757.03 Construction Requirements.
756.04 Method of Measurement.
The accepted amount of electrical conduit of the type installation required shall be measured by the linear foot {meter} to the nearest foot {0.1 m}.
756.05 Basis of Payment.
a.Unit Price Coverage . The accepted electrical conduit, measured as noted above, will be paid at the contract unit price bid for the type installation involved. Said unit price bid shall be full compensation for the furnishing and installation of the electrical conduit, for the specified pipe or concrete encasement, for any required backfill material, for all excavation and backfill , jacking or boring, disposal of excess material, and for all labor, tools, equipment, and incidentals necessary to complete the work.
b.Payment will be made under Item No .: 756-A ___ inch {mm} Electrical Conduit, * Lines, Type ** Installation - per linear foot {meter} * Specify number of lines in installation ** Specify type of installation PORTABLE TRAFFIC SIGNAL
757.01 Description
This Section shall cover the work of furnishing new portable traffic signals or utilizing State furnished portable traffic signals. The furnishing of new portable traffic signals includes all services and operational supplies necessary to provide a functional portable traffic signal unit. All portable traffic signals shall comply with the Manual on Uniform Traffic Control Devices (MUTCD), publications of the Institute of Transportation Engineers (ITE), the National Electrical Manufactures Association (NEMA), the National Electrical Code (NEC), and the International Municipal Signal Association (IMSA ).
757.02 Materials.
The portable traffic signal unit shall be complete with power supply, controller, structural support system, all applicable software, communications, and manuals. Portable traffic signals shall be designated according to their type bas ed on Table 4 PTS Type Designations shown in NEMA TS 5 -2017, “Standard for Portable Traffic Signal Systems (PTSS) Standard,” or latest revision.
757.03 Construction Requirements.
a.General. The Contractor shall set up and level the unit at the designated location shown on the plans and approved by the Engineer. The portable traffic signal unit shall be placed on a base consisting of a fine aggregate compacted to the satisfaction of the Engineer or alternate location approved by the Engineer. After setup and leveling, the Contractor shall secure the portable traffic signal trailer to protect from theft. If the unit is stolen, the Contractor shall be required to replace the unit at his own expense. The Contractor shall provide adequate flaggers on a 24 -hour per day, 7 day a week basis until the unit is replaced and fully operational. Signal heads positioned over a road surface shall be mounted a minimum of 17 feet from the bottom of the signal head to the top of the road surface. All other signal heads sh all be mounted at a minimum of 8 feet from the bottom of the signal head to the top of the ground surface. The Contractor shall clean, service and repair State furnished units when the Engineer determines that the portable traffic signal unit is no longe r needed, and shall return the unit to the specified location shown on plans or specified by the Engineer. The aggregate pad shall be removed and disposed of as directed by the Engineer.
b.Pay Item 757 -A. The Contractor shall furnish a new or used porta ble traffic signal unit, and shall be totally responsible for the required performance of the signal. An acceptable portable traffic signal unit shall be one of the units listed on List IV -3, WORK ZONE TRAFFIC CONTROL DEVICES, Sub -Heading “Portable Traffic Signals” of the Department’s “Materials,
757.04 Maintenance Requirements.
Sources, and Devices with Special Acceptance Requirements” manual. Information concerning this list can also be found in Sub -article 106.01(f). The Contractor shall retain ownership of the portable traffic signal unit when the Engineer determines that the signal is no longer needed.
c.Pay Item 757 -B. The Contractor shall furnish a new and fully functional portable traffic signal unit. An acceptable portable traffic signal unit shall be one of the units listed on List IV -3, WORK ZONE TRAFFIC CONTROL DEVICES, Sub -Heading “Portable Traffic Signals” of the Department’s “Materials, Sources, and Devices with Special Acceptance Requirements” manual. When the Engineer determines that the portable traffic signal unit i s no longer needed, ownership shall be transferred to the Department.
d.Pay Item 757 -C. The Contractor shall use a State furnished portable traffic signal unit. The Contractor shall pick - up the unit from the location shown on plans or specified by the Engineer. The Contractor shall clean, service and repair the portable traffic signal unit when the Engineer determines that the signal in no longer needed, and shall return the signal to the Department.
757.04 Maintenance Requirements.
The Contractor shal l keep the portable traffic signal unit in good repair at all times. Each portable traffic signal unit shall have both signal heads working in full operation at all times with red/yellow/green signal faces functioning properly. Failure, malfunction, or d amage to the unit, for any reason, shall require the Contractor to expedite the repair, or replacement, and furnish adequate flaggers or other approved means, at the Contractor’s expense, to provide a safe means for the control of traffic until the unit is put back into service. The Contractor shall perform maintenance to the portable traffic signal unit, which includes the periodic cleaning of the unit along with the repair of damage to the protective coating of the unit. Portable traffic signal unit furn ished under Pay Item 757 -B (Contractor Furnished) and Pay Item 757 - C (State furnished) shall be stored in an approved, secure storage area when not in use. The Contractor shall perform all maintenance operations recommended by the manufacturer of the porta ble traffic signal and keep complete maintenance records.
757.05 Delivery of Unit and Transfer of Title, Pay Items 757- B and 757- C.
Prior to the completion of the project, and when the Engineer determines that the portable traffic signal unit is no longer needed, the Contractor shall clean and service the unit to insure that the unit is in good operational condition and return all manuals, maintenance records and title transfer (title transfer required under Pay Item 757 -B), to the Engineer. The Eng ineer shall inspect the portable traffic signal unit to insure the unit is operational and undamaged before the Contractor delivers the unit back to the State. The Engineer shall authorize the Contractor to return the portable traffic signal unit to the specified location on the plans or specified by the Engineer, as soon as the inspection is complete.
757.04 Method of Measurement.
Measurement of portable traffic signal will be complete individual portable traffic signal unit for the type of unit furnished . There will be no overrun of this item without written permission of the Engineer.
757.05 Basis of Payment.
a.Unit Price Coverage. The portable traffic signal unit, measured as noted above, will be paid for at the contract unit prices which shall be f ull compensation for pickup and delivery of unit, installation of aggregate pad, fine aggregate for the pad, set up of unit; and providing and inputting timings of unit for the exclusive use during the project; maintenance and operation of the unit during the life of the contract; removal of the aggregate pad; and includes all equipment, tools, labor, services, supplies, and incidentals necessary to complete this item of work. The contract price for Pay Item 757 -B and 757- C shall also include the cleaning, servicing, and repair of the unit and pickup from and delivery to the designated storage location.
b.Payment will be made under Item No.: 757-A Portable Traffic Signal, Type _*_ - per Each 757-B State Retained Portable Traffic Signal, Type _*_ - per Each
757.05 Basis of Payment.
757-C State Furnished Portable Traffic Signal, Type _*_ - per Each * Specify Type (TR1 or TR2)
800.01 General.
MATERIALS SECTION 800 MATERIALS
800.01 General.
All materials used in th e work shall be new, unused material that will meet the requirements described in this Division unless the same are altered by specific requirements of any Section of these Specifications, Special Provisions , or by modifying notes on the plans. All materia ls shall also meet the requirements of applicable portions of Section 106 which will supplement the requirements of this Section. All tests shall be in accordance with the current Departmental testing schedule.
800.02 Inspection Arrangements.
a.Contractors' Notification . It shall be the duty of the Contractor to notify the Engineer of the source of the various materials required for each project. This notice shall be received sufficiently in advance of any shipment of materials so that inspection may be arranged at the producing plant if the Engineer so elects.
b.Plant Inspection . Whenever the quantity of materials warrants such an arrangement and/or it is economically advantageous to the Department, the inspection of materials at the original o r immediate source of supply will be made. However, the Department is under no obligation to the Contractor to inspect materials until it arrives at the site of the work. In general, all aggregates, soil, brick, reinforcing and structural steel, bituminous materials, timber, lumber, piling, and posts which are to become a part of the completed work will be inspected at the point of production. For timber, lumber, piling, and posts which are to be given preservation treatment, this inspection will be perform ed at the treating plant in conjunction with inspection of the treating process.
1.For lumber and timber products, the producer shall have sorted his stock and shall have separated a sufficient quantity of material to insure that all of each item for inspection is available before the Inspector is called. In the event that part of the shipment is rejected because of failure to meet the specification requirements, the producer shall furnish other stock to replace the rejected items.
2.Should the quantity of any material rejected for failure to meet specification requirements amount to 20 percent or more of the material inspected and tested at that time, the inspection operation will be suspended until the producer shall have regraded hi s stock or revised his production methods to produce material uniformly conforming with the specifications. When sampling stockpiles of aggregates, base materials, etc., the average of all samples must be within the gradation band required for the size ag gregate specified. In no case will stockpiles be acceptable if more than 20% of the total samples fall outside the gradation band. In addition, any failing sample must be within 20% of the range specified for any designated sieve.
3.In case the stock has not been properly prepared or separated before calling an Inspector, or in case of delay in replacement of rejected material, the extra inspection cost occasioned by such delay will be charged against the Contractor for whom the material is being produced and will be deducted from any sums due or which may become due the Contractor.
4.Where a Contractor's producer or jobber requests inspection of material for warehouse stock or for use in plants where stocks of materials inspected and accepted for use in h ighway construction or maintenance cannot be kept separated from materials which are to be used on other work, the cost of inspection of those materials which have been approved for highway work, but are later diverted to other uses not connected with the Department's highway construction or maintenance, will be charged to the Contractor who requested such inspections.
Source: Alabama Standard Specifications for Highway Construction, 2022 Edition. Pages 706–708 of 934.