B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
General Provisions (00100-00999)

757PORTABLE TRAFFIC SIGNAL

AL · 2022 Standard Specifications✓ Full text on BuildSpecBook pages 706–0 Save this section

Ask about Section 757

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

664

The Contractor shall retain ownership of the portable traffic signal unit when the Engineer determines that the signal is no longer needed.

(c)Pay Item 757-B.

The Contractor shall furnish a new and fully functional portable traffic signal unit. An acceptable portable traffic signal unit shall be one of the units listed on List IV-3, WORK ZONE TRAFFIC CONTROL DEVICES, Sub-Heading “Portable Traffic Signals” of the Department’s MSDSAR manual. When the Engineer determines that the portable traffic signal unit is no longer needed, ownership shall be transferred to the Department.

(d)Pay Item 757-C.

The Contractor shall use a State furnished portable traffic signal unit. The Contractor shall pick- up the unit from the location shown on plans or specified by the Engineer. The Contractor shall clean, service and repair the portable traffic signal unit when the Engineer determines that the signal in no longer needed and shall return the signal to the Department.

757.0Maintenance Requirements.

The Contractor shall keep the portable traffic signal unit in good repair at all times. Each portable traffic signal unit shall have both signal heads working in full operation at all times with red/yellow/green signal faces functioning properly. Failure, malfunction, or damage to the unit, for any reason, shall require the Contractor to expedite the repair, or replacement, and furnish adequate flaggers or other approved means, at the Contractor’s expense, to provide a safe means for the control of traffic until the unit is put back into service. The Contractor shall perform maintenance to the portable traffic signal unit, which includes the periodic cleaning of the unit along with the repair of damage to the protective coating of the unit. Portable traffic signal unit furnished under Pay Item 757-B (Contractor Furnished) and Pay Item 757- C (State furnished) shall be stored in an approved, secure storage area when not in use. The Contractor shall perform all maintenance operations recommended by the manufacturer of the portable traffic signal and keep complete maintenance records.

757.05Delivery of Unit and Transfer of Title, Pay Items 757-B and 757-C

Prior to the completion of the project, and when the Engineer determines that the portable traffic signal unit is no longer needed, the Contractor shall clean and service the unit to ensure that the unit is in good operational condition and return all manuals, maintenance records and title transfer (title transfer required under Pay Item 757-B), to the Engineer. The Engineer shall inspect the portable traffic signal unit to ensure the unit is operational and undamaged before the Contractor delivers the unit back to the State. The Engineer shall authorize the Contractor to return the portable traffic signal unit to the specified location on the plans or specified by the Engineer, as soon as the inspection is complete.

757.06Method of Measurement

Measurement of portable traffic signal will be complete individual portable traffic signal unit for the type of unit furnished. There will be no overrun of this item without written permission of the Engineer.

757.07Basis of Payment

(a)Unit Price Coverage.

The portable traffic signal unit, measured as noted above, will be paid for at the contract unit prices which shall be full compensation for pickup and delivery of unit, installation of aggregate pad, fine aggregate for the pad, set up of unit; and providing and inputting timings of unit for the exclusive use during the project; maintenance and operation of the unit during the life of the contract; removal of the aggregate pad; and includes all equipment, tools, labor, services, supplies, and incidentals necessary to complete this item of work. The contract price for Pay Item 757-B and 757-C shall also include the cleaning, servicing, and repair of the unit and pickup from and delivery to the designated storage location.

(b)Payment will be made under Item No.:

757-A Portable Traffic Signal, Type _*_ - per Each 757-B State Retained Portable Traffic Signal, Type _*_ - per Each 757-C State Furnished Portable Traffic Signal, Type _*_ - per Each * Specify Type (TR1 or TR2) MATERIALS 665

DIVISION 800 — MATERIALS — MATERIALS

800.01General

All materials used in the work shall be new, unused material that will meet the requirements described in this Division, unless the same are altered by specific requirements of any Section of these Specifications, Special Provisions, or by modifying notes on the plans. All materials shall also meet the requirements of applicable portions of Section 106 which will supplement the requirements of this Section. All tests shall be in accordance with the current Departmental testing schedule.

800.02Inspection Arrangements

(a)Contractors' Notification.

It shall be the duty of the Contractor to notify the Engineer of the source of the various materials required for each project. This notice shall be received sufficiently in advance of any shipment of materials so that inspection may be arranged at the producing plant if the Engineer so elects.

(b)Plant Inspection.

Whenever the quantity of materials warrants such an arrangement and/or it is economically advantageous to the Department, the inspection of materials at the original or immediate source of supply will be made. However, the Department is under no obligation to the Contractor to inspect materials until it arrives at the site of the work. In general, all aggregates, soil, brick, reinforcing and structural steel, bituminous materials, timber, lumber, piling, and posts which are to become a part of the completed work will be inspected at the point of production. For timber, lumber, piling, and posts which are to be given preservation treatment, this inspection will be performed at the treating plant in conjunction with inspection of the treating process.

(c)General Details.

 For lumber and timber products, the producer shall have sorted his stock and shall have separated a sufficient quantity of material to ensure that all of each item for inspection is available before the Inspector is called. In the event that part of the shipment is rejected because of failure to meet the specification requirements, the producer shall furnish other stock to replace the rejected items.  Should the quantity of any material rejected for failure to meet specification requirements amount to 20 percent or more of the material inspected and tested at that time, the inspection operation will be suspended until the producer shall have regraded his stock or revised his production methods to produce material uniformly conforming with the specifications.  When sampling stockpiles of aggregates, base materials, etc., the average of all samples must be within the gradation band required for the size aggregate specified. In no case will stockpiles be acceptable if more than 20% of the total samples fall outside the gradation band. In addition, any failing sample must be within 20% of the range specified for any designated sieve.  In case the stock has not been properly prepared or separated before calling an Inspector, or in case of delay in replacement of rejected material, the extra inspection cost occasioned by such delay will be charged against the Contractor for whom the material is being produced and will be deducted from any sums due or which may become due the Contractor.  Where a Contractor's producer or jobber requests inspection of material for warehouse stock or for use in plants where stocks of materials inspected and accepted for use in highway construction or maintenance cannot be kept separated from materials which are to be used on other work, the cost of inspection of those materials which have been approved for highway work, but are later diverted to other uses not connected with the Department's MATERIALS 666

highway construction or maintenance, will be charged to the Contractor who requested such inspections.

800.03Testing, General

Where maximum and minimum specification limits are given, it is intended and expected that materials having approximately mean values will be furnished under the respective specifications. The established allowances for variations in the determination of these values are considered in establishing the limits and no tolerances in excess of the established variation allowances will be permitted unless so specifically stated in the proposal or on the plans. Unless otherwise specified in the test procedure or material specification, all test results will be rounded off in accordance with ASTM E 29 and reported to the same number of places as the specification. Where material is fabricated of or treated with another material or any combination of materials is assembled to form a product, any or all of which are covered by these specifications, the failure of any of the components of the product to comply with the designated specifications shall be deemed sufficient cause for the rejection of the whole. The sieves used for testing materials shall be woven wire cloth conforming to ASTM E 11.

800.04Tests for Concrete Materials

Preliminary samples of fine aggregate, water, and cement shall be subject to both 7 and 28 day tests or their equivalent and acceptance based thereon. During the progress of the work, these materials may be accepted on the basis of the 7 day test, except that Type III cement may be accepted on the basis of the 3-day test.

800.05Bituminous Mixture Stability and Density Test

These tests shall conform to the current methods as described in ALDOT-307 or ALDOT-344, depending on the maximum aggregate size.

800.06Measurement of Liquid Bituminous Materials

(a)Measurement.

Actual measurement shall be in accordance with the provisions of Subarticle 109.02(a) and/or (b).

(b)Procedure.

Unless otherwise provided in the proposal form, the procedure in conjunction with all shipments in tank cars or trucks shall be as follows:

1.The producer or supplier shall furnish to the Engineer in charge of the project a shipping notice

(Form BMT-146) for each shipment, containing the following information:

a.Tank number and initials, if any.
b.Type, grade, and weight {mass} of bituminous material contained.
c.Date of Shipment.
d.Shipping Point.
e.Destination.
f.Consignee.
g.Project Number.
h.Temperature of bituminous materials, degrees Fahrenheit {Celsius}, at time truck tank was

measured. Failure to furnish data will be cause for rejecting the shipment.

2.Before each shipment of bituminous material is unloaded, the Engineer shall be given

opportunity to make such measurement as necessary to determine the net quantity of materials delivered.

3.Conversion of verified weight to gallons {mass to liters} may be used for measurement

purposes provided prior written approval is obtained from the Engineer.

800.07Soil Analysis Test

(a)Mechanical Analysis.

This test shall be performed in accordance with AASHTO T 88.

(b)Elutriation Test for Clay.

This test shall be performed in accordance with AASHTO T 88.

Referenced in this section
Sections that cite this one

Get an email when 757 changes

Alabama revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Alabama Standard Specifications for Highway Construction, 2022 Edition. Pages 706–0 of 934. View official source ↗

Ask about this section

Scoped to Alabama 2022 Standard Specifications for Highway Construction, Section 757 — PORTABLE TRAFFIC SIGNAL. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.