110.03 Record Keeping.
Should the Contractor fail to sign and return the voucher within t he 30 days, he will be declared in default in accordance with Paragraph 5 of Article 108.12. Upon receipt of the signed final estimate voucher or default action taken per Paragraph 5 of Article 108.12, the Department will issue a warrant in the amount due the Contractor. The final warrant will be issued to the Surety in cases where the Contractor is placed in default under Article 108.12 and the contract is placed in the hands of the Surety. By agreement it is hereby stipulated that the Contractor and the S urety are forever barred and estopped from any recovery of claims whatsoever against the Department under the terms of the contract.
110.01 General.
When filing a claim, the Contractor shall follow the procedures set forth in this Sect ion. Any claims by a Subcontractor must be submitted to the Contractor. The Contractor may then submit the Subcontractor’s claim on their behalf following the same procedures, or otherwise choose to accept full responsibility for the Subcontractor’s claim and any associated costs, delays, or impacts to the project.
110.02 Notice of Intent.
In any case where the Contractor deems that extra compensation is due him for additional cost not clearly covered in his contract and not ordered by the Engineer as extra work as defined herein, the Contractor shall notify the Construction Bureau in writin g, with copy to the Project Manager, of his intention to make claim for such extra compensation. The written notice of intent to file a claim shall be furnished to the Engineer prior to the time the contested work is started. Oral notification by the Contr actor and confirmed in writing by the Contractor within three calendar days, will be accepted as complying with this requirement. Electronic submission of said notification will be accepted. The written notice of intent to file a claim shall set forth the reasons the Contractor believes additional compensation will be due, the nature of cost involved and insofar as possible the total amount of the claim. The Contractor hereby agrees to waive any claim for additional compensation if notification, as provided in the foregoing, is not furnished or the Engineer is not provided facilities by the Contractor for keeping account of actual costs. Such notice by the Contractor, and the fact that the Engineer has kept account of the cost as aforesaid, is not evidence o f the validity of the claim. A separate determination of the validity of the claim will be made by the ALDOT. If the Contractor decides to rescind the notice of intent and voluntarily waive any claim for additional compensation, he shall notify the Constr uction Bureau in writing, with copy to the Project Manager. The Contractor hereby agrees to rescind the notice of intent and waive any claim for additional compensation if he accepts any alternate resolution outside the claims process, in whole or in part, such as a time extension or supplemental agreement. A copy of said alternate resolution should be sent to the Construction Bureau to formally close the claim file.
110.03 Record Keeping.
After giving the ALDOT a notice of int ent to file a claim, the Contractor shall keep daily records of all costs incurred for affected operations. These daily records shall identify each operation affected, quantities of any additional work performed, the specific locations where work is affect ed, and the potential effect to the project’s schedule such as days of delay or changes in production rates . Additionally, these records shall include details of all labor, material, and equipment applicable to affected operations. On Monday, or the first work day, of each week following the date of the notice of intent to file a claim, the Contractor shall provide the ALDOT’s Project Manager with the daily reco rds for the preceding week. The ALDOT’s Project Manager will also keep separate records for the purpose of verifying the Contractor’s records. If the Contractor's records indicate costs greater than those kept by the ALDOT, the ALDOT will notify the Contra ctor of any discrepancies . The Contractor shall have the opportunity to provide additional documentation regarding said discrepancies
110.04 Claims Process.
Refusal or failure by the Contractor to present his records shall constitute a waiver by the Contractor of his claim. To protect the integrity of the independent records maintained by ALDOT for comparison with those submitted by the Contractor , ALDOT records will not be made available to the Contractor until after ALDOT’S receipt of the Contractor’s complete records documenti ng the claim . ALDOT will retain possession of the records and provide copying facilities with the Contractor reimbursing the ALDOT for the expense of the copying. No amendment to the claim shall be made following receipt of the ALDOT’s records.
110.04 Cla ims Process.
110.05 Claim Compensation.
Board by that member impossible, difficult or unobjective. The three primary members of the Board and three alternates are appointed in the fol lowing manner. The Transportation Director appoints the primary and one alternate for one position. The Alabama Road Builders' Association appoints the primary and one alternate for a second position. The Transportation Director and the Alabama Road Builde rs' Association jointly appoint the primary and one alternate for a third position. The jointly appointed primary member will be the Board Chairman. The jointly appointed alternate will be the alternate Board Chairman. At least one Board Member must be a l icensed Professional Engineer in the State of Alabama. In the event that an alternate member is elevated to permanently replace a primary member of the Board, then a new alternate shall be appointed in the same manner as was the departing alternate. Such w ill also be the case if an alternate position is declared vacant by the Director due to death, illness, incompetence or other reasons. In the event that both the primary member and the alternate member are unable to serve or must recuse themselves due to c onflict of interest, etc., on a particular claim(s) hearing, a new member of the Board will be appointed in the same manner as the primary member to sit for that particular hearing. The ALDOT will notify the Contractor in writing of the date of the presentation and the names of the Board members. The Contractor will have ten calendar days from receipt of the letter to file with the Director, by certified mail, an objection as to the composition of the Board which specifically details the nature of the obj ection. The Director shall have final authority in determining the composition of the Board. Each Board member will be paid $60 per hour for actual time spent on reviewing the plans, specifications, and claim; attending the presentation and for preparing the report to the Director. This payment will cover all compensation and expenses.
110.05 Claim Compensation.
110.06 Required Claim Documentation.
Article 104 — 03.
110.06 Required Claim Documentation.
All claims shall be submitted in writing and shall be sufficient in detail to enable the Engineer to ascertain the basis and the amount of each claim as set forth in Article 110.03, Subarticle 110.04(a), and Subarticle 109.04(b). Al l information submitted to the Department under this Article will be used solely for analyzing and/or resolving the claim. Additionally, the following information shall be provided for all claims:
110.07 Auditing Of Claims.
110.07 Auditing Of Claims.
All claims filed against the Department shall be subject to audit by the Department’s External Auditor at any time fo llowing the filing of such claim. The audit may begin on ten days notice to the Contractor, Subcontractor, or Supplier. The Contractor, Subcontractor, or Supplier shall cooperate with the auditors. Failure of the Contractor, Subcontractor, or Supplier to m aintain and retain sufficient records to allow the Department's auditor to verify the claim shall constitute a waiver of that portion of such claim that cannot be verified and shall bar recovery thereunder. Without limiting the generality of the foregoing, and as a minimum, the auditors shall have available to them the following documents:
111.01 Goals.
SECTION 111 DISADVANTAGED BUSINESS ENTERPRISE (DBE)
111.01 Goals.
This contract contains a specific goal for the participation of certified DBEs. The goal is expressed as the percentage of the total amount of the contract that is required for DBE participation and is given in the proposal. This type of participation is defined as Race Conscious. If no specific percentage is indicated in the proposal, then any DBE firm utilized for work in this contract is defined as Race Neutral. The requirements listed in Article 111.08 and 111.09 still apply to contrac ts with no specific goal. In addition, any participation by DBEs above the required goal is also defined as Race Neutral.
111.02 Certification.
The Department maintains a current listing of certified DBE firms by categories of work. The Department’s certification extends only to the requirements of 49 CFR 26 with regard to business size, disadvantaged status, and ownership and control of business. The certification does not attest in any way to the capabilities or capacity of any business to perform s atisfactorily. DBE firms that are not on the current certification list must seek approval prior to tendering an offer on any project. Any work performed on a contract or subcontract that was executed prior to a firm obtaining DBE certification is not eligible to be counted as participation towards the goal.
111.03 Submittal of DBE Utilization Plan.
This contract will be awarded to the lowest responsible bidder. All bidders must submit within five calendar days of the letting date the following information in writing on Form OE -110 (DBE Utilization Plan) provided by the Department: • The name , certification number, and address of the DBE firm or firms; • Identify the type of firm as a contractor (including haulers), supplier, or manufacturer; • The pay item(s) a nd description of the work to be subcontracted , including the quantities, subcontract unit prices, and the unit of measurement for compensation; • If said unit of measurement for compensation differs from that of the pay item, indicate the percentage of the overall pay item quantity to which the subcontract applies ; • The total dollar amount of the work to be subcontracted to the DBE firm (this amount shall not include Bonds or Gross Receipts Tax) ; • A written commitment from the bidder to use the DBE; • A written confirmation from the DBE that it is participating in the contract as provided in the commitment. Each DBE should only be listed on one line. Additional sheets detailing the required information , such as quotes received, may be attached as needed.
111.04 Failure by Low Bidder or Contractor to Meet DBE Goal.
In the event the apparent low bidder cannot meet the DBE goal for submission of his DBE Utilization Plan, or the Contractor does not meet the DBE goal based on actual participation during construction, he must provide documentation that good faith efforts were made to meet the goal in accordance with Article 111.05, including seeking replacement DBE participation when a DBE is terminated or fails to perform.