110.01Description
This work shall consist of all work necessary for the movement of personnel and equipment to and from the project site, except for seeding, and for the establishment and removal of all field offices, buildings, and other facilities necessary to the performance of the work.
110.02Limitations
For the purpose of payment, the mobilization portion of this work will be limited 10 to 5% of the original total contract price. The remainder of the work will be considered demobilization. The first progress estimate will include a percentage payment of the pay item for mobilization and demobilization that is equal to the lesser of 5% of the original total contract price or the c ontract lump sum price for the pay item mobilization and demobilization.
The balance of the lump sum price will be paid when the contract has been completed and accepted.
110.03Method of Measurement 20
No measurement will be made.
110.04Basis of Payment
This work will be paid for at the contract lump sum price for mobilization and demobilization.
Payment will be made under:
Pay Item Pay Unit Symbol
Mobilization and Demobilization .......................................... LS 110.04
The cost of all materials, equipment, tools, labor, transportation, operations, and incidentals required for mobilization and demobilization shall be included in the cost of this work.
If no pay item for mobilization and demobilization is shown in the Schedule of Pay Items, the cost of the work described above shall be included in the total cost of the contract, with no direct payment for the work.
MOBILIZATION AND DEMOBILIZATION in other states
Get an email when 110 changes
Indiana revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.