-1-25; 2026-27, 2-3-26)" - the current edition, last amended 2-3-26, no successor. Confirmed present: minimum permit fee $125.00, permit application processing fee $125.00, reinspection $100.00 with 2nd/3rd/4th at $200.00/$300.00/$400.00, training and continuing education $0.02 per $1.00 of permit and plan review fee, public awareness $0.005, and the s.553.721 (1%) and s.468.631(1) (1.5%) Florida surcharges with their $2.00 minimums. FLORIDA HB 803 CHECK, NEGATIVE FOR THIS ROW: s.40.27(d)(12) DOES price private providers (inspections-only reduces the permit fee by $100.00 per inspection; plan-review-and-inspections is billed hourly at $37.70 clerical / $99.80 Building Official), but NONE of those lines is among our stored examples, so HB 803's invalidation of private-provider fees does not touch any stored Broward figure.
Source: published fee schedule · Verified 9/17/2026
Reroof Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Minimum base roofing permit fee Flat fee $250.00 | $250.00 |
○Minimum base permit fee Flat fee $125.00 | $125.00 |
Permit fee rate on job value, $1 to $9,999,999.99 3.0% | see rule |
Permit fee rate on job value over $10,000,000.00 2.5% | see rule |
○Permit application processing fee, nonrefundable, paid at application in addition to permit fees Flat fee $125.00 | $125.00 |
○Reinspection for the same violation (1st) Flat fee $100.00 | $100.00 |
Reinspection for the same violation (2nd / 3rd / 4th) $200.00 / $300.00 / $400.00 | see rule |
○Training and continuing education surcharge, per $1.00 of permit and plan review fee Flat fee $0.02 | $0.02 |
○Public awareness surcharge, per $1.00 of permit and plan review fee Flat fee $0.01 | $0.01 |
Florida Department of Commerce surcharge, s. 553.721 F.S. (min $2.00) 1% | see rule |
Building Code Administrators and Inspectors surcharge, s. 468.631(1) F.S. (min $2.00) 1.5% | see rule |
Work without a permit Double Fee | see rule |
How this jurisdiction calculates the fee
Fees are set by the Broward County Administrative Code, Chapter 40, Part VI (Building Code Division), sections 40.27 through 40.32, read in the Administrative Code as codified through Supplement 28 (banner: codified through Resolution No. 2026-283, adopted June 9, 2026). Sections 40.29 through 40.32 were last amended by Resolution 2025-038, adopted 2-25-25, effective 5-1-25; section 40.28 by Resolution 2026-27, 2-3-26. Permit fees are the greater of the $125.00 minimum base permit fee ($250.00 minimum base roofing permit fee) or 3.0% of job value for job values of $1 to $9,999,999.99, and 2.5% for job values over $10,000,000.00. Job value is the greater of the RS MEANS Manual (latest edition) figure or the applicant's estimated job value. Permit fees include standard inspections but do not include plan review or reinspections. A nonrefundable $125.00 permit application processing fee is charged at application in addition to applicable permit fees. Reinspection for the same violation is $100.00 and subsequent reinspections are charged in multiples of $100.00 ($200.00, $300.00, $400.00). Surcharges stack on top: training and continuing education at $0.02 per $1.00 of permit and plan review fee, public awareness at $0.005 per $1.00, a Florida Department of Commerce surcharge of 1% under s. 553.721 F.S. (minimum $2.00), and a Building Code Administrators and Inspectors surcharge of 1.5% under s. 468.631(1) F.S. (minimum $2.00). A Board of Rules and Appeals surcharge also applies under section 43.1. Work started without a permit is charged double fee. SUPERSESSION NOTE (2026-09-10): the previously cited PDF at broward.org/Building/Forms/Documents/40.27.___General_Fees_Schedule.pdf now returns HTTP 404 - broward.org has migrated to a new CMS and no longer publishes this schedule as a standalone PDF. The stored figures had been the pre-2025 ones: a 1.85% rate, reinspections at $66/$132/$198/$264, a 1.5% Florida DCA surcharge and no application processing fee. All of those are superseded.
Source: published fee schedule · Verified 9/15/2026
Retaining Wall Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Minimum base permit fee Flat fee $125.00 | $125.00 |
Permit fee rate on job value, $1 to $9,999,999.99 3.0% | see rule |
Permit fee rate on job value over $10,000,000.00 2.5% | see rule |
○Permit application processing fee, nonrefundable, paid at application in addition to permit fees Flat fee $125.00 | $125.00 |
○Reinspection for the same violation (1st) Flat fee $100.00 | $100.00 |
Reinspection for the same violation (2nd / 3rd / 4th) $200.00 / $300.00 / $400.00 | see rule |
○Training and continuing education surcharge, per $1.00 of permit and plan review fee Flat fee $0.02 | $0.02 |
○Public awareness surcharge, per $1.00 of permit and plan review fee Flat fee $0.01 | $0.01 |
Florida Department of Commerce surcharge, s. 553.721 F.S. (min $2.00) 1% | see rule |
Building Code Administrators and Inspectors surcharge, s. 468.631(1) F.S. (min $2.00) 1.5% | see rule |
Work without a permit Double Fee | see rule |
How this jurisdiction calculates the fee
Fees are set by the Broward County Administrative Code, Chapter 40, Part VI (Building Code Division), sections 40.27 through 40.32, read in the Administrative Code as codified through Supplement 28 (banner: codified through Resolution No. 2026-283, adopted June 9, 2026). Sections 40.29 through 40.32 were last amended by Resolution 2025-038, adopted 2-25-25, effective 5-1-25; section 40.28 by Resolution 2026-27, 2-3-26. Permit fees are the greater of the $125.00 minimum base permit fee ($250.00 minimum base roofing permit fee) or 3.0% of job value for job values of $1 to $9,999,999.99, and 2.5% for job values over $10,000,000.00. Job value is the greater of the RS MEANS Manual (latest edition) figure or the applicant's estimated job value. Permit fees include standard inspections but do not include plan review or reinspections. A nonrefundable $125.00 permit application processing fee is charged at application in addition to applicable permit fees. Reinspection for the same violation is $100.00 and subsequent reinspections are charged in multiples of $100.00 ($200.00, $300.00, $400.00). Surcharges stack on top: training and continuing education at $0.02 per $1.00 of permit and plan review fee, public awareness at $0.005 per $1.00, a Florida Department of Commerce surcharge of 1% under s. 553.721 F.S. (minimum $2.00), and a Building Code Administrators and Inspectors surcharge of 1.5% under s. 468.631(1) F.S. (minimum $2.00). A Board of Rules and Appeals surcharge also applies under section 43.1. Work started without a permit is charged double fee. SUPERSESSION NOTE (2026-09-10): the previously cited PDF at broward.org/Building/Forms/Documents/40.27.___General_Fees_Schedule.pdf now returns HTTP 404 - broward.org has migrated to a new CMS and no longer publishes this schedule as a standalone PDF. The stored figures had been the pre-2025 ones: a 1.85% rate, reinspections at $66/$132/$198/$264, a 1.5% Florida DCA surcharge and no application processing fee. All of those are superseded.
Source: published fee schedule · Verified 9/15/2026
Shed Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Minimum base permit fee Flat fee $125.00 | $125.00 |
Permit fee rate on job value, $1 to $9,999,999.99 3.0% | see rule |
Permit fee rate on job value over $10,000,000.00 2.5% | see rule |
○Permit application processing fee, nonrefundable, paid at application in addition to permit fees Flat fee $125.00 | $125.00 |
○Reinspection for the same violation (1st) Flat fee $100.00 | $100.00 |
Reinspection for the same violation (2nd / 3rd / 4th) $200.00 / $300.00 / $400.00 | see rule |
○Training and continuing education surcharge, per $1.00 of permit and plan review fee Flat fee $0.02 | $0.02 |
○Public awareness surcharge, per $1.00 of permit and plan review fee Flat fee $0.01 | $0.01 |
Florida Department of Commerce surcharge, s. 553.721 F.S. (min $2.00) 1% | see rule |
Building Code Administrators and Inspectors surcharge, s. 468.631(1) F.S. (min $2.00) 1.5% | see rule |
Work without a permit Double Fee | see rule |
How this jurisdiction calculates the fee
Fees are set by the Broward County Administrative Code, Chapter 40, Part VI (Building Code Division), sections 40.27 through 40.32, read in the Administrative Code as codified through Supplement 28 (banner: codified through Resolution No. 2026-283, adopted June 9, 2026). Sections 40.29 through 40.32 were last amended by Resolution 2025-038, adopted 2-25-25, effective 5-1-25; section 40.28 by Resolution 2026-27, 2-3-26. Permit fees are the greater of the $125.00 minimum base permit fee ($250.00 minimum base roofing permit fee) or 3.0% of job value for job values of $1 to $9,999,999.99, and 2.5% for job values over $10,000,000.00. Job value is the greater of the RS MEANS Manual (latest edition) figure or the applicant's estimated job value. Permit fees include standard inspections but do not include plan review or reinspections. A nonrefundable $125.00 permit application processing fee is charged at application in addition to applicable permit fees. Reinspection for the same violation is $100.00 and subsequent reinspections are charged in multiples of $100.00 ($200.00, $300.00, $400.00). Surcharges stack on top: training and continuing education at $0.02 per $1.00 of permit and plan review fee, public awareness at $0.005 per $1.00, a Florida Department of Commerce surcharge of 1% under s. 553.721 F.S. (minimum $2.00), and a Building Code Administrators and Inspectors surcharge of 1.5% under s. 468.631(1) F.S. (minimum $2.00). A Board of Rules and Appeals surcharge also applies under section 43.1. Work started without a permit is charged double fee. SUPERSESSION NOTE (2026-09-10): the previously cited PDF at broward.org/Building/Forms/Documents/40.27.___General_Fees_Schedule.pdf now returns HTTP 404 - broward.org has migrated to a new CMS and no longer publishes this schedule as a standalone PDF. The stored figures had been the pre-2025 ones: a 1.85% rate, reinspections at $66/$132/$198/$264, a 1.5% Florida DCA surcharge and no application processing fee. All of those are superseded. 2026-09-17 (lane B run 1390, pipeline run 94): all eleven stored figures re-verified verbatim. library.municode.com serves an Angular shell to curl and was rendered with headless Chromium (4,060 lines), returning full section text. Broward County Administrative Code s. 40.27 General Fees Schedule carries the amendment history "(2004-490, 5-25-04; ... 2024-062, 2-20-24; 2025-038, 2-25-25, eff. 5-1-25; 2026-27, 2-3-26)" - the current edition, last amended 2-3-26, no successor. Confirmed present: minimum permit fee $125.00, permit application processing fee $125.00, reinspection $100.00 with 2nd/3rd/4th at $200.00/$300.00/$400.00, training and continuing education $0.02 per $1.00 of permit and plan review fee, public awareness $0.005, and the s.553.721 (1%) and s.468.631(1) (1.5%) Florida surcharges with their $2.00 minimums. FLORIDA HB 803 CHECK, NEGATIVE FOR THIS ROW: s.40.27(d)(12) DOES price private providers (inspections-only reduces the permit fee by $100.00 per inspection; plan-review-and-inspections is billed hourly at $37.70 clerical / $99.80 Building Official), but NONE of those lines is among our stored examples, so HB 803's invalidation of private-provider fees does not touch any stored Broward figure.
Source: published fee schedule · Verified 9/17/2026
Water Heater Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Minimum base permit fee Flat fee $125.00 | $125.00 |
Permit fee rate on job value, $1 to $9,999,999.99 3.0% | see rule |
Permit fee rate on job value over $10,000,000.00 2.5% | see rule |
○Permit application processing fee, nonrefundable, paid at application in addition to permit fees Flat fee $125.00 | $125.00 |
○Reinspection for the same violation (1st) Flat fee $100.00 | $100.00 |
Reinspection for the same violation (2nd / 3rd / 4th) $200.00 / $300.00 / $400.00 | see rule |
○Training and continuing education surcharge, per $1.00 of permit and plan review fee Flat fee $0.02 | $0.02 |
○Public awareness surcharge, per $1.00 of permit and plan review fee Flat fee $0.01 | $0.01 |
Florida Department of Commerce surcharge, s. 553.721 F.S. (min $2.00) 1% | see rule |
Building Code Administrators and Inspectors surcharge, s. 468.631(1) F.S. (min $2.00) 1.5% | see rule |
Work without a permit Double Fee | see rule |
How this jurisdiction calculates the fee
Fees are set by the Broward County Administrative Code, Chapter 40, Part VI (Building Code Division), sections 40.27 through 40.32, read in the Administrative Code as codified through Supplement 28 (banner: codified through Resolution No. 2026-283, adopted June 9, 2026). Sections 40.29 through 40.32 were last amended by Resolution 2025-038, adopted 2-25-25, effective 5-1-25; section 40.28 by Resolution 2026-27, 2-3-26. Permit fees are the greater of the $125.00 minimum base permit fee ($250.00 minimum base roofing permit fee) or 3.0% of job value for job values of $1 to $9,999,999.99, and 2.5% for job values over $10,000,000.00. Job value is the greater of the RS MEANS Manual (latest edition) figure or the applicant's estimated job value. Permit fees include standard inspections but do not include plan review or reinspections. A nonrefundable $125.00 permit application processing fee is charged at application in addition to applicable permit fees. Reinspection for the same violation is $100.00 and subsequent reinspections are charged in multiples of $100.00 ($200.00, $300.00, $400.00). Surcharges stack on top: training and continuing education at $0.02 per $1.00 of permit and plan review fee, public awareness at $0.005 per $1.00, a Florida Department of Commerce surcharge of 1% under s. 553.721 F.S. (minimum $2.00), and a Building Code Administrators and Inspectors surcharge of 1.5% under s. 468.631(1) F.S. (minimum $2.00). A Board of Rules and Appeals surcharge also applies under section 43.1. Work started without a permit is charged double fee. SUPERSESSION NOTE (2026-09-10): the previously cited PDF at broward.org/Building/Forms/Documents/40.27.___General_Fees_Schedule.pdf now returns HTTP 404 - broward.org has migrated to a new CMS and no longer publishes this schedule as a standalone PDF. The stored figures had been the pre-2025 ones: a 1.85% rate, reinspections at $66/$132/$198/$264, a 1.5% Florida DCA surcharge and no application processing fee. All of those are superseded. 2026-09-17 (lane B run 1390, pipeline run 94): all eleven stored figures re-verified verbatim. library.municode.com serves an Angular shell to curl and was rendered with headless Chromium (4,060 lines), returning full section text. Broward County Administrative Code s. 40.27 General Fees Schedule carries the amendment history "(2004-490, 5-25-04; ... 2024-062, 2-20-24; 2025-038, 2-25-25, eff. 5-1-25; 2026-27, 2-3-26)" - the current edition, last amended 2-3-26, no successor. Confirmed present: minimum permit fee $125.00, permit application processing fee $125.00, reinspection $100.00 with 2nd/3rd/4th at $200.00/$300.00/$400.00, training and continuing education $0.02 per $1.00 of permit and plan review fee, public awareness $0.005, and the s.553.721 (1%) and s.468.631(1) (1.5%) Florida surcharges with their $2.00 minimums. FLORIDA HB 803 CHECK, NEGATIVE FOR THIS ROW: s.40.27(d)(12) DOES price private providers (inspections-only reduces the permit fee by $100.00 per inspection; plan-review-and-inspections is billed hourly at $37.70 clerical / $99.80 Building Official), but NONE of those lines is among our stored examples, so HB 803's invalidation of private-provider fees does not touch any stored Broward figure.
Source: published fee schedule · Verified 9/17/2026
See the full write-up: Broward County building permit cost
Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.