640MOBILIZATION AND DEMOBILIZATION

AK · 2020 Standard SpecificationsBook pages 393394View official source ↗

365 ALASKA 2020 SECTION 640 MOBILIZATION AND DEM OBILIZATION

640-1.01 DESCRIPTION . Perform work and operations necessary to:

1.move personnel, equipment, supplies, and incidentals to the project site;
2.establish of fices, buildings, and other facilities, except as provided under Section 644;
3.perform other work and operations and pay costs incurred, before beginning construction;
4.complete similar demobilization activities; and
5.furnish required submittals such as as -builts, certificates, payrolls, civil rights reports, and equipment warranties.
6.comply with the Alaska Department of Labor and Workforce Development (DOLWD) requirements for Worker Meals and Lodging, or Per Diem; as described in the Laborers’ and Mechanics ’ Minimum Rates of Pay (Pamphlet 600), current issue. On Federal -aid projects, PL 109- 59, 119 STAT. 1233, Sec. 1409(c) also applies.
7.ensure subcontractors comply with the Federal and State DOLWD requirements. Ensure facilities meet the Alaska Administrat ive Code 8 AAC 61.1010 and 8 AAC 61.1040 Occupational Safety and Health Standards, 18 AAC 31 Alaska Food Code, and U. S. Code of Federal Regulations 29 CFR Section 1910.142 Temporary Labor Camps. Do not consider the cost of Meals and Lodging, or Per Diem i n setting wages for the worker or in meeting wage requirements under AS 23.10.065 or AS 36.05.

640-2.01 MATERIALS. None.

640-3.01 CONSTRUCTIO N REQUIREMENTS. None.

640-4.01 Method of M Easurement.

Numbered items 1. through 4. apply only to items 640.0001. and 640.0002. :

1.When you earn 4 percent of the original contract amount from other bid items: 40 percent of the amount bid for mobilization and demobilization, or 4 percent of the original contract amount, whichever is less, will be paid.
2.When you ear n a total of 8 percent of the original contract amount from other bid items: An additional 40 percent of the amount bid for mobilization and demobilization, or an additional 4 percent of the original contract amount, whichever is less, will be paid.
3.The re maining balance of the amount bid for Mobilization and Demobilization will be paid after all submittals required under the Contract are received and approved.
4.Progress payments for Worker Meals and Lodging, or Per Diem will be computed as equivalent to the percentage, rounded to the nearest whole percent, of the original contract amount earned. Under Item 640.0005, the pay unit is calculated by calendar day. 366 ALASKA 2020 640-5.01 BASIS OF PA YMENT . Payment will be made under: PAY ITEM Item Number Item Description Unit 640.0001.____ Mobilization and Demobilization LS 640.0004.____ Worker Meals and Lodging, or Per Diem LS 640.0005.____ Worker Meals and Lodging, or Per Diem CDAY 367 ALASKA 2020 SECTION 641 EROSION, SEDIMENT, A ND POLLUTION CONTROL

641-1.01 DESCRIPTION . Provide proj ect administration and Work relating to control of erosion,

sedimentation, and discharge of pollutants, according to this section and applicable local, state, and federal requirem ents, including the APDES Construction General Permit. The state APDES program is administered by DEC. Section 301(a) of the Clean Water Act (CWA) and 18 AAC 83.015 provide that the discharge of pollutants to water of the U.S. is unlawful except as allowed by the CGP.

641-1.02 DEFINITION S. These definitions apply only to Section 641.

ACTIVE TREATMENT SYSTEM (ATS) OPERATOR . The Contractor’s qualified representative who is responsible for maintaining and operating an active treatment system (as defined in the CGP) for stormwater runoff. ALASKA CERTIFIED ERO SION AND SEDIMENT CO NTROL LEAD (AK -CESCL). A person who has completed training, testing, and other requirements of, and is currently certified as, an AK-CESCL from an AK -CESCL Training Program (a program developed under a Memorandum of Understanding between the Department and ot hers). The Department recognizes AK -CESCLs as “qualified personnel” required by the CGP. An AK -CESCL must be recertified every three years. (See Qualified Person.) ALASKA DEPARTMENT OF ENVIRONMENTAL CONSE RVATION (DEC). The state agency authorized by EPA t o administer the Clean Water Act’s National Pollutant Discharge Elimination System. ALASKA POLLUTANT DIS CHARGE ELIMINATION S YSTEM (APDES). A system administered by DEC that issues and tracks permits for stormwater discharges. BEST MANAGEMENT PRAC TICES (BMP S). Temporary or permanent structural and non- structural devices, schedules of activities, prohibition of practices, maintenance procedures, and other management practices to prevent or minimize the discharge of pollutants to waters of the United States. BMPs also include, but are not limited to, treatment requirements, operating procedures, and practices to control plant site runoff, spillage or leaks, sludge or waste disposal, or drainage from material storage. CLEAN WATER ACT (CWA ). Federal Water Pollution Control Amendments of 1972, as amended (33 U.S.C. 1251 et seq.). CONSTRUCTION ACTIVIT Y. Physical activity by the Contractor, Subcontractor or utility company; that may result in erosion, sedimentation, or a discharge of pollutants into stormwater. Construction Activity includes soil disturbing activities (e.g. clearing, grubbing, grading, excavating); and establishment of construction materials or equipment storage or maintenance areas (e.g. material piles, borrow area, concrete truck chute washdown, f ueling); and industrial activities that may discharge stormwater and are directly related to the construction process (e.g. concrete or asphalt batch plants). CONSTRUCTION GENERAL PERMIT (CGP). The permit authorizing stormwater discharges from Construction Activities, issued and enforced by Alaska DEC. It authorizes stormwater discharges provided permit conditions and water quality standards are met. CORPS OF ENGINEERS PERMIT (COE PERMIT). A U.S. Army Corps of Engineers Permit for construction in waters of the US. Such permit may be issued under Section 10 of the Rivers and Harbors Act of 1899, or Section 404 of the Clean Water Act.

Source: Alaska Standard Specifications for Highway Construction, 2020 Edition. Pages 393394 of 584.