278 ALASKA 2020 SECTION 550
550-1.01 DESCRIPTION . Furnish, place, finish, and cure Portland cement concrete for
manholes, inlets, sidewalk, curb, gutter and other minor structures and incidental construction as shown on the Plans.
550-2.01 MATERIALS. Use materials conforming to Subsection 501- 2.01.
550-2.02 COMPOSITION OF MIXTURE – JOB MI X DESIGN. Provide a Job Mix Design, JMD,
meeting the requirements of Table 550- 1 for each class of concrete included in the Contract. TABLE 550 -1 COMMERCIAL CONCRETE DESIGN REQUIREMENTS Class B W Water -Cement Ratio, lbs/lbs, maximum 0.45 0.50 Total Air Content, % 5.5 – 6.5 4.0 – 6.5 Coarse Aggregate Gradation, AASHTO M 43 No. 57 or 67 No. 7, 8, 57, or 67 Compressive Strength, psi, minimum 4,000 3,000 Alternative sizes of coarse aggregate, as shown in AASHTO M 43, may be used when approved in writing. Calculate the water -cement ratio based on the total weights of all water and all cementitious material. Portland cement, blended hydraulic cement, fly ash, ground granulated blast -furnace slag, and silica fume are cementitious materials. Fly ash, ground granulated blast -furnace slag, silica fume, and combinations of these materials may be used as a substitute for Portland cement provided the quantity meets the limits of Table
550-2 and the total combined quantity of fly ash, ground granulated blast -furnace slag, and silica
fume does not exceed 40 percent of the total cementitious materi al by weight. TABLE 550 -2 SUPPLEMENTARY CEMENT ITIOUS MATERIAL LIMI TS Material Max. Percent Fly Ash 35% Ground Granulated Blast -Furnace Slag 40% Silica Fume 10% Maximum percent includes initial quantities in blended cement plus supplementary cementitious materials.
550-3.01 BATCHING, M IXING, AND DELIVERY. Batch concrete according to the approved
JMD. Mix ingredients into a thoroughly intermingled uniform mixture. Hand mixing is not allowed. Do not retemper concrete mixtures except that additional water may be added on- site provided the total amount of water, including that added on site, is within the proportion tolerances of 550- 3.02. Account for the actual volume of concrete remaining in the mix er. Complete all water additions within 30 minutes of the introduction of mixing water to the cementitious materials. If additional water is added, provide additional mixing to ensure a thoroughly intermingled uniform mixture is attained. Discharge the concrete within 1.5 hours of adding the mixing water to the cementitious materials, and within 1.5 hours of adding the cementitious materials to the aggregates. The Engineer may extend the time for placement if provided for in the approved JMD.
550-3.02 EVALU ATION OF MATERIAL FO R ACCEPTANCE. The Engineer may accept
concrete based on conformance with the approved JMD according to this Subsection. Sampling SECTION 5 50 280 ALASKA 2020 and testing is not required for acceptance. However, the Engineer reserves the right to sample, test, eva luate, and reject concrete according to Subsection 501- 3.03.
550-3.03 PLACING CON CRETE. Prepar e foundations according to Section 204 or as specified
for the applicable pay item. Use forms designed and constructed according to Section 512 or as specified for the applicable pay item. Ensure forms, reinforcing steel, and other embedded items are free of concrete splatter and other foreign material. Remove standing water from within the forms. Moisten foundations and forms with water before the concrete is placed. Prevent movement of forms, reinforcing steel, and other embedded items. Ensure the concret e temperature is between 50°F and 90°F when placed. Place and consolidate each layer before the preceding layer takes initial set. Limit layer thickness to the capacity of the vibrators to consolidate and merge the concrete with the previous layer. Do not place concrete that has developed initial set. Place concrete as near as possible to its final position. Prevent segregation of the mix. Do not deposit a large quantity of concrete and run or work the concrete along the forms. Limit the free- fall height of the concrete to less than 5 feet. When pumping concrete use a pump producing a continuous stream of concrete without air pockets.
550-3.04 CONSOLIDATI ON OF CONCRETE. Consolidate fresh concrete within 15 minutes of
placement. Consolidate concrete using mechanical vibrators to make an impervious, dense, homogeneous mass free of voids and rock pockets. Vibrate in a uniform pattern spaced less than 1.5 times the radius of visible effectiveness. Effectively vibrate the full depth of each layer. Do not vibrate concrete that has initially set. Do not hold vibrators against reinforcing steel or use vibrators to flow or spread the concrete into place. Do not allow the concrete to segregate, form pools of mortar, or form laitance on the surface.
550-3.05 FINISHING C ONCRETE SURFACES. After the concrete is consolidated and prior to
the application of curing materials, strike- off unformed concrete surfaces to the required elevation and slope. Finish the surface by floating to remove local irregularities. Leave sufficient mortar to seal the concrete surface. Do not use mortar topping for concrete surfaces. Do not use aluminum finishing equipment. Complete initial floating operations before bleed water or excess moisture is present on the surface and before the concrete de velops initial set. Complete final finishing before final set occurs. Do not use finishing aids or additional water to assist in finishing concrete surfaces. Do not finish concrete surfaces if bleed water is present.
550-3.06 CURING CONCRETE. Begin curing immediately after final finishing. Maintain curing for
at least 72 hours. During the curing period, keep the conc rete at a satisfactory moisture content and at a temperature of at least 50°F.
550-3.07 PROTECTION OF CONCRETE. Protect concrete from damage. Do not apply loads to
the concrete until curing operations are completed and until the concrete has attained sufficient strength to safely carry the applied loads without damage. Forms may be removed after the concrete has cured for at least 24 hours and will not be damaged. Remove and replace concrete damaged by rain, flowing water, frost action, or overheating at no cost to the Department.
550-3.08 ANCHOR BOLT S, DUCTS, PIPES, AND CONDUITS. When anchor bolts, ducts, pipes,
or conduits will be encased in concrete, secure them in the forms before placing the concrete. When installing anchor bolts in pipe sleeves, pre- cast holes, cored holes, or drilled holes, completely fill the cavity with grout meeting Subsection 701- 2.03.
550-4.01 METHOD OF M EASUREMENT. See Section 109 and the following.
Cubic Yard. The lesser of the actual volume placed or neat line volume of concrete accepted i n place.
550-5.01 BASIS OF PA YMENT. If Items 550.0001.____, 550.0002.____, 550.0003.____, or
550.0004.____ do not appear in the Bid Schedule concrete is subsidiary to other items. Material not appearing in the Bid Schedule and is contained within, embedded, or attached to concrete elements is subsidiary. Repairing unacceptable concrete is subsidiary. Payment will be made under: PAY ITEM Item Number Item Description Unit 550.0001.____ Class B Concrete LS 550.0002.____ Class W Concrete LS 550.0003.____ Class B Concrete CY 550.0004.____ Class W Concrete CY 284 ALASKA 2020 DIVISION 600 –MISCELLANEOUS CONSTRUCTION SECTION 601 METAL FLUME DOWNDRAI NS
601-1.01 DESCRIPTION. Furnish and install tapered inlet assemblies, metal flume downdrains,
and anchor assemblies, at the locations shown on the Plans.
601-2.01 MATERIALS. Fabricate tapered inlets and flume downdrains using any one of the base
metals listed in AASHTO M 36 or AASHTO M 196. Use a minimum sheet thickness of 0.060 inches. Use steel nuts and bolts, galvanized acc ording to AASHTO M 232.
601-3.01 CONSTRUCTIO N REQUIREMENTS. Fabricate downdrains according to the details
and dimensions shown on the Plans. Weld bulkheads and flume pieces to the inlet assembly to form watertight connections. Do not use dissimilar metal at any one installation. Anchor assemblies shown on the Plans may be used with an aluminum installation if the anchor assemblies are electrically insulated. Connect flume downdrain sections together and to the inlet assembly using galvanized bolts as show n on the Plans.
601-4.01 METHOD OF M EASUREMENT. See Section 109, measured along the invert from the
lower end of the inlet assembly, not including flume stub, to the lower end of the flume.
601-5.01 BASIS OF PA YMENT. The contract price includes the inlet, anchor assemblies,
miscellaneous hardware, and excavation for the installation. Payment will be made under: PAY ITEM Item Number Item Description Unit 601.0001.____ Metal Flume Downdrain LF