108Mobilization and Demobilization

MD · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 253–254 Save this section

Ask about Section 108

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

108 — MOBILIZATION AND DEMOBILIZATION 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 108 — MOBILIZATION AND DEMOBILIZATION

108.01 Description

Construction preparatory and closing (clean-up) operations that include the movement of personnel, supplies, materials, tools, equipment, and incidentals to, within, and away from the project site collectively for the project and for individual work operations; and the establishment and removal/decommissioning of the Contractor’s offices, buildings, and other facilities necessary to commence, continue, and conclude the work. Perform final clean-up as specified in GP-4.09.

108.02 Materials

Not applicable.

108.03 Construction

Not applicable.

108.04 Measurement and Payment

Mobilization and Demobilization will not be measured but will be paid for at the Contract lump sum price. The cost of all required insurance and bonds will be incidental to this item. Payment of the Mobilization and Demobilization item will be made according to the following payment schedule.

a.25 percent of Mobilization and Demobilization, up to a maximum of 2.5 percent of the adjusted Contract amount, will be paid in the first monthly estimate after the Contractor has established the necessary facilities.
b.25 percent of Mobilization and Demobilization, up to a maximum of 2.5 percent of the adjusted Contract amount, will be paid in the second monthly estimate after the Contractor has established the necessary facilities.
c.50 percent of Mobilization and Demobilization, up to a maximum of 5 percent of the adjusted Contract amount, will be paid upon completion of 30 percent of the adjusted Contract amount.
d.Any remaining amount will be paid when the Contract has been accepted for maintenance as specified in GP-5.13. 108 — MOBILIZATION AND DEMOBILIZATION 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS The adjusted contract amount is defined as the total Contract amount less the lump sum bid for Mobilization and Demobilization. The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work. Payment of the Mobilization and Demobilization item will not be made more than once, regardless of the fact that the Contractor may have, for any reason, shut the work down on the project or moved their equipment away from the project and then back again. If the Mobilization and Demobilization item is not provided, the cost of mobilization and demobilization, including the required insurance and bonds, will be incidental to the other items specified in the Contract Documents. The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work.

Get an email when 108 changes

Maryland revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Construction and Materials, 2026 Edition. Pages 253–254 of 1,138. View official source ↗

Ask about this section

Scoped to Maryland Standard Specifications for Construction and Materials, Section 108 — Mobilization and Demobilization. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.