Division VII — Drainage Facilities
61 GENERAL
61-1 General
61-1.01 General
Section 61 includes general specifications for constructing drainage facilities.
61-1.02 Materials
Not Used
61-1.03 Construction
Not Used
61-1.04 Payment
Not Used
61-2 Culvert and Drainage Pipe Joints
61-2.01 General
61-2.01A Summary
Section 61 -2 includes specifications for con structing joint systems and couplers for culverts and drainage pipes . Joint systems and couple rs for culverts and drainage pipes are classified as standard, positive, or downdrain.
61-2.01B Definitions
shear strength : Required joint shear strength expressed as a percentage of the calculated pipe shear strength at a transverse section remote from t he joint. moment strength : Moment strength required of the joint expressed as a percentage of the calculated moment capacity of the pipe on a transverse section remote from the joint. tensile strength : Resistance to the longitudinal force that tends to sep arate adjacent pipe sections. integral joint overlap : Projection of 1 pipe barrel into another pipe barrel. sleeve joint overlap : Minimum sleeve width required to engage abutted pipe barrels. watertightness : Ability of a joint to hold water under pressure without leaking. joint: Connection point for 2 or more pipe sections.
61-2.01C Submittals
For watertight joints, submit your analysis or test results performed on representative joints proposed for installa tion. Submit a certificate of compliance for each classification of joint systems and couplers. Where field leakage testing is shown for pipe systems, submit:
61-2.01D Quality Assurance
61-2.01D(1) General
Reserved
61-2.01D(2) Quality Control
61-2.01D(2)(a) General
Reserved
61-2.01D(2)(b) Watertightness Test
Perform watertightness tests of the assembled joints. The assembled joints must pass the tests without joint leakage. The watertightness test must consist of testing the hydrostatic pressure on a joint by connecting 2 pipe sectio ns under the manufacturer's instructions. Provide suitable bulkheads within the pipe adjacent to and on either side of the joint or at the outer ends of the joined pipe sections. Do not place mortar or concrete coating, filling, or packing in addition to t hat normally required for the joint before conducting the watertightness test. After the pipe sections are fitted together with the gasket or gaskets in place, subject the assembly to a 10 -foot water pressure head above the pipe crown for 10 minutes. Moist ure or beads of water appearing on the surface of the joint are not considered leakage. Perform the test on individual joints at the manufacturer's plant. Test joint watertightness on pipe sections in straight alignment and on pipe sections deflected from straight alignment. When you test joints on pipe sections not in straight alignment, position the pipe sections to create a gap on one side of the outside pipe perimeter that is 1/2 inch wider than the gap for the pipe sections in straight alignment. If yo u use coupling bands to test the pipe sections not in straight alignment and the maximum gap on one side of the outside pipe perimeter is less than 1/2 inch wider than that for the pipe sections in straight alignment, position the coupling band and the pip e sections to provide the maximum gap.
61-2.01D(2)( c) Performance Specifications
For joint systems and couplers under section 61 -2.01D(2)( c), determine the values for joint properties by mathematical analysis or an authorized test . Joint components subject to bending forces must not be stressed beyond the minimum specified yield strength of the material as determined by using the plastic section modulus. Joint systems or couplers must:
61-2.01D(3) Field Leakage Te sting
61-2.01D(3)(a) General
Perform field leakage testing on culverts and drainage structures wherever field leakage testing is shown. Field leakage testing includes:
61-2.01D(3)(b) Exfiltration and Infiltration Testing
Exfiltration and infiltration tests must comply with ASTM C969 except:
61-2.01D(3)(c) Low -Pressure Air T est
You may use the low -pressure air test instead of the exfiltration test or the infiltration test for pipes 30 inches in nominal diameter or less. You may prewet the pipes. Test pipes f rom inlet to inlet or shorter lengths. Do not use the low -pressure air test for drainage pipes over 30 inches in nominal diameter regardless of the material type. If you use a low -pressure air test, perform the test immediately following pipe cleaning. Brace plugs and bulkheads to prevent release during the low -pressure air test. Locate gauges, air piping manifolds, and valves above the ground. Do not allow anyone to enter a manhole or inlet of a plugged pipe when it is under pressure. Equip the air test ing apparatus with a pressure release device, such as a rupture disk or a pressure relief valve, designed to relieve pressure in the pipe at 6 psi when under test. SECTION 61 GENERAL Start the test after the pressure is stabilized at or above an internal pressure of 3.5 psi greater than the average back pressure of the groundwater that could submerge the pipe. Start recording the time when the internal pressure drops to 3.5 psi. The tested portion of the pipe passes the field leakage test when the pressure drop is less than 1 psi for the time period calculated for the size and length of the pipe to be tested as shown in the following table: Minimum Test Time for Pressure Drop Nominal pipe diameter (in) Time for pressure drop (minutes/100 ft) 6 0.7 8 1.2 10 1.5 12 1.8 15 2.1 18 2.4 21 3.0 24 3.6 27 4.2 30 4.8
61-2.01D(3)(d) Other Allowable Tests
If authorized, you may test :
61-2.01D(3)(b) and 61 -2.01D(3)(c). The minimum test times for pressure drop for pipes:
3.1. 30 inches in nominal diameter and smaller must be the same as the low -pressure air test specified in section 61 -2.01D(3)(c) 3.2. 33 inches in nominal diameter must be 5.4 minutes per 100 feet 3.3. 36 inches in nominal diameter must be 6.0 minutes per 100 feet
61-2.01D(3)(e) Joints or Pi pe Section Not Passing Leakage Testing
Identify joints or pipe sections that exceed the maximum allowable leakage after you complete field leakage testing. Repair and retest the failed joints or pipe sections until they comply with the test requirements. Repair and retest the failed joints or pipe sections as specified in the repair procedures submitted under section 61 -2.01C. If the same joint fails the leakage test a second time, remove and replace the pipe sections on either side of the joint with new pi pes. Replace any pipe section that fails. Retest the replaced pipe section for leaks.
61-2.01D(3)(f) Reserved
61-2.02 Materials
Resilient joint material must be a neoprene expanded rubber or sheet rubber gasket, "O" ring rubber gasket, butyl rubber base joint sealant, or other authorized resilient material. All joints, including any connection, must be capable of transferring the required shear across the joint. Watertightness must be attained by use of an authorized durable, high -quality, resilient joint material designed to perform the intended function.
61-2.03 Construction
Not Used SECTION 61 GENERAL
61-2.04 Payment
The payment quantity for field leakage testing:
61-3 Alternative Culverts
61-3.01 General
Section 61 -3 includes specifications for constructing alternative culverts. Choose from the types of alternative culverts shown. Reinforced concrete pipe must comply with section 65. Corrugated steel pipe and pipe arches must comply with section 66. Corrugated aluminum pipe and pipe arches must comply with section 66. Corrugated polyethylene pipe must comply with section 64. Corruga ted PVC pipe with smooth interior must comply with section 64. Polypropylene dual wall pipe must comply with section 64. Structural steel plate pipe, arches, and pipe arches must comply with section 67. Structural aluminum plate pipe, arches, and pipe arch es must comply with section 67. Reinforced concrete box culverts must comply with section 51. Alternative culverts include concrete collars and concrete tees and reinforcement for connecting new pipe to existing or new facilities.
61-3.02 Materials
Concre te for the collars and tees must be minor concrete. Reinforcement for the concrete collars or tee connections must comply with section 52.
61-3.03 Construction
Not Used
61-3.04 Payment
Not Used
61-4 Alternative Slotted Pipe
61-4.01 General
Section 61 -4 includes specifications for installing alternative slotted pipe . Choose from the types of alternative slotted pipe shown. Do not mix different types of slotted pipe in the same installation. Slotted plastic pipe must comply with section 64 -3. Slotted corrugated steel pipe must comply with the specifications for slotted corrugated steel pipe in section 66 -2.
61-4.02 Materials
Not Used SECTION 61 GENERAL
61-4.03 Construction
Not Used
61-4.04 Payment
Not Used
61-5 Concrete Backfill for Pipe Trenches
61-5.01 General
61-5.01A Summary
Section 61 -5 includes specifications for placing concrete backfill in pipe trenches .
61-5.01B Definitions
Reserved
61-5.01C Submittals
If RSC is used for concrete backfill, submit the concrete mix design and test data from an authorized laboratory at least 10 days before excavating the pipe trench. The laboratory must specify the cure time required for the concrete mix to attain a 500 psi compressive strength when tested under California Test 521.
61-5.01D Quality Assurance
Reserved
61-5.02 Materials
Concrete backfill must comply with the specifications for minor concrete, except the concrete must contain at least 380 pou nds of cementitious material per cubic yard. You may use RSC for concrete backfill except:
61-5.03 Construction
For installation of plastic pipe where saturated clay, peat, or other unsuitable material is encountered immediately adjacent to the pipe trench, the material must be removed to a distance at least equal to 1/4 of the pipe diameter, but not less than 6 inche s, on each side of the pipe. Place concrete backfill in the trench against undisturbed material at the sides and bottom of the trench in a way that prevents (1) floating or shifting of the pipe and (2) voids or segregation of the concrete. Immediately remove foreign material that falls into the trench before or during placement of the concrete. Construct and compact earth plugs at the ends of the planned concrete backfill to contain the concrete within the trench where necessary. Wherever mi nor concrete is used, do not place materials on top of the concrete backfill within 8 hours of placing the concrete backfill. Wherever RSC is used, do not place materials on top of the concrete backfill before the required cure time to attain 500 psi has e lapsed. Consolidate concrete backfill using high -frequency internal vibrators. If HMA is to be placed directly on the concrete backfill, broom the surface with a heavy broom to produce a uniform rough surface.
61-5.04 Payment
The payment quantity for conc rete backfill (pipe trench) is the volume determined from the dimensions shown and the length of pipe if the limits of concrete backfill are shown. If the limits of concrete backfill are not shown, the payment quantity for concrete backfill (pipe trench) i s the volume determined as follows: SECTION 61 GENERAL
61-6 Temporary Culverts
61-6.01 General
Section 61 -6 includes specifications for constructing temporary culverts . Temporary culverts include pipe bends, wyes, tees, and other branches. Excavation, backfill, and shaped bedding must comply with section 19 -3.
61-6.02 Materials
You may install a removed, undamaged, temporary culvert in the permanent work if it complies with the specifications for the permanent culvert and it is new when installed as a temporary culvert on the project.
61-6.03 Construction
Install a size and type of temporary culvert capable of sustaining the intended load and discharging a quantity of water equivalent to the type and size of culvert shown. Obtain authorization for the strength and capacity of the culvert before its installation. Excavate and backfill the trench for a temporary culvert in a way that provides a firm, nonsettling foundation for the roadbed to be cons tructed over the culvert.
61-6.04 Payment
The payment quantity for temporary culvert:
61-7 Temporary Slotted Pipe
Reserved